IEQ (Indoor Environmental Quality) Advanced 1 Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

How many prerequisites are there for IEQ and what are they?

A

2 prerequisites

P1. Minimum indoor air quality performance
P2. Environmental tobacco smoke control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How many credits are there for IEQ and what are they?

A

9 credits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How does an engineer determine if natural ventilation is feasible?

A

By using the CIBSE Application Manual AM10 flowchart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What percentage of individual occupant spaces AND shared multi-occupant spaces must have lighting controls?

A

90% of individual occupant spaces

100% of multi-occupant spaces

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is required for healthcare projects to meet IEQ C , Construction IAQ Management Plan that other project types are not required to include?

A

EQMP (Environmental Quality Management Plan)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the 3 acceptable forms of documentation for documenting low-emitting products?

A
  • testing reports
  • MSDS
  • third party certification
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What action is required for a project to earn IEQ C , Daylight?

A

Take daylight measurements in regularly occupied spaces X months from completion???

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the threshold for an sDA simulation?

A

Question 28

300 lux, 50%?..

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

For a flush out while the building is UNOCCUPIED, what quantity of outside air must be introduced to the project space?

A

14,000 cu ft per square foot of floor area

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

For a flush out while the building is OCCUPIED, what quantity of outside air must be introduced to the project space?

A

3,500 cu ft per square foot of the floor area and must continue until 14,000 cu ft of outdoor air is introduced

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Question 37

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Under what circumstances must testing for air quality occur to meet IEQ C , IAQ Assessment?

A

During normal occupied hours and while operating at a minimum outdoor airflow rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What 3 options can a project do to earn points for IEQ C, Enhanced IAQ Strategies Option 2 Additional Enhanced IAQ Strategies?

A
  • Exterior contamination prevention
  • Additional source control and monitoring
  • Natural ventilation room by room calculations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the calculation for an occupied flush-out to achieve IEQ C, IAQ Assessment?

A

Occupied = 0.3 cfm per total square foot

Example 1. 100,000sf building = 100,000 x 0.3 = 30,000 cfm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Under what circumstances will a project not have to address exterior noise?

A

Building is located 1/2 mile from any significant noise source

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is required before a flush-out or air testing?

A
  • install all finishes and furniture
    • for residential projects, install owner provided furniture
  • complete punch list items that would generate VOCs
  • test and balance the HVAC system
17
Q

What CRI makes lighting look natural?

A

CRI of 80

18
Q

Define LUMINANCE

A

How much lighting is on the plane of a surface