Planning Flashcards

1
Q

Deterministic Estimates

A

AKA Point Estimates. Present a single number or amount. i.e. 36 months

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Probabilistic Estimates

A

include a range of estimates along with the associated probabilities within the range. They can be developed manually by developing a weighted average based on multiple likely outcomes OR running a simulation to develop a probability analysis of a particular outcome.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Absolute Estimates

A

Are specific information and use actual numbers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Relative Estimates

A

Are shown in comparison to other estimates. Relative estimates only have meaning within a given context.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Flow-based Estimating

A

Are developed by determining the cycle time and throughput. Cycle time = total elapsed time it takes one unit to get through a process. Throughput = number of items that can complete a process in a given amount of time. These two numbers can provide an estimate to complete a specified quantity of work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Crashing

A

Is a schedule compression method that seeks to shorten the duration for the least incremental cost. Can include adding people to activities working overtime, or paying to expedite deliveries.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Fast Tracking

A

Is a schedule compression method in which activities or tasks that are normally done in sequence are performed in parallel, at least for a portion of their duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Lead

A

A lead is where the work of a successor activity is accelerated; such as starting a successor activity before the predecessor has finished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Lag

A

A lag is a delay of a successor activity. Rather than waiting for an activity to finish before the next one starts, have the end of the successor activity finish a determined amount of time after the end of the predecessor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Mandatory Dependency

A

A relationship that is contractually required or inherent in the nature of the work. This type of dependency usually cannot be modified.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Discretionary Dependency

A

A relationship that is based on best practices or project preferences. This type of dependency may be modifiable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

External Dependency

A

A relationship between project activities and non-project activities. This type of dependency usually cannot be modified.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Internal Dependency

A

A relationship between one or more project activities. This type of dependency may be modifiable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Value

A

Value may include features, risk reduction, experimentation, or other ways of delivering protecting value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Effort Driven Activities

A

The duration can be reduced by adding people. This approach may work up to a point, after which adding people may actually extend duration (increase in time due to coordination, communication, conflict, potential rework).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Physical Resources

A

Any resource that is NOT a person. i.e. Materials, equipment, software, testing environment, licenses, etc.

17
Q

Make or Buy Analysis

A

Identifying those deliverables and services that will be developed in-house and those that will be purchased from external sources.

18
Q

PESTLE

A

Political
Economic
Socio-cultural
Technical
Legal
Environment

19
Q

TECOP

A

Technical
Environment
Commercial
Operational
Political

20
Q

VUCA

A

Volatility
Uncertainty
Complexity
Ambiguity