Manage Changes Flashcards
What must a contracting officer have to deal with changes in customer requirements?
A mechanism to deal with these changes.
What are some uses of unilateral modifications?
Unilateral modifications are used to make administrative changes, issue change orders, and make changes authorized by clauses other than a changes clause.
What is a bilateral modification?
A bilateral modification is a contract modification that is signed by both the contractor and the contracting officer, used to make negotiated equitable adjustments, definitize letter contracts, and reflect other agreements modifying the terms of contracts.
Who can modify or change contracts on behalf of the Government?
Only warranted contracting officers acting within the scope of their authority can modify or change contracts on behalf of the Government.
What are the two types of contract modifications according to FAR 43.103?
The two types of contract modifications are bilateral modifications and unilateral modifications.
What must a contracting officer obtain before executing a contract modification that increases funds?
A certification of fund availability.
What should the certification of fund availability be based on?
The negotiated price or, if the modification is completed before negotiation, the best available estimate of cost.
Under what conditions can a contracting officer execute a contract modification without obtaining a certification of fund availability?
When the modifications are conditioned on availability of funds or contain a limitation of cost or funds clause.
What types of changes are permitted under the changes clause?
The types of changes permitted are subject to the contract’s contract-type, which can be fixed-price, cost-reimbursement, or time & materials.
What is the purpose of the changes clause in government contracts?
The changes clause permits the contracting officer to make unilateral changes in designated areas within the general scope of the contract.
How are change orders documented according to FAR?
Change orders are documented by issuing written change orders on Standard Form 30, Amendment of Solicitation/Modification of Contract (SF 30).
In which type of contracts is a contractor not obligated to continue performance after a change order?
In cost-reimbursement or incrementally funded contracts, the contractor is not obligated to continue performance or incur costs beyond the limits established in the Limitation of Cost or Limitation of Funds clause.
What must a contractor do when a contracting officer issues a change order?
The contractor must continue performance of the contract as changed, except in cost-reimbursement or incrementally funded contracts.
What should contracting officers do regarding equitable adjustments resulting from change orders?
Contracting officers should negotiate equitable adjustments resulting from change orders within the shortest practicable time.
What typically results from the change order process?
The change order process typically results in two modifications: the modification issuing the change order and the modification issuing the supplemental agreement between the parties.
What is a change order?
A change order is issued by a contracting officer directing changes in the general scope of the contract.
Under what circumstances can a contracting officer issue a change order by electronic means without a SF 30?
A contracting officer may issue a change order by electronic means without a SF 30 under unusual or urgent circumstances, provided that the message contains substantially the information required by the SF 30 and immediate action is taken to issue the SF 30.
What documents are required when change orders are not forward priced?
When change orders are not forward priced, they require a change order and a supplemental agreement reflecting the resulting equitable adjustment in contract terms.
What is the purpose of a supplemental agreement in contract modifications?
A supplemental agreement is used to reflect the resulting equitable adjustment in contract terms when an equitable adjustment in the contract price or delivery terms can be agreed upon in advance.
What are some examples of when unilateral modifications are used?
Unilateral modifications are used to make administrative changes, issue change orders, make changes authorized by clauses other than a changes clause, and issue termination notices.
What is a unilateral agreement in contract modifications?
A unilateral agreement is a contract modification that is signed only by the contracting officer and is used for administrative changes, issuing change orders, making changes authorized by clauses other than a changes clause, and issuing termination notices.
What type of modifications are all changes to commercial contracts under FAR clause 52.212-4?
All changes to commercial contracts under FAR clause 52.212-4 are bilateral in type.
What does FAR clause 52.212-4(c) state regarding modifications of commercial contracts?
FAR clause 52.212-4(c) states that changes may only be made by written agreement of both parties.
What is the Government’s policy regarding the resolution of contractual issues in controversy?
The Government’s policy is to try to resolve all contractual issues in controversy by mutual agreement at the contracting officer’s level.