Handling & Erection of Steel Joists Flashcards

1
Q

What is the maximum depth of an open web joist?

A
  1. 30”
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the standard bearing depth of open web steel joists?

A
  1. 2 1/2”
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

In an open web joist designation of 18K7. The “7” indicates the _____of the joist.

A
  1. Chord Section.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the depth at midspan for a steel joist designated as 42G30N12K?

A
  1. 42”.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The proper method used to unload steel bar joist when possible is.________

A
  1. By the Bundle.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Steel joists should be stored on a job site.______

A
  1. Upside down in a vertical position.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

It is imperative that a Joist Girder be placed._______

A
  1. as indicated by the tag end.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Joist Girders are primary structure items that are supported (normally) by. ______?

A
  1. Columns.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When steel joists bear on and are supported by steel girders, the joist.______

A
  1. Must be placed at top chord panel points.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Steel joist girders may be secured by welding or by use of. _______

A
  1. Two 3/4” bolts.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

For a 33’-60’ long steel joist, the hoist cable should not be removed until _________?

A
  1. A row of bolted diagonal bridging is installed near the mid-span.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Erecting a 42’ long joist, what requirement must be met before slacking the hoist line?

A
  1. Center row of bridging be installed.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A _______ indicates that the bar joist are not installed straight lengthwise.

A
  1. Sweep.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

_______________ is the correct method of securing a square end joist.

A
  1. Right side up so that the joist will bow up at the mid-span.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A row of bottom chord bridging is required near each end of the joist. _________

A
  1. When uplift forces are design consideration.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Construction loads placed on steel joists only after joist’s are. _________

A
  1. Properly bridged.
17
Q

Horizontal bridging shall be lapped a minmum of how many inches. ________

A
  1. 2”.
18
Q

The approximate camber in a 60’ longspan joist is. ________.

A
  1. 1 1/2”.
19
Q

Before securing, square ended bar joists should ___________.

A
  1. Restrained and Stabilized.
20
Q

With k-series joist, securing plates should not be less than _____wide.

A
  1. 6”.
21
Q

K-series joist bear on columns not less than ____ over masonry or concrete support.

A
  1. 4”
22
Q

What is the minimum number of bridging rows for a k-series joist with a chord size of #8 and a span of 38’ to be used in a two-story building? _____

A
  1. Three Rows.