LOT 202.08 Extraction Steam / MSRs Flashcards
1
Q
- LOT 202.08 Extraction Steam / MSRs*
- *
Where does the steam for the SGFPTs come from?
A
- < 40%:*
- *MS Equalizing Header**
- > 40%:*
- *MSR 11 Extraction Steam**
2
Q
- LOT 202.08 Extraction Steam / MSRs*
- *
Which FW Heaters are located in the condensers?
A
FWHs 15A/B/C
FWHs 16A/B/C
3
Q
- LOT 202.08 Extraction Steam / MSRs*
- *
Where does the extraction steam go on the LP Turbine?
A
- Turbine End:*
- *4th Stage: FWH 14A/B**
- *6th Stage: FWH 15A/B/C**
- *8th Stage: FWH 16A/B/C**
- Generator End:*
- *2nd Stage: FWH 13A/B**
- *6th Stage: FWH 15A/B/C**
Blowdown flash tank steam goes to FWH 13A/B.
4
Q
- LOT 202.08 Extraction Steam / MSRs*
- *
Where are the MSR thermocouples located?
A
Crossover piping between IVs and LP Turbines
- Used for feedback control and temperature indication on reheater temperature control panel.
- Also indicated on CP018 recorder.
5
Q
- LOT 202.08 Extraction Steam / MSRs*
- *
Where does the extraction steam go on the HP Turbine?
A
4th Stage Extraction: FWH 11A/11B
Exhaust: DA (FWH 12)
6
Q
- LOT 202.08 Extraction Steam / MSRs*
- *
If the unit is operating for an extended period of time with one MSR out of service, what should power be maintained at?
A
> 50%
Minimizes erosion of LP Turbine’s last row of blading.