Lecture 16 - Bill of Quantities Flashcards

1
Q

Standard Methods of Measurement

A

ensure clear understanding of works hence providing price that is not open to disagreement (CESMM3)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

Bill of Quantities

A

complete list of all items necessary for completion. providing sufficient info to the tenderer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

BOQ - Principle Quantities

A

list of major work components with approx. quantities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

BOQ - Premable

A

Descriptive section at front of BOQ

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

BOQ - Daywork Schedule

A

Applies to additional work which cannot be easily measured/valued

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

BOQ - Work Items

A

General items described by CESSMM, (contractual requirements, provisional items, prime costs items)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

BOQ - Grand Summary

A

A | Tabulation of sub-totals
B | General Contingency Allowance (5%)
C| Adjustment items (Lump sum added, payments/deduction)
D| Grand Total

How well did you know this?
1
Not at all
2
3
4
5
Perfectly