Explain the Different Stages of a Typical Change Control Process Flashcards

1
Q

Why Change Control?

A
  • We may not be able to control it happening but we want to remain in control
- Changes may be: 
> Unavoidable 
> Highly desirable 
> Unnecessary 
> Not useful 
  • Proposed change should be formally controlled, understanding the impact of a proposed change before a decision is made
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Change Reviews

A
  • Prior to approval and implementation, changes need to fully reviewed by:

> project team
relevant stakeholders
project sponsor

  • Impact must be assessed against
    > the project
  • Business-as-usual
  • other projects
  • Approved changes should be fully documented and efficiently communicated
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Change Control Process

A
  • Projects must have an effective change control process
  • The project manager is responsible for ensuring
    > a robust process is in place
    > it is used
    > the project team is familiar with its operation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Change Control Process Steps

A
  • Change request and change log
  • Initial evaluation
  • Recommendation
  • Update plans
  • Implement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Change Request

A
  • Change request is the process through which all requests to change the baseline scope of a project, programme, or portfolio are captured, evaluated and then approved, rejected or deferred
  • The requesting stakeholder provides relevant information on the nature of the change
  • Perhaps on a change request form
  • Each change is entered in to the change log
- ALL change requests should be registered along with their status e.g. 
> pending
> approved
> rejected
> deferred
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Change Request Initial Evaluation

A
  • Is the request worth evaluating in detail or is it even possible
  • consumes resources, which is a deviation from the plan
  • the proposed change may be rejected at this stage
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Change Request Detailed Evaluation

A
  • The change is evaluated to consider the impact on the project’s baseline :
> scope
> time 
> cost
> quality 
> benefits 
  • other factors such as risk, safety, and environmental impact may also be considered
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Change Request Impact Assessment

A
  • what would have to change
  • what effort would the change require
  • what is the affect on schedule/ budget
  • what are the knock on effects
  • would the business case alter
  • would the risks increase or decrease
  • would the agreed time for delivery change
  • is the change within agreed tolerances

Note: That for proposed major changes, the effort involved in analysing the impact can itself have a significant impact on the project and therefore the analysis needs to be approved.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Change Request Recommendation

A
  • a recommendation is made that the change should be:

> approved
rejected
deferred

  • the sponsor has ultimate authority to act
  • the decision must be communicated
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Change Request Update Plans

A
  • planning determines what is to be delivered, how much will it cost, when it will have delivered, how will be delivered and who will carry it out
  • if a change is approved, all plans are updated to reflect the change
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Change Request Implement

A
  • all necessary actions are taken to implement the change, including updating project documentation
  • the implementation is monitored along with the rest of the project
  • unauthorised changes should be put through the process retrospectively
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Change Request Change Control Log/ Register

A
  • The log consists of:

> change request form
current status
ultimate outcome in terms of effect on : schedule, budget, any other knock on effects
part of the audit trail
current stat of project should = baseline project plan + approved changed
unauthorised changes should be processed retrospectively

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Change Request Scope Creep

A
  • Scope Creep is when a project’s scope gets bigger and bigger
  • common cause of project failure alongside uncontrolled change
  • increases cost
  • causes unplanned delay
  • has a detrimental effect on quality
  • reduces morale and productivity

DISADVANATGES

  • can be bureaucratic
  • can be long winded
  • can be expensive
  • sometimes used to discourage change
  • can make projects unresponsive to changing needs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly