PjM Specific Flashcards

1
Q

Which consultants are licensed?

A

Civil engineers
Landscape Architects
Structural Engineers
MEP Engineers
Security (in some states)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Which consultants are not licensed?

A

Sustainability Consultant
Code consultant
Cost estimator
Audiovisual Consultant
Lighting Consultant
Acoustics Consultant

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

When can the contractor terminate the contract after 30 days of stopped work due to what 3 reasons?

A

If the architect has refused to issue a certificate of payment without giving a reason
If the owner has not made a payment within the time given in the contract documents
If the work was stopped due to a court order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

RFI Type 1

A

Graphic/Confirming RFI
count as 2-hour points

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

RFI Type 2

A

Coordination/Missing Information RFI
count as 5-hour points

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

RFI Type 3

A

Code/Contract Information RFI
count as 10-hour points

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Who inspects the site prior to partial occupancy?

A

the Owner, Contractor, and Architect shall jointly inspect the area to be occupied or portion of the Work to be used in order to determine and record the condition of the Work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the owner responsible for in a sustainable project?

A
  • Providing drawings, maintenance manuals, building operation costs to the architect if needed
  • Preparing appeals in connection with revoked certification
  • Ensure that the design fits in with the sustainability plan at every stage of the project
  • Complying with the authorities when dealing with ownership and operations during and after construction,
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Can an architect photograph their work?

A

The architect has the right to photograph the building for use in promotional material

If the client has not notified in writing that some or all of the property is confidential, the architect can take photographs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What should an architect keep record of during the DD phase?

A

Written record of changes made and the party initiating the change

Client’s approval of design development drawings

Regulatory agency approvals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What would a project management notebook typically include?

A

Project related contracts such as the owner-architect agreement

Job communications including meeting minutes and emails

Goal statements

Overall project budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the four major parts of a project manual?

A

bidding requirements
contracts
general and supplementary conditions
specifications

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are 3 advantages of quality circles?

A

Cost and time reductions in production
Improves trust and communication among employees and management
Improved motivation among staff

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are process based quality control systems? Use examples

A

Process-based quality control systems automate tasks so that they can be completed with little to no human input.

The following are examples of process-based quality controls:
- Using project management software
- Using financial management software
- Using clash detection in a BIM model

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Damp proofing

A

a type of moisture control applied to building walls and floors to prevent moisture from passing into the interior spaces

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Name 3 that are likely to be included in the project team for a proposal

A

Project Manager
Lead designer
Consultants such as mechanical and electrical engineers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Can the architect and consultant ever make changes to eachothers instruments of service?

A

Not without written permission from eachother

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Appraisal costs

A

Appraisal costs are associated with measuring and monitoring activities related to quality. These costs are associated with the suppliers’ and customers’ evaluation of purchased materials, processes, products, and services to ensure that they conform to specifications.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

External failure costs

A

costs occur when products or services that fail to reach design quality standards are not detected until after transfer to the customer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Internal failure costs

A

costs incurred when a product fails to meet quality standards and the failure is discovered before the product reaches customers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Prevention costs

A

Prevention costs are incurred to prevent or avoid quality problems. These costs are associated with the design, implementation, and maintenance of the quality management system. They are planned and incurred before actual operation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

GANTT chart

A

essentially a snapshot of a project. It covers both dependent as well as non-dependent milestones.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Critical Path chart

A

more specific than GANTT or milestone. It focuses on only the dependent or sequential tasks that can upset the project timeline and lead to delays in completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Milestone chart

A

This method is used for short-duration projects with relatively few tasks and fees typically under $35,000.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

assemblies cost estimate

A

more precise than the order of magnitude approach and is possible after early detailed information about project construction is defined during the design development phase. An assemblies estimate may also be referred to as a systems estimate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

unit price estimating

A

requires a greater level of detail that is not defined until after the design development phase.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

mixed use

A

A building that has multiple areas with different uses too large to be accessory is considered mixed use within the IBC §508.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

accessory use

A

An accessory use is one that is considered ancillary to the main use and occupancies and does not occupy more than 10% of the building area of the story in which it is located.

29
Q

When can a contractor request proof that the owner can pay?

A

When there is a change in the contract sum
When the contractor has a reasonable concern about the owner’s ability to pay
If the owner does not pay the contractor

30
Q

When can the architect or consultant terminate service?

A

Must give 7 days written notice

If the Owner (or architect) fails to make payments to the Architect in accordance with this Agreement, such failure shall be considered substantial nonperformance and cause for termination or, at the Architect’s option

If the Owner (or architect) suspends the Project for more than 90 cumulative days for reasons other than the fault of the Architect, the Architect may terminate this Agreement by giving not less than seven days’ written notice.

31
Q

When can the contractor terminate services?

A

The Contractor may NOT terminate any time for convenience. There are specifics that are outlined in the contract. Only the Owner has that right.

The Contractor may terminate the contract if the work has stopped for 30 days at no fault of the Contractor or Sub. Not 14 days.

The Contractor may terminate if the Owner delays or interrupts the Work for more than 100% of the total days scheduled for completion or 120 days in any 365-day period, whichever is less.

The Contractor may terminate if an Architect has not issued a Certificate for Payment within the required timeline and has not provided information or evidence as to why.

32
Q

When can the owner terminate work?

A

The Owner may terminate this Agreement upon not less than seven days’ written notice to the Architect for the Owner’s convenience and without cause.

In the event of termination not the fault of the Architect, the Architect shall be compensated for services performed prior to termination, together with Reimbursable Expenses then due and all Termination Expenses as defined in Section 9.7.

Termination Expenses are in addition to compensation for the Architect’s services and include expenses directly attributable to termination for which the Architect is not otherwise compensated, plus an amount for the Architect’s anticipated profit on the value of the services not performed by the Architect.

33
Q

What 2 things happen for final completion?

A

the Contractor has fully performed the Contract except for the Contractor’s responsibility to correct Work

a final Certificate for Payment has been issued by the Architect

34
Q

What should an architect do on site visits?

A

Check for defects and deficiencies
Look for any differences in the construction when checked against the contract documents and/or shop drawings
Keep the owner informed of ongoing work at the site

35
Q

Who is a contractor responsible for safeguarding the following against injury and damage?

A

His or her employees
The work
Neighbors and others affected by the work
Neighboring property

36
Q

4 things typically found in work plans

A

Scope of services
Breakdown of services and tasks
Dependencies
Total fee of project

37
Q

Production of the following documents are the responsibility of the owner:

A

Site survey
Written legal description of the site
Boundaries and contours of the site
Percolation tests and soil bearing values

38
Q

IRC (International Residential Code)

A

a stand-alone document where no other code or reference is needed (unless listed as a reference within the IRC).

39
Q

top down approach

A

Estimates for finding fees for direct labor are based on historical data
The total fee is estimated using rules of thumb
Fees allocated for various stages will depend on the type of delivery method
Top-down approach takes less time and decisions can be taken faster
The top-down approach is more effective when the project cost is can only be roughly estimated
A combination of top down and bottom up approach would yield more accurate estimates

40
Q

At what number of employees do you need to file an EEO report?

A

50
“The EEO-1 Report is a compliance survey mandated by federal statute and regulations. The survey requires company employment data to be categorized by race/ethnicity, gender and job category.”

41
Q

All employers must comply with:

A

Equal Pay Act
OSHA
I-9 Employee Eligibility Verification
Fair Labor Standards Act (FLSA)
Personnel Files
Health Insurance Portability and Accountability Act (HIPPA)
American Recovery and Reinvestment Act (ARRA) of 2009
Employee Retirement Income Security Act (ERISA)

42
Q

Comply with these 3 once you reach 15 employees:

A

Consolidated Omnibus Budget Reconciliation Act of 1986 (COBRA)
Civil Rights Act, Title VII
Americans with Disabilities Act (ADA)

43
Q

Employers with 20+ employees must additionally comply with (1)

A

Age Discrimination in Employment Act (ADEA)

44
Q

Employers with 50+ employees must additionally comply with (4)

A

Family Medical Leave Act (FMLA)
Affirmative Action Plan
EEO Reporting
Annual Report (Form 5500)

45
Q

Masterformat

A

developed first, list be material, more commonly used

46
Q

Uniformat

A

list by system, works well with BIM

47
Q

What table lists the required fire separation of occupancies?

A

508.4

48
Q

1 acre

A

43,560 sf

49
Q

When does a CM as constructor price the GMP set?

A

off of DD drawings

50
Q

Can the owner use the instruments of service if the architect terminates for cause?

A

No

51
Q

Can the owner use the instruments of service if the owner terminates for cause?

A

Yes

52
Q

Can the owner use the instruments of service if the owner terminates for convenience?

A

Yes, but must indemnify the architect

53
Q

Architect’s Supplemental Instructions (ASI)

A

minor changes to work that don’t change cost or scope or schedule

54
Q

metal pipes vs plastic

A

Metal piping has more friction (bad), but more thermal expansion (good)

55
Q

When is the proper time for a mandatory code review

A

after CDs and before bidding

56
Q

Who reviews the application for payment in design build?

A

owner

57
Q

1 acre

A

43,560 sf

58
Q

After how long of the Owner suspending work can the Architect terminate the agreement?

A

90 days

59
Q

Name 3 causes of scope creep

A

The architect working on changes to a drawing that have been suggested by the client after approval

Employees working extra hours on presentation quality after all the work on construction drawings is completed

Not checking whether the work being done is what was contracted

60
Q

How many days does the architect have to relay info from Owner to consultant?

A

7 days

61
Q

What is meant by a waiver of subrogation in an owner-architect contract?

A

A waiver of subrogation means that the architect and the owner cannot sue each other for items covered by their property insurances.

62
Q

What are some consequences of shortening a project’s schedule?

A

-Higher costs of construction from increased man-hours; if the design schedule is shortened this may also result in increased oversights that could result in construction errors
-Higher costs of design from increased man-hours
-Lower quality project from shortening the time-frame but NOT increasing man-hours spent on the project

62
Q

specification writing

A

Should reflect the level of quality expected
Must comply with codes
Must be up to date and technically accurate

63
Q

When creating a hybrid fee structure for a project, what is the ideal structure for each phase of the project if trying to appease both Owner and Architect?

A

SD - Hourly (because it will encourage the owner to be decisive)

DD & CD - Fixed Fee (Shows the architect will be efficient)

CA - Hourly (Because its is difficult for the arch to predict construction changes)

% of Const Cost - bad for the arch because true const costs are hard to assess

GMP & Lump Sum - same as fixed fee, but typically applied to contractor fees.

64
Q

The speed at which fire extends along the surface of a material is a measure of which term?

A

Flame Spread Index

65
Q

What indicates the amount of smoke given off when a tested material is burned?

A

Smoke Developed Index

66
Q

What indicates how much heat energy a material will add to a fire when burned?

A

Fuel Contributed Rating

67
Q
A