PI Planning Flashcards
Two Inputs for PI Planning:
Vision and Top 10 Features
Outputs of PI Planning
Program Board
Team and Program PI Objectives
True or False: Features are implemented by Stories
True
State of the Business occurs on which day of PI Planning
Day 1 (activity #1)
When does the Product/Solution (vision and prioritized features) get revealed during PI Planning?
Day 1 (activity 2)
When would these activities occur during PI Planning: Planning Context and Lunch Team Breakouts Draft Plan Review Management Review and Problem solving
Day 1
Which day of PI Planning do these activities occur on: Planning adjustments Team Breakouts Final plan review and lunch Program Risks PI Confidence Vote Plan Rework if necessary Planning Retrospective and moving forward
Day 2
Who has content authority to make decisions at the user story level?
Product owner
Who has the responsible to manage the timebox, the dependencies, and the ambiguities?
The Scrum Master
Who is responsible to define user stories, plan them into the Iteration, and work out interdependencies with other teams.
Agile Team
Create alignment with PI ________
Objectives
______ _______are planned and aren’t just extra things to do just in case you have time.
Uncommitted Objectives
If the team has low confidence in meeting a PI objective it should be moved to ______
Uncommitted
If an ________has many unknowns, consider moving it
to uncommitted and put in early spikes
objective
Uncommitted objectives count when calculating _______
load
Establish __________ by looking at the average output of the last Iterations.
Velocity