Lecture 15 - Pricing & Payment Flashcards
Pricing
Determine and explain the tender price
Payment
how/when the contractor will be paid
Lump Sum
contractor is paid pre-determined price for completion of a whole contract provided at tender
Re-measurement
contractor paid for measured work done, through Bill of quantitites or schedule of rates
Bill of Quantities
Project is broken down into individual items with appox. amounts from drawing
Schedule of Rates
Items are listed, no quantity, tenderer makes approx. amounts, used when work cannot be accurately found
Activity Schedule
List of activities which tenderer needs to undertake to complete project, total price based on sum of activity prices
Cost Reimbursable
Contractor is reimbursed for actually incurred cost plus fee. Used for inadequate definition of work or exceptional complexity
Target Price
Contractor is reimbursed costs and bids price/fee at tender