€h 05 - Horizontal Distribution System Flashcards
5-1 horizontal pathways
Continuous pathways =
(2)
*Conduit
* containment
5–1 horizontal pathway
Non continuous pathways =
J-hook
5–7
Wet locations =
(3)
* Sand
* gravel
* soil
5–9 considerations for horizontal pathways
Planning purposes =
Hallways
5–9 maximum occupant density
Work area (WA) =
* 100 ft.²
5–9
BAS =
(3)
* Building automation system
* 250ft.2
* pathway capacity - 1 cable each system
5–10 cable diameter
4 pr cable =
.35in
5–10 cable diameter
2-fiber cable =
.18in
5-14 unsuitable conduit
Flexible conduit =
(4)
*Creep
* shift
* sheath damage
*not recommended
5–14 unsuitable conduit
If flexible conduit must be used =
Size increase by one trade size
5-14 acceptable conduit runs
ITS design =
Best direct route
5–14 acceptable conduit runs
Continuous section =
No longer than 100 feet
5–14 acceptable conduit runs
Pull boxes/pull points =
More than 100 feet
5–15 unacceptable conduit runs
Conduit should not be run =
Near heat sources
5-15 unacceptable conduit runs
Aluminum or ENT =
never be placed in concrete floors
5–19 recommended conduit capacity
Cross-section area formula =
.785 x diameter²
5–19 recommended conduit capacity
Q: what is the cross-sectional area if the diameter of the cable is .35? =
.785 x (.35)² = .0962
5–19 been radii for conduits
4 pair cable =
4 times
5–19 bend radii
Multi-pair copper cable=
10 times
5–19 been radii
TBB cable=
8 times
5–20 design with conduit bends
If run requires (2) 90° bends =
Pull point
5–20 designs with conduit bends
Third 90° bend =
Derate the design capacity by 15%
5–20 using three bends in conduit
Third bend may be acceptable =
(3)
* Not longer 33 feet
* conduit size increased
* Bend is 12 inches of cable feed end
5–21 conduit terminations
Protrude through structural floor =
1 inch to 4 inch
