Design Economics And Cost Planning Flashcards
How does storey height affect construction cost?
- More vertical distribution
- Greater number of lifts
- Requirements for sprinkler or dry riser
Can you list the RIBA plan of works?
Stage 0: Strategic definition
Stage 1: Preparation and briefing
Stage 2: Concept design
Stage 3: Spatial coordination
Stage 4: Technical design
Stage 5: Construction and manufacturing
Stage 6: Handover
Stage 7: In use
When would you carry out cost plans?
Stage 2-4
What is the New Rules of Measurement?
Method of measurement used in construction
What is the New Rules of Measurement?
Standard method of measurement used in construction
Can you name the different documents of NRM?
NRM 1: order of cost estimating and cost planning for building works
NRM 2: measurement of detailed building works
NRM 3: order of cost estimating and planning for maintenance works
What assumptions and exclusions did you include for the Trowbridge town hall cost plan?
What information was needed on the CSM project to produce a feasibility?
What VE options did you recommend on the Brabazon project?
Change the material of the conduit in the bedroom from galvanised steel to plastic
Can you explain the process of value engineering?
What was included in your pre-tender estimate for Dyson D9?
What’s the main purpose of a cost plan?
To control affordability of design
Ensure clients are provided with value for money
To provide robust information so the client can make informed decisions
Why do we include assumptions and exclusions?
Statements for clear or ambiguous information
What constitutes a cost plan?
Building works
Main contractors prelims
Main contractors OH&P
Risk allowances
Design/project team fees
Other project costs
Inflation
What is included for project design fees?
- Consultants (based on %)
- Pre construction (% or lump sum)
- Main contractor design fee
What is the purpose of a cost estimate?
To ensure affordability
To break the costs into elements
To agree a cost limit
When are estimates carried out in the RIBA plan of works?
Stage 0 - feasibility estimate
Stage 1 - order of cost estimate
Stage 3/4 - pre tender estimate
What information is required for a cost estimate for building services?
- Indicative specifications
- Indicative sustainability requirement’s
- Initial risk register
What constitutes a cost estimate?
Facilitating works
Building works
Main contractor preliminaries
Main contractor overheads and profit
Project design team fees
Other project costs
Risk allowance
Inflation
Total
What does the base cost include?
Excludes risk and inflation
Facilitating works
Building works
Main contractors preliminaries
Main contractor overheads and profit
Project and design fee
Other project costs
What are facilitating works?
Works need to be complete before the fit out can commence
Demolition
Hoarding
Where would you use a functional unit method?
Retail
Hotel
Student accommodation
What is included within ‘other costs’
Costs not directly associated with the building but needed for the development
Land acquisition, fees for letting agent, planning permission costs
What is the purpose of a cost plan?
To set element cost targets
To control the design development (affordability)
Ensure value for money