material requirements planning Flashcards

1
Q

Material requirements planning (MRP)

A

the logic for determining the number of parts, components, and materials needed to produce a product

MRP is a logical, easily understandable approach to the problem of determining the number of parts, components and materials needed to produce each end item. MRP also provides the schedule specifying when each of htese items should be ordered and produced

MRP is based on dependent demand. Dependent demand is caused by the demand for a higher level item

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Master production scheduling

A

generallly, the master production schedule deals with end items and is a major input to the MRP process. IF the end item is quite large or quite expensive, however, the master schedule may schedule major subaseemblies or components instead

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

To ensure good master scheduling, the master scheduler (the human being) must:

A

include all demands from product sales, warehouse replenishment, spares and interplant requirements

never lose sight of the aggregate plan

Be involved with customer order promising

Be visible to all levels of management

Objectively trade off manufacturing, marketing and engineering conflicts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Master production schedule (MPS)

A

a time phased plan specifying how many and when the firm plans to build each item

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Time fences

A

periods of having some specified level of opportunity for the customer to make changes

E.g. are frozen (no change), slushy, liquid (change allowed)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Available to promise

A

a feature of MRP systems that identifies the difference between the number of units currently included in the master schedule and the actual (firm) customer orders

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

kBill of materials

A

the complete product description, listing the materials, parts and ocmponents, and also the sequence in which the product is created

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Modular bill of materials

A

the term for a buildable item that can be produced and stocked as subassembly. It is also a standard item with no options within the module

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Super bill

A

of materials includes items with fractional options

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Low level coding

A

placing all identical items at the same level

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Inventory records

A

The MRP program accesses the status segment of the record according to specific time periods. Theres records are accesssed as needed during program run

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Net change system

A

an MRP system that calculates the impact of a change in the MRP data

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Four lot sizing techniques

A

Lot for lot

Economic order quantity

least total cost

least unit cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Lot sizes

A

the part quanitties issued in the planned order receipt and planned order release sections of an MRP schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Lot for lot (most common technique)

A

Sets planned order to exactly match the net requirements

Produces exactly what is needed each week with no inventory carried over into future periods

Minimizes carrying costs

Does not take into account setup costs or capacity limitations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Economic order quantity

A

An EOQ model eiher fairly constant demand must exist or safety stock must be kept to provide for demand variabliilty

Qopt = sqr(2ds/h)

17
Q

least unit cost method

A

is a dynamic lot sizing technique that calculates the order quantity by comparing the carrying cost and the setup (or ordering) cost for various lot sizes and then selects the lot in which thesea re most near equal

18
Q

Least unit cost

A

the least unit cost method is a dynamic lot sizing technique that adds ordering and inventory carrying cost for each trial lot size and divides the number of units in each lot size, picking the lot size with the lowest unit cost

19
Q

Choosing the best lot size

A

the advantage of the least unit cost method is that it is a more complete analysis and wuld take into account ordering or setup costs that might change as the order siize increases. If the ordering or setup costs remain constant, the lowest total cost method is more attractive because it is simpler and easier to cmopute yet it would be just as accurate under that restriction

20
Q
A