NASCLA - Additional Questions Flashcards

1
Q

A ramp with 1:12 slope, will travel how far.

A

30 feet 09IBC 1010.4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

30 Rooms in a motel, how many handicap spaces are required?

A

2 : 09 IBC 1106.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What would be the min/max circle dimension in a bathroom for it to be handicap accessible?

A

60, ACC 304.3.1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Min/Max height of a fire alarm pull station.

A

42/48, 09IBC 907.4.2.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

20 Room Motel – How Many Fire Alarm Appliances Devices are Required?

A

2, 09IBC T 907.5.2.3.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

During which portion of a project would a Steel Joist Delivery most likely present a concern?

A

Last third ?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A Min/Max sidewalk width during construction:

A

4ft, 09IBC IBC 3306.2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When planning to control work site traffic, what should be considered?

A

Construction site itself, “Construction Jobsite Management” pg 154

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A theater must have emergency standby power for how long?

A

90 min, 09IBC 1006.3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which contract type best matches the progress payment to % of completion:

A

Cost Plus, “Construction Jobsite Management” pg 183

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

In estimating, to justify additional costs for security, all should be considered Except:

A

Ordering in large quantities to save on delivery costs, ?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

If working outside near a 50KV power line, how far should you stay from the line?

A

10 Feet, OSHA 1926.1408 Power Line Safety Table (new) old ref 1926.550 (a)(15)(i)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A door jamb should be installed at what point?

A

After rough opening is built, “Carpentry” pg 618

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

If there’s a rough opening for a door, what should be installed first?

A

Jambs, “Carpentry” pg 618

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Where there’s a wall, step flashing should be installed:

A

Under the shingles, Roofing Pg. 100

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How should door stops be installed?

A

Lock side first, “Carpentry” pg 620

17
Q

When you have wet soil near an underground utility line, what equipment should you use?

A

Tracked backhoe, P&E pg 170