Module 3 - Process Walkthrough Flashcards
What is an exception ?
A situation where the project is forecast to deviate beyond the tolerance levels
Who provides the project mandate for the project ?
Corporate, Programme management or the customer
Which process is triggered by the project mandate ?
Starting up a project process
During which process is the project brief created ?
Starting up a project process
When is the outline business case produced ?
Starting up a project process
When is the business case produced ?
Initiating a project process
How often is the business case updated ?
At every stage boundary
When is the communication management approach created ?
Initiating a project process
What is the communication management approach ?
Guideline for how communication the project will be executed, both with internal and external stakeholders
What management products are produced during the SU process ?
ISP
Product description
Project brief
Project product description
What management products are produced during the IP process ?
BMA
PID
Business case
Change control approach
Communication management approach
Quality management approach
Risk management approach
List the processes in PRINCE2
Starting up a project process
Initiating a project process
Controlling a stage process
Managing product delivery process
Managing stage boundary process
Closing a project process
Directing a project process
Who provides the project mandate ?
Corporate, programme management or customer
How many PRINCE2 Processes are there ?
7
Which PRINCE2 Process could span for multiple stages ?
Directing a project process