OM CH: 9 Flashcards

1
Q

Exception Messages

A

Reschedule in
Reschedule out
Planned order due for release
Parameter violation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Reschedule in

A

(if the available balance becomes negative, because the scheduled receipt is too late. Like it has to be put a week or two earlier).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Reschedule out

A

(if the available balance is enough to cover gross requirements. It does not become negative but there is a scheduled receipt which is not needed yet.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Planned order due for release

A

(is a shortage can not be fixed, because lead time is too much and order is required earlier.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Parameter violation

A

If the MRP schedule does not play by the rules of the game

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

System nervousness

A

extremely variable demand in MPS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Two ways to avoid system nervousness

A
  1. Time fences: you block information for certain periods of the MRP schedule
  2. Pegging: look for cause in BOM
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

available-to-promise

A

room to accept more customer orders.

Like MPS is 40 for 3 periods but only 37 items were ordered so far. 3 = available-to-promise

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Bull-whip effect (Forrester effect)

A

small order changes from the customer to the producer cause big variation the other way around.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

downstream demand

A

demand from the consumers. Consumers are downstream. Producers are upstream.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Lumpy-demand effect

A

ROP systems are not suitable for high unexpected demand

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is aggregate planning for and what is another word for it?

A

For planning the medium term.
It is above the MPS BOM and MRP
Another word is Sales and Operations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Disaggregation

A

planning from medium or long term to short term

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The low-level code

A

The low-level code represents the lowest level of the item in any current, job, or production schedule bill of material (BOM). A low-level code of 0 indicates that the item is an end item (finished good) and is not a subcomponent of another item.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

MRP

A

Material Requirement Planning.

Determines the number of products we need for all products of the BOM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly