PMP_Process_Domain_Brainscape Flashcards

1
Q

What is the most important output of Direct and Manage Project Work?

A

Deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What process formally accepts the completed project or phase?

A

Close Project or Phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the key output of Monitor & Control Project Work?

A

Work Performance Reports

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What’s the difference between Manage Project Knowledge and Monitor & Control Project Work?

A
  • Manage Project Knowledge focuses on capturing and sharing lessons learned.
  • Monitor & Control Project Work ensures project performance aligns with the plan.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the key output of Validate Scope?

A

Accepted Deliverables

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What process creates the Work Breakdown Structure (WBS)?

A

Create WBS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What’s the difference between Validate Scope and Control Quality?

A
  • Validate Scope: Stakeholder acceptance.
  • Control Quality: Internal quality assurance.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the key output of Develop Schedule?

A

Project Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the four types of dependencies in scheduling?

A
  1. Finish-to-Start (FS) – Most common
  2. Start-to-Start (SS)
  3. Finish-to-Finish (FF)
  4. Start-to-Finish (SF) – Rare
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What’s the key difference between Critical Path and Critical Chain?

A
  • Critical Path: Uses task durations & dependencies.
  • Critical Chain: Adds resource buffers to account for constraints.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the key output of Determine Budget?

A

Cost Baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the three types of cost estimates?

A
  1. Rough Order of Magnitude (ROM): -50% to +50%
  2. Definitive Estimate: -5% to +10%
  3. Budget Estimate: -10% to +25%
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What’s the key formula for Earned Value Management (EVM)?

A

EV = % Complete × Budget at Completion (BAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the three processes of Quality Management?

A
  1. Plan Quality Management – Define quality standards
  2. Manage Quality – Audit & process improvements
  3. Control Quality – Inspect deliverables
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the difference between Prevention Costs and Appraisal Costs?

A
  • Prevention Costs – Avoid defects (e.g., training)
  • Appraisal Costs – Detect defects (e.g., testing)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the difference between Internal and External Failure Costs?

A
  • Internal Failure Costs – Before delivery (e.g., rework)
  • External Failure Costs – After delivery (e.g., warranty claims)
17
Q

What are the key outputs of Develop Team?

A

Team Performance Assessments

18
Q

What’s the difference between RACI and RAM?

A
  • RACI – Roles & Responsibilities matrix (Responsible, Accountable, Consulted, Informed)
  • RAM – Assigns resources to project activities
19
Q

What process resolves resource shortages and conflicts?

A

Acquire Resources

20
Q

What’s the formula for communication channels?

A

n(n-1) / 2

21
Q

What is the key output of Plan Communications Management?

A

Communications Management Plan

22
Q

What is the difference between Push, Pull, and Interactive communication?

A
  • Push: Emails, reports
  • Pull: Intranet, shared drives
  • Interactive: Meetings, calls
23
Q

What is the most important output of Perform Qualitative Risk Analysis?

A

Risk Register Updates

24
Q

What is the key output of Perform Quantitative Risk Analysis?

A

Project Risk Report

25
Q

What are the four types of risk responses for negative risks (threats)?

A
  1. Avoid – Eliminate risk
  2. Mitigate – Reduce impact
  3. Transfer – Insurance or outsourcing
  4. Accept – Do nothing
26
Q

What are the four types of risk responses for positive risks (opportunities)?

A
  1. Exploit – Maximize benefits
  2. Enhance – Improve likelihood
  3. Share – Partner with another party
  4. Accept – Take advantage if it happens
27
Q

What are the three main types of contracts?

A
  1. Fixed-Price (FP) – Best for predictable work
  2. Cost-Reimbursable (CR) – Good for R&D projects
  3. Time & Materials (T&M) – Hourly or unit-based contracts
28
Q

What’s the key output of Conduct Procurements?

A

Signed Contracts

29
Q

What’s the biggest difference between Fixed-Price and Time & Materials contracts?

A
  • Fixed-Price: More risk on seller
  • T&M: More risk on buyer
30
Q

What are the key outputs of Identify Stakeholders?

A

Stakeholder Register

31
Q

What are the four types of stakeholders based on power and interest?

A
  1. High Power, High Interest – Manage closely
  2. High Power, Low Interest – Keep satisfied
  3. Low Power, High Interest – Keep informed
  4. Low Power, Low Interest – Monitor