Domestic Building Contract Act 1995 Flashcards
What is a Prime Cost Item (PC)?
Fixture or fitting (boxed item) that’s been selected or its price is unknown at the time of signing contract.
Purpose of the Domestic Building Act?
Regulate Contracts
Provide for dispute resolution
Require builders have insurance
What is a Provisional Sum (PS) Item?
An estimate allowed of the cost of carrying out particular work. Labour or materials that a builder cannot define at the time of signing the contract.
Deposit Limits for Contracts under and over $20,000
5% over $20k
10% under 20k
Breach 100 Penalty Points
How many penalty points for misleading info on PS and PC items
35 Penalty Points
How long is a cooling off period after signing a contract?
5 clear business days
When can you have a cost plus contract
1 million + contract
If reno, restoration, refurb of an existing building and is difficult to cost.
Limits on progress payments - Method A contract
Deposit 5%
Base 10%
Frame 15%
Lock-up 35%
Fix 25%
Completion - Balance
When can a builder enter into a domestic builder contract that has an escalation clause?
If contract price is more than $500,000
How long does a builder have to give a copy of a contract to the owner?
As soon as is practicable, no later than 5 clear business days.
Breach: 20 penalty points + 1 point per day