Lecture 2 (3) Flashcards
Assembly line balancing
- Specify the sequential relationships among tasks using a precedence diagram
- Determine the required workstation cycle time
C = Production time per day/required outper per day (in units)
- Determine the theoretical minimum number of workstations
Nt = Sum of task times (T)/ Cycle time (C)
- Select a primary rule to assign task to workstations and a secondary rule to break ties
- Assing tasks (one at a time) to the first workstation unitil no more tasks can be added (due to cycle time or sequencing constraints) Repeat for all subsequent workstations until all tasks are assigned
- Evaluate the efficiency of the balance
Efficiency = Sum of task times (T)/ Actual number of workstations (Na) * Workstation cycle time (C)
- If efficiency is unsatisfactory, rebalance using a different rule
Workstation cycle time formula
C = production time per day/required output per day
The maximum duration a job takes for completion at each workstation
Theoretical number of workstations Nt
Nt = sum of task times (T)/cycle time (C)
Efficiency of the balance formula (assembly line balancing)
Efficiency = Sum of task times (T)/Actual number of workstations (Na) * WOrkstation cycle time (C)
Primary rule of prioritizing tasks
Prioritize tasks based on the largest number of following tasks
Secondary rule: Prioritize tasks in order of longest task time
Break-even analysis
A standard approach to choosing among alternative processes or equipment is a break even analysis
A break-even chart visually presents alternative profits and losses due to number of units produced or sold
The method is most suitable when processes and equipment entail a large initial investment and fixed cost, and when variable production costs are reasonably proportional to the number of units produced
Break even analysis example
- A manufacturer is considering three options for obtaining a machined
part - Buy the part from a supplier for $200 per unit (no fixed cost)
- Purchase Cost = $200 × Demand
- Make the part on a semi-automatic lathe for $75 per unit
(fixed costs of $80,000) - Produce-using-lathe cost = $80,000 + $75 × Demand
- Make the part with a machining center for $15 per unit
(fixed costs of $200,000) - Produce-using-machining-center cost = $200,000 + $15 × Demand
Break even point A: Set totla cost for option 2 equal to total cost for option 3
Break point B: Set total cost for option 1 equal to total cost for option 2 and solve for D
Chart alternatives with break points: for this example: at break point A machine center becomes efficient
At break point B semiautomatic lathe becomes efficient