Differentiate between resource smoothing and resource levelling Flashcards

1
Q

Resource Smoothing

A
  • Used when the time constraints take priority
  • The objective is complete the work by the required date while avoiding peaks and troughs of resource demand
  • Resource levelling is used when limits on the availability of resources are paramount
  • Time-limited scheduling; time is relatively more important than cost
  • Can be applied to ensure that resources are used as efficiently as possible
  • Involves utilising float or increasing/ decreasing resources for specific activities
  • Peaks and troughs of resource usage are evened out
  • Does not affect project duration
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Resource Levelling

A
  • Technique in project management that overlooks resource allocation and resolves possible conflict arising from over-allocation
  • When project manager undertake a project, they need to plan their resources accordingly
  • Resource-limited scheduling
  • Applied when there are resource constraints
  • Forces the amount of work not to exceed the amount of resource available
  • Asks the question ‘with the resources available, when will the work be finished?’
  • Can result in durations being extended or delayed at both activity and project level
How well did you know this?
1
Not at all
2
3
4
5
Perfectly