Practice Exam - Planning, Design, and Construction Flashcards

1
Q

Prior to modifying the façade of a facility that is listed on the National Register, it is required to have the facility reviewed by what organization?

a. State Historic Preservation Office (SHPO)
b. American Historical Association (AHA)
c. APPA
d. Historic Buildings Association (HBA)

A

a. State Historic Preservation Office (SHPO)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The impacts of capital expansion on facilities
operations should be assessed for:
a. Best practices of peer institutions
b. Punch list, commissioning, and warranty
responsibilities
c. Quality control inspections of construction
d. Maintenance and operating budgets, staffing, and life cycle costs

A

d. Maintenance and operating budgets, staffing, and life cycle costs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A campus signage and way finding standard should include all of the following types of signage except:
a. Directional and way finding
b. Building identification
c. Regulatory and warning information
d. Student elections, events, and temporary
postings

A

d. Student elections, events, and temporary

postings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The focus on space planning and management is a smart strategy given the current tough and unpredictable times because:
a. Of the rising cost of space
b. Space is poorly managed
c. Academic space is not very well used
d. Space analysis and management provide a
framework for decision-making and utilization

A

d. Space analysis and management provide a

framework for decision-making and utilization

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Non-standard signage and exterior graphics can be the single most significant item creating a _______ on campus

a. Sense of artistic display
b. Sense of visual clutter
c. Sense of freedom from regulation
d. Sense of eclecticism

A

b. Sense of visual clutter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A Request for Proposal (RFP) for construction work refers to a submittal based on:

a. A past working relationship
b. Specific products and services
c. Qualifications, experience, and cost
d. The lowest price

A

c. Qualifications, experience, and cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A typical delivery method for facilities construction includes:

a. Just in Time (JIT)
b. Cost to Benefit Method (CBM)
c. Design/Build/Multi-prime (DBM)
d. Construction Management at Risk (CMAR)

A

d. Construction Management at Risk (CMAR)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Construction contracts typically require issuing a notice to proceed, a schedule of values, a contractor’s schedule, and:

a. Pre-construction meetings
b. Notification to the local labor pool
c. Consumer price index
d. Inflation index

A

a. Pre-construction meetings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which of the following is not considered desirable for use with plans and specifications?

a. Construction Institute specifications
b. AIA (American Institute of Architects) drawing standards
c. Master Specification
d. Government specifications

A

d. Government specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

An effective campus master plan should incorporate the institution’s utility, landscape, and sustainability plans as well as the:

a. Academic strategic plan
b. Water conservation plan
c. Future building plan
d. City or county expansion plan

A

a. Academic strategic plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Programming, inspections, scheduling, and punch lists are typical duties for:

a. Construction Managers (CM)
b. Project Managers (PM)
c. Design architects
d. Trade supervisors

A

b. Project Managers (PM)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Compliance and code enforcement are critical campus elements that should be effectively addressed by what typical campus department:

a. Security/police
b. Incident Commander
c. Risk Management/Environmental Health and Safety
d. Emergency Operations

A

c. Risk Management/Environmental Health and Safety

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Reduction of change orders on construction
contracts can be better managed by use of:
a. Schedule of Values analysis
b. Construction Management at Risk delivery method
c. Careful review of the As-Built drawings
d. None of the above

A

b. Construction Management at Risk delivery method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Some institutions are allowed to use other
construction and delivery methods besides
traditional design/bid/build. Select one such method that can save time:
a. Just in Time
b. Quick Build
c. Design-Build
d. Job order contracting

A

c. Design-Build

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Space planning standards are effective and incorporate academic space types that are referred to as:

a. CEPT codes
b. NEC codes
c. ICC codes
d. HEGIS codes

A

d. HEGIS codes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Utility master plans are critical in mapping all utilities above and below grade using current ______ technology.

a. Geographic Information System (GIS)
b. Global Positioning System (GPS)
c. Google Earth
d. Terra Serve imaging

A

a. Geographic Information System (GIS)

17
Q

The process of commissioning a new facility begins at what stage:

a. Schematic design – SD
b. Design development- DD
c. Construction documents- CD
d. Substantial completion– SC

A

a. Schematic design – SD

18
Q

Value Engineering (VE) measures for construction and projects includes consideration for:

a. Means, methods, and materials
b. Maintenance methods
c. Superior quality of materials
d. None of the above

A

a. Means, methods, and materials