Lecture 2 (3) Flashcards

1
Q

Assembly line balancing

A
  1. Specify the sequential relationships among tasks using a precedence diagram
  2. Determine the required workstation cycle time

C = Production time per day/required outper per day (in units)

  1. Determine the theoretical minimum number of workstations

Nt = Sum of task times (T)/ Cycle time (C)

  1. Select a primary rule to assign task to workstations and a secondary rule to break ties
  2. Assing tasks (one at a time) to the first workstation unitil no more tasks can be added (due to cycle time or sequencing constraints) Repeat for all subsequent workstations until all tasks are assigned
  3. Evaluate the efficiency of the balance

Efficiency = Sum of task times (T)/ Actual number of workstations (Na) * Workstation cycle time (C)

  1. If efficiency is unsatisfactory, rebalance using a different rule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Workstation cycle time formula

A

C = production time per day/required output per day

The maximum duration a job takes for completion at each workstation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Theoretical number of workstations Nt

A

Nt = sum of task times (T)/cycle time (C)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Efficiency of the balance formula (assembly line balancing)

A

Efficiency = Sum of task times (T)/Actual number of workstations (Na) * WOrkstation cycle time (C)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Primary rule of prioritizing tasks

A

Prioritize tasks based on the largest number of following tasks

Secondary rule: Prioritize tasks in order of longest task time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Break-even analysis

A

A standard approach to choosing among alternative processes or equipment is a break even analysis

A break-even chart visually presents alternative profits and losses due to number of units produced or sold

The method is most suitable when processes and equipment entail a large initial investment and fixed cost, and when variable production costs are reasonably proportional to the number of units produced

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Break even analysis example

A
  • A manufacturer is considering three options for obtaining a machined
    part
  • Buy the part from a supplier for $200 per unit (no fixed cost)
  • Purchase Cost = $200 × Demand
  • Make the part on a semi-automatic lathe for $75 per unit
    (fixed costs of $80,000)
  • Produce-using-lathe cost = $80,000 + $75 × Demand
  • Make the part with a machining center for $15 per unit
    (fixed costs of $200,000)
  • Produce-using-machining-center cost = $200,000 + $15 × Demand

Break even point A: Set totla cost for option 2 equal to total cost for option 3

Break point B: Set total cost for option 1 equal to total cost for option 2 and solve for D

Chart alternatives with break points: for this example: at break point A machine center becomes efficient

At break point B semiautomatic lathe becomes efficient

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly