JCT Contracts Flashcards
What is the function of a relevant matter as a contractual mechanism?
Entitles the contractor to Loss and Expense
What is the function of a relevant matter as a contractual mechanism?
Entitles the contractor to claim for Loss and Expense
What is the contractual significant of a Relevant Event?
Allows the Contractor an Extension of Time
You have prepared contract documents, could you talk through the full suite of contract documents you have prepared?
For D&B projects, split into 3 volumes:
1 - Contract
Form of contract
Insurances
2 - CPs
CPP
CSA
Interim Payment Schedule
3 - ERs Preliminaries Design Information Change Control Procedures Basebuild Information
You’ve undertaken interim Valuations and issued payment recommendation to the EA. What are the timescales for providing payment recommendations?
Payment recommendation is not a contractual term.
Timeline under JCT for interim Valuation payments
21 day payment cycle from payment application to final date for payment
Contractor submits interim application for payment 7 days before the ‘due date’
5 Days after the due date EA issues the Payment Notice
14 days after the due date is the final date for payment
5 days prior to the final date for payment a pay less notice can be issued
What is a payless notice?
If the Client intends to pay less than the amount set out in the payment notice they must issue a pay less notice, along with the basis for its calculation 5 days prior to the final date for payment
You talk about assessing the value of EA instructions, how have you done this?
First principal to use contract rates
Benchmarked rates
Market testing
How could market testing be used to agree variations?
…………
You’ve done a final account, what’s the contractual process how the final account is submitted and agreed?
The contractor submits final account with all supporting information (ie back up to all valuation of variations)
Generally a final account meeting is arranged to agreed any outstanding variation costs
Final account statement is drafted including all necessary adjustments and signed by both parties and concludes the financial obligations of both parties (except for defects)
What happens after the contractor submits the final account?
the final account should be ascertained no later than 3 months after receipt on all supporting information from the contractor (which should be no longer than 6 months of Practical Completion)
What is a final account?
“The final account is the conclusion of the contract sum (including all necessary adjustments) and signifies the agreed amount that the employer will pay the contractor. It includes any works that are paid to the contractor through the main contract” - RICS Black Book
Final account procedures RICS Guidance Note 1st Edition
What does the final account include?
The contract sum
Variations / Instructions Provisional Sums Loss and Expense Prime cost sums (if applicable) Acceleration (if applicable)
Any other items affecting total cost
On Elsley House, you advised on a letter of intent, what advise did you give your client?
I advised that we could instruct the Contractor to proceed with consent to spend up to a certain value while the contract was being finalised.
This enabling the Contractor to start procuring long lead items prior to entering into contract
What is included in a letter of intent?
The parties – the names and titles of the parties as stated within the contract documents
The works – described in clear and concise terms
The price (if agreed) – clearly stating the currency and whether this price is to be considered
a maximum expenditure limit until the formal execution of the contract
A statement of the intention of the parties to enter into and be bound by a formal contract
The dates for possession and completion and whether there is any sectional completion
envisaged or required within the contract
Entitlements of both parties upon the revocation, frustration or repudiation of the contract
Procedure for calculating interim payments if work proceeds
Procedure for calculating and issuing final payment should the work not proceed or if a formal
contract is not executed between the parties
Insurances that are to be provided
The maximum expenditure limit allowed under the letter of intent
Termination procedure
Confirmation that the contract created by the letter of intent will terminate upon execution of
the principle contract(s)
Dispute resolution procedure.
What risks might you make your client aware of before proceed under a letter of intent?
Contractor has no contractual obligation until contract is signed and could potentially walk away
Delays achieving a fixed price / cost certainty that you get when the entering into a contract