Downstream & beyond: Decommissioning Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

What is decommissioning?

A

Decommissioning is the process of “closing down” an oil rig after production processes have ended.

Decommissioning is a rapidly developing area of the oil & gas sector with many risks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Decommissioning steps

A
  1. Permits & regulatory compliance
  2. Hydrocarbon purge & flush
  3. Plug & abandon
  4. Topside decommission (dismantle)
  5. Structure removal (or not?)
  6. site clean up
  7. monitoring and surveying
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why are rigs decommissioned?

A

Oil rigs not used in 5 years or more are typically decommissioned

  • Idle structures could be damaged (during environmental disasters)
  • Damaged platforms and wells are more costly to decommission than non-damaged ones
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

10 Detailed Steps in Decommissions

A
  1. Project Management, Engineering, and Planning
  2. Permitting and Regulatory Compliance
  3. Platform Preparation
  4. Well Plugging and Abandonment
  5. Conductor Removal
  6. Mobilization and Demobilization of Derrick Barges
  7. Platform Removal
  8. Pipeline and Power Cable Decommissioning
  9. Materials Disposal
  10. Site Clearance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Project Management

A

Feasibility studies are conducted to determine the best, most cost-effective, safest approach

The planning for decommission starts 3 years in advanced before well runs dry

Involves:

  • Review of contractual obligations
  • Engineering analysis
  • Operational planning
  • Contracting
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Permitting & Regulatory Compliance

A

Local consulting firms are typically hired to ensure all permits are in order before decommission since they know the laws and regulations in the region.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Permitting & Regulatory Compliance

Execution Plan is one of the ……………. steps in the process. it includes:

A

first

  1. Environmental info & field surveys of site
  2. Schedule of decommission activities
  3. Equipment needed
  4. Labor needed
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The Execution Plan is needed for these reasons:

A
  • •To get regulatory permits
  • •Assess & reduce environmental impact
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Hydrocarbon Purge & Flush

A

To prepare for decommissioning, everything must be cleaned!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The Purge Includes:

A
  1. Cleaning:
    1. Tanks
    2. Processing equipment
    3. Piping
  2. Disposal of residual hydrocarbons
  3. Removal of platform equipment, including:
    1. Cutting pipes & cables
    2. Separating modules
    3. Installing padeyesto lift modules
    4. Reinforcing the structure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Well Plugging & Abandonment

A
  • This stage is one of the most expensive aspects of decommissions
  • Plugs must be tagged for proper placement, or pressure-tested for integrity
  • includes two phases:
    • the planning phase
    • well abandonment phase
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The Planning Phase

A
  • •Data collection
  • •Preliminary inspection
  • •Selection of abandonment methods
  • •Submittal of application for government approval
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Well Abandonment Phase

A
  • Well entry preparations
  • Filling the well w/fluid
  • Removal of downhole equipment
  • Cleaning out wellbore
  • Plugging:
    • Open-hole
    • Casing stubs
    • Annular space
    • Surface plug
    • Fluid between plugs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

the well plug and adandonment process includes the following stages:

A
  1. perforating casing to facilitate water circulation
  2. injecting cement plug to create intermediate bariier
  3. cutting and recover surface casing strings
  4. inserting packer and injecting cement to create environmental barrier.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Topside Decommission

A

Platform components & conductor casings must be removed at least 15ft below the ocean floor.

there are three methods for conductor casing removal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

there are three methods for conductor casing removal

A
  1. severing: using explosives, mechanical or abrasive cutting
  2. pulling/ sectioning: uses casing jacks to raise the conductors
  3. offloading: uses rental crane to lay down each conductor casing segment in the platform area (carried off by boat to a port)
17
Q

Jacket Removal

A

After topside removal, this is the next step in the demolition process and is very costly

Jacket removal process:

  1. divers may use:
    1. explosives
    2. mechanical means
    3. torches
    4. abrasive technology
  2. cuts are made on piles 15ft below the mudline
  3. jacket is removed in small pieces or as a single lift
18
Q

Pipeline & Power Cable Decommission

A

Pipeline or power cables may be decommissioned in place if they don’t interfere with navigation or fishing