CONSTRUCTION ESTIMATING EDITION; CHAPTER 4, 5 Flashcards

1
Q

Detailed labor estimates are used to determine?

A

the number of direct labor man-days and trade skill requirements
for a construction project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Only direct labor man-days are reflected in a ____ labor estimate.

A

Projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Direct Labor?

A

includes all man-days expended directly on an assigned construction task, either in the field
or in shops, that contribute directly to the completion of the project. This does not include administrative
time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Indirect Labor?

A

Includes all labor required to support construction tasking that does not contribute directly
to the completion of a project. (e.g., coordinating with other crews and maintaining tools). Although necessary to the project, it does not
directly contribute to the end product.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Overhead Labor?

A

includes all labor not considered to be productive labor, since it does not contribute
directly or indirectly to the project. It includes all labor that must be performed, regardless of the assigned
mission (e.g., administrative).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A man-day is a unit of work performed by one person in?

A

8 hours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

LABOR ESTIMATE?

A

The labor estimate is created using construction work elements, both work items and material items, identified in
the project’s material estimate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

how many labor categories are used by military engineers?

A

3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

project crew leaders use the information from which estimates to develop a projects construction activity summary sheets?

A

initial labor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

a critical factor in producing an accurate labor estimate is determining which rate?

A

production/work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

what are used to determine the number of direct labor man days and trade skill requirements for a construction project?

A

labor estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

direct labor requirements are broken into what?

A

Task of work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

which type of work includes installing millwork, door and window frames, trim, kitchen cabinets, wooden stairs, closet units, and finish walls?

A

finish carpentry

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

what division includes doors, frames, windows, glass, and hardware?

A

Division 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

what division includes a variety of interior work work items gypsum boards, plaster construction, tile, acoustical ceilings, wood, and flooring?

A

Division 9

How well did you know this?
1
Not at all
2
3
4
5
Perfectly