Contract Practice Flashcards
Can you explain how the Local Democracy, Economic Development and Construction act affects construction contracts?
Employer/Contract Administrator (“paying party”) must issue a payment notice no later than 5 days after due date
Payment notice must specify the sum (even if its zero)
The sum notified becomes payable (subject to ‘Pay Less’)
Paying party must notify if they intend to issue a Pay Less
What did the Local Democracy, Economic Development and Construction act supersede?
Construction Act
Can you explain what the changes were from the construction act to the local democracy, economic development and construction act?
Can you explain the main differences between JCT and NEC?
JCT is a suite whereas NEC has 6 main options
There are different roles (e.g., project manager in NEC is the Employer’s agent or Contract administrator in JCT)
There is not quantity surveyor in NEC
Changes are compensations events in NEC and Variations in JCT
The programme is a contract document in NEC
What factors would you consider when advising a client on contract selection?
The type of procurement (e.g., design and build is generally suited to D&B contracts)
Size, value and complexity of the works (bigger more complex projects require different contract provisions)
What are the main differences between the contracts you have worked on?
JCT MWD did not have provisions for bonds, sectional completion and had different contract documents
What is a collateral warranty and where might it be used?
A collateral warranty is a mechanism which creates a contractual link between a party in the main contract and a third party beneficiary). So in the event of defects the Employer or funder has a link with the party who undertook the design or construction.
We used a collateral warranty on Dyson and Okehampton where there were elements of the contractor’s design portion.
What else can you use in place of a collateral warranty?
Third Party Rights Act can be used in the same principle as a collateral warranty but I would not advise relying on the court system to adjudicate because its timely, could affect reputation and is not as straightforward
What is a bond?
A security given to the employer in the event of contract default to cover costs up to a financial limit
What types of bonds are you aware of?
Performance bond
Retention bond
Advance payment bond
Are you aware of the different types of bond redress?
On-demand bond
Conditional bond
Default bond
Can you explain the payment provision dates included in Okehampton Station Refurbishment project?
7 days before the due date the contractor issued a interim application
5 days after the due date I would issue the payment recommendation to the Contract Administrator and they would issue a Payment notice to the Client
30 days after the due date the client would make final payment to the contractor (amended to suit internal invoicing)
What contract documentation did you compile for Dyson D9?
Contract
Schedule of amendments
Employer’s Requirements (dyson standards, drawings, specifications)
Pre-construction information
Pricing document
What is included in a pre-construction information document?
- Security
- Site hoarding
- Permit to work system
- Emergency procedures
You mentioned you have a schedule of contract amendments, can you give me a few examples?
The final date for payment was amended from 14 days to 33 days to suit the client’s internal payment procedures
Key subcontractors required for design portions
What pricing options are there for a JCT ICD?
Option A - pricing schedule based on drawings and specification
Option B - contract sum analysis or schedule of rates
What is a contractor’s design portion?
A section of the works where a specialist completes design
What was the limit of liability for the contractor’s design portion on the Dyson 9 project?
£5,000,000
Why was CDP used on Dyson and what benefit did it give your client?
M&E was complex and required specialist input
What insurance was included for the Dyson D9 project and why?
Contractor’s Public liability insurance - covers injury or damage to person or property
Contractor’s professional indemnity insurance - contractors design portion
Works insurance - option C because D9 was an existing building
What different options does the JCT have for work insurance?
Option A - Joint names all risk insurance taken out by contractor
Option B - Joint names all risk insurance taken out by employer
Option C - Joint names existing structure and content insurance taken out by employer
When might an employer opt for option B or option A?
The employer may have an annual policy for different assets so it may be more cost effective to use their umbrella policy
What is liquidated damages?
Liquidated damages is a pre-estimate of revenue loss suffered by the client which is levied to the contractor if they fail to complete on time
What level of LD’s was included in the Okehampton Station Refurbishment and Dyson D9 project?
Dyson D9 = £6,000 per week
Okehampton station refurbishment = £Unliquidated damages apply (court to make decision)
What is a contract?
A binding promise written or oral by one party to fulfill an obligation to another party in return for consideration
What makes a binding contract?
Offer
Acceptance
Consideration
Intention (to create legal relations)
What are expressed and implied terms?
Expressed terms are written into the contract through negotiation
Implied terms are written into the contract by statute
What are the risks of a verbal contract?
It is more difficult to prove the specific terms and conditions
How is the NEC contract made up?
Main options
Secondary options
X clauses
Z clauses
What are the main options of the NEC?
Option A: Price contract with an activity schedule
Option B: Priced contract with a bill of quantities
Option C: Target cost contract with an activity schedule
Option D: Target cost contract with a bill of quantities
Option E: Cost reimburseable contract
Option F: Management contract
What are the main contracts included within the JCT suite?
Standard building contract
Intermediate building contract
Minor works building contract
Design and build contract
Prime cost contract
Management building contract
What are the headings within a typical JCT contract?
Recitals ~ Recites facts including works, project etc
Articles ~ Contractor’s obligation, contract sum, roles,
Contract Particulars ~ key information (base date, practical completion, payment dates, retention, insurance, liquidated damages)
Attestation ~ execution of contract (under hand or deed)
Contract conditions ~ definitions and interpretations of clauses
Schedules ~
If there is no due date specified within the Contract Particulars what date does the due date become?
One month after date of possession
Can you give me an example of when a ‘Pay Less’ might be used?
Liquidated Damages
What are fluctuation clauses?
Provisions in the contract for monetary adjustments made to the original contract prices to compensate for changes in pricing levels at a macro-economic level
What is an extension of time?
An extension to the programme due to a relevant event
What’s the difference between a relevant event and relevant matter?
A relevant event is related to time and not always subject to monetary claim. Whereas a relevant matter is the employer is at fault for effecting contractors progress and consequently receives a monetary claim