Ch 13 - Design, Construction, & Project Management Flashcards

1
Q

13–4 lessons learned

First step =

A

Lessons learned

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

13–4 project management knowledge areas

A SoW should contain =

A

Except purchases, doe not belong

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

3–8 building a work breakdown structure (WBS)

Execution steps =

(3)

A

*ClientProduct

* Market conditions

*Or all the above!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

13–10 developing a schedule using PERT, milestone, gantt and calendar charts

PERT =

(2)

A

* Program evaluation and review technique

* Network diagrams to identify predecessor and successor relationships on projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

13-11 Developing a schedule using pert, milestone, gantt and calendar charts

PERT diagrams =

A

Start and finish dates of each activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

13-11 Developing a schedule using pert, milestone, gantt and calendar charts

Gantt chart =

A

bar chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

13-13 Developing estimates

Analogous =

A

Estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

13–13 developing estimates

PERT formula =

A

(Optimistic + (4 x most likely) + pessimistic)/6 40 50 60 = 50 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

13–14 developing a budget using earned value analysis

Ahead of schedule =

A

Earned value method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

13–19 design team members

Architect =

Engineer =

A

* Hired by owner

* Licensed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

13–19 construction team members

General contractor =

A

Complete the work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

13–23 design phases

Stipulated sum =

Cost plus fee =

Unit price =

A

* Fixed price

* Reimbursed

* Cannot be determined

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

13–27 elements of design package

Division 06 =

A

Wood, plastics, and composites

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

13–28 elements of design package

Division 27 =

Division 28 =

Division 16 =

A

*Communications

* Electronic safety and security (ESS)

* Old telecom division

How well did you know this?
1
Not at all
2
3
4
5
Perfectly