Element 1 Construction Law & Management Flashcards
Give a definition of “Structure”?
Any building, timber, masonry, metal or reinforced concrete structure, caisson, mast or tower.
Give a definition of Excavation?
Work carried out below ground level.
Identify the 5 stages for Construction Work, from a Health & Safety perspective?
- Concept and feasibility….Design, layout and construction methods are decided and developed.
- Design and planning….Specifications, final drawings and notification to the authorities.
- Tender/selection….Selection process for the Principal Contractor.
- Construction phase….Construction work is planned, programmed and prepared. Then carried out and managed throughout.
- Commissioning and handover….Bringing the project into operation, handover to Client.
Give a definition of “Project”?
All work on a construction development, including planning, design, management and all construction work until the end of the construction phase.
When planning and managing construction projects, list some particular issues/considerations?
- Transitory Nature of Workers….competency, training, knowledge, ill-health, behaviour.
- Temporary Nature of Construction Activities and the Constantly Changing Workplace….different tasks, stages.
- Time Pressures from Clients and Principal Contractors.
- Weather Conditions….external/internal, time of year, safety implications.
- Levels of Numeracy and Literacy of Workers….communication issues, different backgrounds.
- Non-English Speaking Workers…..communication issues.
Identify the main reasons why an organisation has to manage Health and Safety?
- Legal
- Moral
- Financial
Identify the typical areas where statistically high numbers of injury occur?
- Falls from height
- Slips, trips and falls occurring on the same level
- Being struck by falling/moving objects
- Manual handling
Give a definition of “Notifiable”?
The relevant enforcing authority (HSE, ORR, ONR), must be informed if the project is expected to last longer than 30 working days AND have more than 20 workers working on the project at any one time, or exceed 500 person days.
Give a particular Client duty?
- To ensure that both the principal designer and principal contractor comply with their duties.
- To make suitable arrangements for managing a project….sufficient time, resources, etc.
Give a particular duty of the principal designer?
- Responsible for managing the pre-construction phase of the project.
- Ensure designers carry out their duties.
- Prepare and provide relevant information to other duty holders.
Give the particular responsibilities/duties of the principal contractor?
- Manage the construction phase of the project.
- Prepare the Construction phase plan.
- Co-ordination of Sub-Contractors.
- Ensure implementation by the contractors of legal requirements for health and safety.
- Ensure that employers apply the general principles of prevention and follow the construction phase plan.
- Ensure that a suitable site induction is provided, steps taken to prevent unauthorised access to the site and that adequate welfare facilities are provided.
Liaise with the principal designer and share information. - Ensure workers are competent and consulted in securing health and safety.
Define an “F10”
This is the form from the HSE - “Notification of a Construction Project” - that is completed by the Client BEFORE a project starts.
It is sent to the HSE and a copy must be displayed on site.
What does ORR stand for?
Office of Rail Regulation
What does ONR stand for?
Office for Nuclear Regulation
Explain what key information should be included in the “Pre-Construction information”?
- The project, such as the client brief and key dates of the construction phase.
- The planning and management of the project, such as resources, time allocation, arrangements to ensure coordination between duty holders.
- The health and safety hazards of the site, including design and construction hazards.
- How health and safety hazards will be addressed.
- Any relevant information in an existing health and safety file.