final exam Flashcards

(61 cards)

1
Q

capacity

A

the maximum rate of output of a process or a system

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

utilization

A

The degree to which equipment, space, or the workforce is currently being used

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

utilization calculation

A

(average output rate/maximum capacity) * 100%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

capacity cushions

A

the amount of “reserve capacity” a process maintains

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

economies of scale

A

reduce cost by increasing output rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

diseconomies of scale

A

cost increases as the facility’s size increases

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

capacity cushion calculation

A

100% - average utilization rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

setup times

A

The time required to change a process or an operation from making one service or product to making another.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

bottleneck

A

limits the organization’s ability to meet the product volume, product mix, or demand fluctuation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

theory of constraints

A

focuses on managing constraints that delay a firm’s progress toward its goal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

throughput time

A

Total elapsed time from the start to the finish of a job

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

TOC steps

A
  1. identify system bottlenecks
  2. exploit/improve the bottlenecks
  3. subordinate all other bottlenecks to step 2
  4. elevate the bottlenecks
  5. do not be complacent
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

identifying bottlenecks

A

large setup times and cost leads to larger runs being made

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

immediate predecessors

A

Work elements that must be done before the next element can begin

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

mixed model lines

A

A production line that produces several items belonging to the same family

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

lean system

A

maximize the value by removing waste and delays from activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

type of waste in lean

A
  1. overproduction
  2. inappropriate processing
  3. waiting
  4. transportation
  5. motion
  6. inventory
  7. defects
  8. underutilization of employees
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

jidoka

A

immediately stopping the process when something is wrong and then fixing the problems

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

muda

A

waste

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

poka-yoke

A

methods aimed at designing fail-safe systems that minimize human error

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

heijunka

A

The leveling of production load by both volume and product mix.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

kaizen

A

The philosophy of continually seeking ways to improve processes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

takt time

A

Cycle time needed to match the rate of production to the rate of sales or consumption

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

pull method

A

customer demand activates the production

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
push method
production begins in advance of customer needs
26
the 5 S's
1. sort 2. straighten 3. shine 4. standardize 5. sustain
27
takt time calculations
working time available/ customer demand
28
Kanban
keeping records of what you have, what you are using, and what needs to be reordered to control flow
29
just in time
The belief that waste can be eliminated by cutting unnecessary capacity or inventory and removing activities that don't add value
30
JIT system
rearranging the organization to make a firm realize the benefits of JIT principles.
31
project objectives
statement of scope, time frame, and resources
32
critical path
The sequence of activities that takes the longest time to complete; determines earliest possible completion date
33
gantt chart
helps team allocate resources and plan for project
34
earliest finish time
earliest start + estimated duration
35
latest start
latest finish - duration
36
activity slack
latest start - earliest start or latest finish - earliest finish
37
risk management plan
identifies risks finds ways to overcome them
38
risk categories
1. strategic fit 2. service/product attributes 3. product team capability 4. operations
39
PERT
(optimistic time + 4*most likely time + longest amount of time) / 6
40
project life cycle
monitor status, monitor resources
41
inventory management
The planning and controlling of inventories to meet the competitive priorities
42
average cycle inventory
lot size/2
43
3 types of inventory
raw material, work in process, finished goods
44
SKU
stock keeping unit
45
ABC analysis
dividing SKUs into three classes, according to their dollar usage, so that managers can focus on items that have the highest dollar value
46
economic order quanitity
square root of (2 * annual demand * ordering or setup costs)/holding cost per unit
47
inventory position calculations
on hand + in transit – demand = x
48
periodic
ordering inventory to replenish
49
component
goes through processes to become part of one or more parents
50
parent
manufactured from components
51
dependent demand
demand occurs because the quantity varies due to production plans for other items
52
ATP procedures
available to promise; The quantity of end items that marketing can promise to deliver on specified dates.
53
bill of materials
A record of all the components of an item, the parent-component relationships, and the usage quantities
54
MRP inputs
bill of materials and info in inventory records
55
scheduled receipts
orders that have been placed but not yet completed
56
planned receipts
Orders that are not yet released to the shop or the supplier
57
lead time
when you place the order until receipt
58
MRP explosion
inventory record for a material; shows items lot size policy, vendor, price, lead time
59
MRP explosion calculation
on hand = beginning balance + receipts - sales
60
enterprise process
companywide process that cuts across functional areas, business units, geographical regions, product lines, suppliers, and customers
61
bill of resources
same as BOM but for service firms