how many working days is the interval between PM service inspection for NCF equipment?
40
what provides an opportunity to document that the crew leader has demonstrated the capability to carry out assigned projects?
RDE
who is responsible for developing an aggressive QC plan for each project?
Crewleader
what is the most common source of informal training?
OJT
What is responsible for inspection and surveillance of ongoing Seabee projects?
FEAD
A utility interruption request form should be submitted to ops at least how many weeks in advance of required outage?
2 weeks
What is the most important phase of project planning?
Material take off
How often does the battalion Receive a PSR/PCR showing the status of all project materials?
Monthly
Materials should only requestioned that you will need over what tine frame?
two weeks
What form is all material requestioned on?
NAVSUP Form 1250-1
For requestion materials that have to be obtained from conus locations, allow at least 60 days for normal requisitions and how many days for long lead items?
120 days
when a job is completed, all remaining materials must be offers to the customer. Materials the customer does not want are stored in MLO for how many months?
6 months
what document identifies structures and supporting utilities of the navy ABFC?
FPG
What is defined as a grouping of personnel and material that has a specific function or mission at an advanced base?
Component
Components are usually ordered only under a mobilization situation and requested through whom?
CNO
To meet requirements for contingency support of the naval task force and the fleet marine task force, PHIBCBs and CBUs must be able to redeploy within three and how many days?
6
During the first 30 days after return to homeport, Each NMCB must be capable of deploying an air detachment within how many hours?/
48
While deployed, NMCBs should be able to redeploy within how many days?
6