Module 4 Flashcards

1
Q

Payback period =

A

Time taken to recover initial outlay (recorded as X years, Y months)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Payback period advantages (2)

A
  • Good initial screening tool

- Easy to calculate and understand

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Payback period disadvantages (2)

A
  • Ignores cashflows after the payback period

- Ignores the time value of money (no discounting of cash flows)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Accounting rate of return =

A

Expressing the average annual cashflows compared to the average capital investment as a %

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

ARR formula

A

Average annual profits / Average capital investment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Average annual profits =

A

Average pre tax cash flows less annual depreciation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Average capital investment =

A

1/2 x (cost + residual value)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Accounting rate of return advantage

A

Simple to understand

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Accounting rate of return disadvantages (3)

A
  • Can’t meaningfully compare to cost of capital
  • Ignores the time value of money
  • Ignores the life of the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Net Present Value (NPV) =

A

Discounting cashflows to their present value using WACC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

If NPV > 0

A

Accept

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

If NPV < 0

A

Reject

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

NPV advantages (3)

A
  • Easy to calculate
  • Includes the time value of money
  • Considers all relevant cash flows
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Internal rate of return (IRR)

A

Discount rate that gives us NPV = 0 as a percentage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

If IRR > Cost of capital

A

Accept

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

If IRR < Cost of capital

A

Reject

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

IRR disadvantages (3)

A
  • Can be possible to get more than one IRR
  • Doesn’t provide the magnitude of the increase in wealth from the project (ignores the scale of any project)
  • Can prove misleading where projects are mutually exclusive or if capital is rationed
18
Q

Cost of preference shares =

A

% preference share / market value

19
Q

Disadvantages with WACC (2)

A
  • Difficult to estimate for unlisted companies

- Not possible to calculate for government organisations

20
Q

Only correct to use the WACC as the discount rate in NPV analysis if (3)

A
  • Project being assessed is small relative to the business
  • Existing capital structure will be maintained
  • Project has same risk profile as rest of business
21
Q

NPV is superior method of investment appraisal because

A

It measures the addition the shareholder’s wealth of accepting a new project

22
Q

Relevant cash flows

A

Those cash flows affected by the decision to invest

23
Q

Relevant cash flows > sunk costs

24
Q

Relevant cash flows > opportunity costs

A

Include the lost contribution

25
Relevant cash flows > overhead costs
Additional overheads > include | Central/ arbitrarily apportioned > exclude
26
Relevant cash flows > Materials
If replaced > replacement cost Not replaced > cost = 0 If could have been sold > lost revenue = cost`
27
Relevant cash flows > Labour
Idle > cost = 0 Full capacity > cost = contribution lost on work they had to stop doing Hired specifically for project > cost = salary paid
28
Relevant cash flows > Machinery
Purchased outright > cost included | Acquired through loan/ lease > ignore interest payments
29
Relevant cash flows > Working capital (stock)
Cash tied up (outflow) -> Cash release (inflow) -> Net effect (for NPV)
30
Assumption > timing of cash flows
Unless told otherwise, assume all cash flows received at end of the year
31
Two impacts of inflation on NPV
- Cash flows rise > project more attractive | - Cost of capital (discount rate) rises > project less attractive
32
Inflate from...
Following period eg if provided with Year 0/ current year prices, inflate from year 1
33
Real terms/ current prices
Ignore inflation
34
Nominal market
Include inflation
35
If one rate of inflation
Ignore inflation > use real cash flows + real discount rate
36
If multiple rates of inflation
Cash flows and cost of capital must be inflated > use nominal cash flows and nominal discount rate
37
Complications arising when foreign projects are assessed (3)
- Discount rates - Exchange rates - Inflation rates
38
Approach to international investment appraisal > Approach 1
1) Forecast projected cash flows 2) Calculate expected forecast exchange rate 3) Convert foreign cash flows to sterling 4) Discount at sterling cost of capital
39
Approach to international investment appraisal > Approach 2
1) Forecast projected cash flows 2) Estimate foreign adjusted discount rate 3) Discount foreign cash flows at foreign discount rate 4) Convert NPV into sterling at spot rate
40
Sensitivity analysis variables (5)
- Selling price - Sales volume - Cost of capital - Initial cost - Operating costs
41
Weakness of sensitivity analysis
- Can only have one variable > unrealistic
42
Simulation
Generates the distributions of the NPVs for each project > the wider the distributions, the higher the risk