€h 05 - Horizontal Distribution System Flashcards

1
Q

5-1 horizontal pathways

Continuous pathways =

(2)

A

*Conduit

* containment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

5–1 horizontal pathway

Non continuous pathways =

A

J-hook

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

5–7

Wet locations =

(3)

A

* Sand

* gravel

* soil

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

5–9 considerations for horizontal pathways

Planning purposes =

A

Hallways

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

5–9 maximum occupant density

Work area (WA) =

A

* 100 ft.²

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

5–9

BAS =

(3)

A

* Building automation system

* 250ft.2

* pathway capacity - 1 cable each system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

5–10 cable diameter

4 pr cable =

A

.35in

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

5–10 cable diameter

2-fiber cable =

A

.18in

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

5-14 unsuitable conduit

Flexible conduit =

(4)

A

*Creep

* shift

* sheath damage

*not recommended

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

5–14 unsuitable conduit

If flexible conduit must be used =

A

Size increase by one trade size

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

5-14 acceptable conduit runs

ITS design =

A

Best direct route

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

5–14 acceptable conduit runs

Continuous section =

A

No longer than 100 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

5–14 acceptable conduit runs

Pull boxes/pull points =

A

More than 100 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

5–15 unacceptable conduit runs

Conduit should not be run =

A

Near heat sources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

5-15 unacceptable conduit runs

Aluminum or ENT =

A

never be placed in concrete floors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

5–19 recommended conduit capacity

Cross-section area formula =

A

.785 x diameter²

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

5–19 recommended conduit capacity

Q: what is the cross-sectional area if the diameter of the cable is .35? =

A

.785 x (.35)² = .0962

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

5–19 been radii for conduits

4 pair cable =

A

4 times

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

5–19 bend radii

Multi-pair copper cable=

A

10 times

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

5–19 been radii

TBB cable=

A

8 times

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

5–20 design with conduit bends

If run requires (2) 90° bends =

A

Pull point

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

5–20 designs with conduit bends

Third 90° bend =

A

Derate the design capacity by 15%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

5–20 using three bends in conduit

Third bend may be acceptable =

(3)

A

* Not longer 33 feet

* conduit size increased

* Bend is 12 inches of cable feed end

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

5–21 conduit terminations

Protrude through structural floor =

A

1 inch to 4 inch

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
5–21 completing conduit installation Complete conduit install = (4)
\* Clean \* reamed \* capped \* Labeled
26
5–21 complete conduit install Equipped with pull cord =
200 lb test rating
27
5–23 points or pull boxes for conduits Slip sleeve = (2)
\* Larger than the main conduit \* length 12 times the diameter
28
5–23 pull points or pull boxes for conduits Gutter =
sheet metal housing or busduct
29
5-23 Using slip sleeves and gutters =
except used as splice locations
30
5-24 pull points and pull boxes pulling and looping boxes only for cables =
\> 2in OD
31
5–24 choosing pull box size Q: If (5) 4" conduits are entering in one pull box, what is the required width?
15+8+8+8+8 = 47"
32
5–26 two general types of access floors Standard height = low-profile floors =
\* 6 in or higher \* less than 6 in
33
5–26 access floor components Access floor consist =
Except longitudinal cross-members (does not belong)
34
5–26 access floor components Panel sizes =
18" to 24"
35
Figure 5.7
## Footnote \* space for tiles \* stringers \* aluminum locking pedestals \* steel footings
36
5-27 Freestanding and cornerlock systems restricted installations =
finished heights 12in or less
37
5–28 design access floor General office areas finished floor height =
8" or higher
38
5–28 design access floors HVAC finished floor height =
12" or higher
39
5–28 design access floors Finished floors =
Min 2" of free space
40
5-29 access floor building structure Depressed slab =
New construction
41
5–29 access floor building structure Normal slab =
Renovated buildings
42
5–30 floor panel coverings Computer room =
High-pressure laminate
43
5–30 floor panel coverings Office =
Factory laminated
44
5–31 load bearing capacity Uniform load capacity =
100 lbf/ft²
45
5–31 load bearing capacity Concentrated load capacity =
2000 lbf
46
5–31 load bearing capacity General office =
50 lbf/ft²
47
5–31 load bearing capacity Dynamic loads =
Falling objects
48
5-32 - running telecom cables connecting hardware =
not be placed in access floor with the exception of CP
49
5-32 Underfloor air distribution on cabling Access floors maybe used as =
a plenum space for distributing conditioned air
50
5–33 access floors Disadvantages =
High initial cost
51
5–35 ceiling distribution systems Ceiling zone method =
904 ft.²
52
5–38 design ceiling system Min ceiling space = (2)
\* 3" above conduits \* 12" above tray or raceway
53
5–40 pathway and cable support Pathways must = (2)
\* Min of. 3" above ceiling tiles \* sufficient space then 6 inch above ceiling tiles
54
5–40 pathway and cable support J hooks distance = 100 feet run =
\* 5ft apart \* 20 j-hooks
55
5-41 pathway and cable support 50 or more cables =
cable tray
56
5–42 cable tray fittings Used for changing direction =
Except covers (does not belong)
57
5–43 cable tray types Ladder =
Two side rails
58
5–43 cable tray types Ventilated trough =
Ventilated bottom
59
5–43 cable tray types Ventilated channel =
Channel
60
5–43 cable tray types Solid bottom =
Solid bottom
61
5–43 cable tray types Spine =
Rigid spine
62
5–43 cable tray types Basket tray =
Wire mesh
63
5–45 supporting cable trays Trays and wire ways =
Supported on 5 feet centers
64
5–46 ceiling homerun method conduit One or two boxes =
Inside diameter of 1 inch
65
5–46 ceiling homerun method conduit Three boxes =
Inside diameter of 1.25 in
66
5-46 zone conduit size 250 ft2 - 600 ft2 = 600 ft2 - 904 ft2 =
## Footnote \* 2 trade size conduit \* 2 1/2 trade size conduit
67
5–50 attaching utility columns Utility poles =
10ft, 12ft, 15ft
68
5-52 other horizontal pathways other types of pathways include = (5)
\* catenary wire (messenger) \*perimeter (surface) raceway \* overfloor ducts \* molding raceways \* poke-thru
69
5-52 perimeter raceways perimeter raceways = (2)
## Footnote \* cubicle furniture \* power run seperate
70
5–60 horizontal cabling system Horizontal cabling installed = (4)
\* Star topology \* both ends terminated on same floor \* splices are not permitted, *with the exception of fiber pigtails* \* bridged taps not allowed
71
5-60 topology application specific-devices not used in horizontal cabling = (3)
## Footnote \* baluns \* splitters \* crossover patch cords
72
5–61 Centralize optical fiber cabling limited =
984 ft
73
5–61 centralized optical fiber cabling Pull through method limitation = (Desktop)
295 ft
74
5–61 centralize optical fiber cabling Q: 1000 ft spool / 295 ft pull-through method =
3 pulls
75
5-65 multidrop conduit system Multidrop conduit system recommended =
buildings to preselected locations
76
5–68 duct floor systems Junction boxes =
60 ft
77
5–69 duct system Distribution ducts =
Distributing cables from the TR to specific floor areas
78
5–70 duct systems Feeder ducts =
Connects TR to distribution ducts
79
5 – 70 duct system Enclosed feeder j boxes =
5" handhold opening
80
5–71 feeder duct types Large lower =
Feeders
81
5–71 feeder duct types Standard Upper=
Power
82
5-71 Feeder duct types Large upper =
Telecommunications
83
5–73 design underfloor ducts Determining duct size =
1 in.² cross-section for each 100 ft.²
84
5–73 design underfloor duct Feeder duct size =
8.9 in.² cross-section for each 800 ft.²
85
5–74 design underground duct Distribution duct sizes = (2)
\* standard 3.3 in2 - 3.9 in.² \* use larger ducts when area is 60ft - 80ft long
86
5–75 design underground duct Slab thickness: one level = 2 level = Feeder beam concept =
\* 5" \* 7" \* 7"
87
5–80 terminating ducts TR duct do not pass =
3 inch to 6 inch
88
5–80 terminating ducts TR duct pass =
Elbow
89
5-93 Cellular Floor System steel cellular floor =
do not use feeder (conduit to a cell) below deck
90
5–102 trench duct for under floor Trench duct cover plates =
4 feet long x up to 38" wide
91
5–103 removing trench duct cover Lifting device =
Stored in TR
92
5–103 removing trench duct cover Suction cups =
.25" eye bolts
93
5-103 removing trench duct cover plates building personnel =
should remove trench duct cover, but telecom personnel is expecteted remove 1 or 2
94
5–117 references TIA-569-B =
Pathways and spaces