Lecture 7 Flashcards

1
Q

What does CMA stand for?

A

Project manager agent. The owner get a project manager to represent the owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What does conclusions can be drawn from the NZTA selection model?

A

Te greater responsibility given to a contractor, the greater the risk and innovation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does DBB stand for?

A

Design - Bid - Build. Owner gets a designer to design the project then gets a contractor to complete the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What does DB stand for?

A

Design build. The owner employs a design builder who designs and constructs the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is alliance?

A

A consortium is formed at the very beginning of the project so that all of the design and construction is completed by the consortium and owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly