Management of Construction Projects Flashcards

1
Q

Who notifies the owner that all deficiencies on the punch list have been corrected?

A
  1. Architect.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The most imporant aspect of the certificate of occupancy is the inspection by who and for what reason?

A
  1. Fire Marshall review for life safety issues.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

According to AIA document G704-2000 what is the correct definition of Substantial Completion?

A
  1. It is the stage in the progress of work when the work or designated portion is sufficiently complete in accordance with the contract documents so that the owner can occupy or utilize the work for its inteded use.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Who’s responsibility is it to finacially close out the project with both the owner and the subcontractors?

A
  1. Project Manager.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The best person to mark up the as-built drawings is?

A
  1. Foreman & Assistant Superintendent.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

All of the following are major phases of a construction project, except?

A

1-3. Project Pre-Analysis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Who is responsible for reviewing subcontractor invoices and requests for payment?

A
  1. Project Engineer.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Who is responsible for preparing daily time sheets for all supervised personnel?

A
  1. Foreman
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the CSI Division 2 Master Format for code for piles, caissons, and cofferdams?

A
  1. 02350.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

A typical constuciton contract consist fo five documents. Which one of the following is not considered a contact document?

A
  1. Invitation to bid.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which of the following is a list of all the activities that must be performed to complete a project?

A
  1. WBS (Work Breakdown Structure).
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What represents the flexibility available to schedule activiteis not on the critical path without delaying the oveall compltion of the project?

A
  1. Activity Float.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Whenever possible, who should be responsible for developing the estimate?

A
  1. Project Manager and Superintendent.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the common waste factor for framing lumber during cost estimating?

A
  1. 10%
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What type of contract best describes this scenario? Owners may choose not to pay contractors for materials stored on the project site but wait until the materials are incorporated into the project.

A
  1. Fixed Price Contract.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which one of the following is the correct definition for Final Lien Release?

A
  1. A lien release issued by the contractor to the owner or by a subcontractor to the general contractor at the completion of a project indicating that all payments have been made and that no liens will be placed on the completed project.