What is the maximum weight of steel joist bridging that can be hoisted?
757.e.3 : 1000 lbs.
Each employee on the face of formwork or reinforcing steel shoul be protected from falling with each of the following precaustions except.
501.b.5 :
When an employer uses fall protection methods that are different than normally used standards, they must_____?
502.k.1 : be site specific.
When 6’ or greater excavtions ar blocked from view by buildign or plan growth _____________ is required?
501.b.7. : Fall Protection.
How many gallons fo flmamable liquid in an non-approved room or storage areas?
152.b.1 : 25’
A hoist tower located inside a structure shall be?
552.c.2 : enclosed on all 4 sides.
How often should atmospheric testign be done in a dn around a 5’ excavation trench in a confied space?
651.g.1.i : Before employ enters.
Which of the following equipment is for the purpose fo fall protection?
501.b.1 : Harness
What soil classification rating is given to sand?
Sub P . App A (b) : Type “C”
What tools requires guards both above and below?
304.d : Circular Saw
Lumber piles shall not exceed 20 feet in height provided that lumber to be handled manually is not stacked more than _________ feet high?
205.b.8.iv : 16’
An employer is responsible for all of the following safety and training education except _______?
.21.all : CPR