During the project closeout process, what step precedes final payment and release of reatainages?
- Contractor completes contract requirements.
A traditional contract delivery system is comprised of which three parties?
- The owner, the architect, and the contractor.
Who does the Project Engineer usually report directly to on the job-site?
- Project Manager.
Under the American Arbitraiton Associations’ Construction Industry Arbirtation Rules, claims should be less than what dollar amount for a 60-day “Fast Track” dispute?
- $50K.
Who is the principal manager of the work, on the job-site. they oversee the subs, and supervises the GC’s own labor forces?
- Superintendent.
Which one of the following is not a necessary step in a right-to-know (MSDS) program?
- Inform key employees about the hazard communication program. This is the answer because it’s suppose to be all employees.
What percent is usually withheld by owners for retainage purposes on a contract?
- 10%.
The ____________ is responsible for inspections to determine the dates for substantial completion and final completion.
- Architect.