What s a stakeholder
A
Anyone affected by the project or who maybe be in a position to to influence it
2
Q
Describing stakeholder responsibilities using RACI
A
BA- mainly responsible for things but consulted about business case
PM- mainly accountable for most things which BAs are responsible for but responsible for usiness case and project indication document
Domain expert- consulted about everything
Business actor- consulted about everything
Senior user- consulted about everything
Project sponsor - accountable for business case and project initiation document, informed about everything else