Module 3 - Process Walkthrough Flashcards

1
Q

What is an exception ?

A

A situation where the project is forecast to deviate beyond the tolerance levels

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Who provides the project mandate for the project ?

A

Corporate, Programme management or the customer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Which process is triggered by the project mandate ?

A

Starting up a project process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

During which process is the project brief created ?

A

Starting up a project process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When is the outline business case produced ?

A

Starting up a project process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

When is the business case produced ?

A

Initiating a project process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How often is the business case updated ?

A

At every stage boundary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When is the communication management approach created ?

A

Initiating a project process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the communication management approach ?

A

Guideline for how communication the project will be executed, both with internal and external stakeholders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What management products are produced during the SU process ?

A

ISP
Product description
Project brief
Project product description

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What management products are produced during the IP process ?

A

BMA
PID
Business case
Change control approach
Communication management approach
Quality management approach
Risk management approach

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

List the processes in PRINCE2

A

Starting up a project process
Initiating a project process
Controlling a stage process
Managing product delivery process
Managing stage boundary process
Closing a project process
Directing a project process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Who provides the project mandate ?

A

Corporate, programme management or customer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How many PRINCE2 Processes are there ?

A

7

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which PRINCE2 Process could span for multiple stages ?

A

Directing a project process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

In what process is the end project report created ?

A

Closing a project process

17
Q

Who executes the controlling a stage process ?

A

Project manager

18
Q

Which process is executed during a management stage to deal with the day to day management of the stage ?

A

Controlling a stage

19
Q

Whens the end stage report created ?

A

Managing a stage boundary process

20
Q

What is the PID ?

A

collection of components, each activity in the the IP process produces components of the PID

21
Q

True or False ? he outputs from the MSB and IP processes are what the project board needs to decide whether they should go ahead with a project

A

True

22
Q

What is a work package ?

A

a way for the project manager to group work activities together and assign work to a team or team manager to produce one or more product

23
Q

What is a highlight report ?

A

A report updating the project board on the stage progress

24
Q

What is a checkpoint report ?

A

Used by a team manager to report to the project manager between CS process and MPD process

25
Q

What are the five activities in directing a project process

A

Authorise initiation
Authorise the project
Authorise a stage or exception plan
Give ad hoc direction
Authorise project closure

26
Q

What does the directing a project process need to authorise initiation ?

A

Project brief and iSP

27
Q

What does the directing a project process need to authorise the project ?

A

PID and BMA for first checkpoint
SP and ESR for second checkpoint