Lecture 3 Flashcards
What steps make up scope management and project planning?
The project charter > project brief > method statements > work breakdown structure
What is WBS?
Work Breakdown Structure. It is breaking up the main goal into smaller pieces to allow for scheduling and cost estimation
What does project control allow for?
It allows for anyone to know where they are, what they need to do etc.
What is the purpose of project management planning?
To estimate duration of tasks, to optimize sequence of tasks and to check with resource availability
What is a PDM?
Precedence Diagram Method. Estimate task duration and relationships between tasks
What are TF, SF and FnF?
Total Float (TF = LF - ES - dur), Start Float (SF = LS - ES), Finish to Float (FnF = LF - EF)