Liferafts Flashcards
What is the inspection interval for the LRU-25/A crew raft and LRU-33/A
1 year leak test
36 months or every 3rd leak test will be a functional
6 months for visual
What are the CO2 inflation assembly configurations
1.consists of an aluminum cylinder reinforced with overlapping carbon filaments bonded with epoxy resin
2. rated at 3500 psig+- 100 at 70 F
3. a pull force of 6-15 lbs required to actuate the inflation valve
4. overpressure rupture disk will rupture at 4500-4900 psig
5. cylinder pressure gauge utilizes a go-no-go color band to indicate
cylinder pressure
6. hydro test every 5 years
M13520.1C P 2-7, 2-8
What is the weight of a LRU-33 raft cylinder with the combination co2 and n2 charge
- 06-LBS CO2
5. 7 LBS N2
What is used for the LRU-33 raft storage cradle
1x4in pine shelving
M13520.1C P 2-8
What is the inspection interval for the mass casualty raft
5 year interval at the factory
1 year visual inspect at ast shop and may be enrolled as a special requirement inspection
Condemned rafts and containers shall be utilized for training and shall be marked in contrasting color in what manner
“DRILL ONLY” in 4 in letters on raft floor buoyancy tubes, and containers
13520.1C 2-5
When is a life raft considered non repairable at the unit level
- Porous fabric areas, open seam or seam tape that cause leak
- Damaged, malfunctioning, excessively corroded worn inlet
Valve, manifold, oral inflation valve, inflate deflate valves - Holes or tears larger than 1 in
- Holes or tears within 1 in of seam
- Holes or tears on no inflatable floors larger than 7 in
- Internal bulkhead leakage
M13520.1C P 2-4
What type of valves are the topping off valves on the LRU-33
Spring loaded poppet valves
M13520.1C P 2-7
What is the relief valve opening and closing pressures for the LRU-33
Opening- 3.2 psi
Closing- 2.4 psi
M13520.1C P 2-7
What are the leak test and functional inspect intervals for the LRU-33
Leak- 180 days
Functional- every 6th leak test or every 36 months
M13520.1C P 2-7
Where can you find repair procedures for life rafts
CGTO PG-85-00-310, Chapter 2
M13520.1C P 2-7
What is the pull force required to inflate the LRU-33
6-15 lbs
M13520.1C P 2-7