Formulas Flashcards
1
Q
BAC
Budget at Completion
A
Sum of all budgets
Total Planned Value for project
2
Q
EV
Earned Value
A
%complete X BAC
3
Q
VAR
Variance
A
BAC - EAC
4
Q
CV
Cost Variance
A
EV - AC
5
Q
SV
Schedule Variance
A
EV - PV
Planned Value
6
Q
CPI
Cost Performance
A
EV / AC
Actual Costs
7
Q
SPI
Schedule Performance Index
A
EV / PV
Planned Value
8
Q
EAC
Estimate At Completion
A
BAC / CPI
9
Q
VAC
Variance At Completion
A
BAC - EAC
10
Q
ETC
Estimate To Completion
A
EAC - AC
11
Q
Communications Channls
A
N*(N-1) / 2
12
Q
Variance
A
[(P-O) / 6] Squared
13
Q
Float or Slack
A
LS-ES and LF-EF
14
Q
BCR
Benefit Cost Ratio
A
Benefit / Cost
15
Q
Order of Magnitude Estimate
A
-25% - +75%
-50 to +100% PMBOK