Contract Practice - Level 3 (EOT) Flashcards

1
Q

Are all Relevant Events also Relevant Matters?

A

No!

Relevant Event - EOT (Time)
Relevant Matter - Loss & Expense (Time & Money)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

You talk about advising on issuing an EAI preventing the Contractor in carry out works and entitle them to an extension of time. Was this not a relevant matter and therefore time and money?

A

Yes this could have been a relevant matter and entitled them to loss and expense

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a Relevant Matter?

A

Term in the contract relating to categories for which a Contractor is entitled to an Extension of Time and Money

An something the client has caused that has resulted in a delay for the Contractor and entitles them to an EOT and L&E

(D&B Clause 4.21)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a Relevant Event?

A

A term in the contract relating to categories for which a Contractor is Entitled to an Extension of Time.

A list of instances in the contract which, in theory, if they happen will entitle the Contractor to an EOT

(D&B Clause 2.26)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Why is it important for the Contractor to get an EOT?

A

If they need to extend their programme and mitigate the need for Liquidated Damages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Can you give some Examples of Relevant Events?

A
Variations 
Instructions 
Deferment of Possession 
Suspension by the Contractor 
Impediment by the Employer
Statutory works 
Exceptional adverse weather 
Specified Perils (Fire, lighting, floods)
Civil Commotion 
Strikes 
Force Majeure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What should happen if the contractor is delayed by a Relevant Event?

A

Contractor should issue a Delay Notice as soon as reasonable apparent:

  • Stating the cause of the delay
  • Identify the Relevant Event

The EA should:

  • Give an EOT
  • Notify the Contract
  • Give reason of EOT within 12 weeks
  • State EOT in relationship to each Relevant Event
  • Fix a New Completion Date
How well did you know this?
1
Not at all
2
3
4
5
Perfectly