Contract Practice Flashcards

1
Q

Can you explain how the Local Democracy, Economic Development and Construction act affects construction contracts?

A

Employer/Contract Administrator (“paying party”) must issue a payment notice no later than 5 days after due date
Payment notice must specify the sum (even if its zero)
The sum notified becomes payable (subject to ‘Pay Less’)
Paying party must notify if they intend to issue a Pay Less

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What did the Local Democracy, Economic Development and Construction act supersede?

A

Construction Act

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Can you explain what the changes were from the construction act to the local democracy, economic development and construction act?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Can you explain the main differences between JCT and NEC?

A

JCT is a suite whereas NEC has 6 main options

There are different roles (e.g., project manager in NEC is the Employer’s agent or Contract administrator in JCT)

There is not quantity surveyor in NEC

Changes are compensations events in NEC and Variations in JCT

The programme is a contract document in NEC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What factors would you consider when advising a client on contract selection?

A

The type of procurement (e.g., design and build is generally suited to D&B contracts)

Size, value and complexity of the works (bigger more complex projects require different contract provisions)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the main differences between the contracts you have worked on?

A

JCT MWD did not have provisions for bonds, sectional completion and had different contract documents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a collateral warranty and where might it be used?

A

A collateral warranty is a mechanism which creates a contractual link between a party in the main contract and a third party beneficiary). So in the event of defects the Employer or funder has a link with the party who undertook the design or construction.

We used a collateral warranty on Dyson and Okehampton where there were elements of the contractor’s design portion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What else can you use in place of a collateral warranty?

A

Third Party Rights Act can be used in the same principle as a collateral warranty but I would not advise relying on the court system to adjudicate because its timely, could affect reputation and is not as straightforward

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a bond?

A

A security given to the employer in the event of contract default to cover costs up to a financial limit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What types of bonds are you aware of?

A

Performance bond
Retention bond
Advance payment bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Are you aware of the different types of bond redress?

A

On-demand bond
Conditional bond
Default bond

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Can you explain the payment provision dates included in Okehampton Station Refurbishment project?

A

7 days before the due date the contractor issued a interim application

5 days after the due date I would issue the payment recommendation to the Contract Administrator and they would issue a Payment notice to the Client

30 days after the due date the client would make final payment to the contractor (amended to suit internal invoicing)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What contract documentation did you compile for Dyson D9?

A

Contract
Schedule of amendments
Employer’s Requirements (dyson standards, drawings, specifications)
Pre-construction information
Pricing document

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is included in a pre-construction information document?

A
  • Security
  • Site hoarding
  • Permit to work system
  • Emergency procedures
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

You mentioned you have a schedule of contract amendments, can you give me a few examples?

A

The final date for payment was amended from 14 days to 33 days to suit the client’s internal payment procedures

Key subcontractors required for design portions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What pricing options are there for a JCT ICD?

A

Option A - pricing schedule based on drawings and specification

Option B - contract sum analysis or schedule of rates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is a contractor’s design portion?

A

A section of the works where a specialist completes design

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What was the limit of liability for the contractor’s design portion on the Dyson 9 project?

A

£5,000,000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Why was CDP used on Dyson and what benefit did it give your client?

A

M&E was complex and required specialist input

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What insurance was included for the Dyson D9 project and why?

A

Contractor’s Public liability insurance - covers injury or damage to person or property

Contractor’s professional indemnity insurance - contractors design portion

Works insurance - option C because D9 was an existing building

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What different options does the JCT have for work insurance?

A

Option A - Joint names all risk insurance taken out by contractor
Option B - Joint names all risk insurance taken out by employer
Option C - Joint names existing structure and content insurance taken out by employer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

When might an employer opt for option B or option A?

A

The employer may have an annual policy for different assets so it may be more cost effective to use their umbrella policy

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is liquidated damages?

A

Liquidated damages is a pre-estimate of revenue loss suffered by the client which is levied to the contractor if they fail to complete on time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What level of LD’s was included in the Okehampton Station Refurbishment and Dyson D9 project?

A

Dyson D9 = £6,000 per week
Okehampton station refurbishment = £Unliquidated damages apply (court to make decision)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
What is a contract?
A binding promise written or oral by one party to fulfill an obligation to another party in return for consideration
26
What makes a binding contract?
Offer Acceptance Consideration Intention (to create legal relations)
27
What are expressed and implied terms?
Expressed terms are written into the contract through negotiation Implied terms are written into the contract by statute
28
What are the risks of a verbal contract?
It is more difficult to prove the specific terms and conditions
29
How is the NEC contract made up?
Main options Secondary options X clauses Z clauses
30
What are the main options of the NEC?
Option A: Price contract with an activity schedule Option B: Priced contract with a bill of quantities Option C: Target cost contract with an activity schedule Option D: Target cost contract with a bill of quantities Option E: Cost reimburseable contract Option F: Management contract
31
What are the main contracts included within the JCT suite?
Standard building contract Intermediate building contract Minor works building contract Design and build contract Prime cost contract Management building contract
32
What are the headings within a typical JCT contract?
Recitals ~ Recites facts including works, project etc Articles ~ Contractor’s obligation, contract sum, roles, Contract Particulars ~ key information (base date, practical completion, payment dates, retention, insurance, liquidated damages) Attestation ~ execution of contract (under hand or deed) Contract conditions ~ definitions and interpretations of clauses Schedules ~
33
If there is no due date specified within the Contract Particulars what date does the due date become?
One month after date of possession
34
Can you give me an example of when a ‘Pay Less’ might be used?
Liquidated Damages
35
What are fluctuation clauses?
Provisions in the contract for monetary adjustments made to the original contract prices to compensate for changes in pricing levels at a macro-economic level
36
What is an extension of time?
An extension to the programme due to a relevant event
37
What’s the difference between a relevant event and relevant matter?
A relevant event is related to time and not always subject to monetary claim. Whereas a relevant matter is the employer is at fault for effecting contractors progress and consequently receives a monetary claim
38
Can you give me some examples of relevant events?
Severe weather, COVID 19, Employer change, delayed possession of site
39
Can you give me some examples of a relevant matter?
Delayed start on site, delays in receiving instructions, discrepancies in contract documents
40
What can a contractor claim for under loss and expense?
Prolongation of preliminaries Thickening of preliminaries Distribution to labour
41
What is the main reason why building contracts include a provision for an extension of time?
To preserve the employer’s right to liquidated damages If a delay occurred caused by the employer and there was no extension of time provisions then the contractor would no longer be bound to complete by the completion date
42
What is a contract?
A binding promise written or oral by one party to fulfill an obligation to another party in return for consideration
43
What makes a binding contract?
Offer Acceptance Consideration Intention (to create legal relations)
44
What are expressed and implied terms?
Expressed terms are expressly agreed in a building contract Whereas implied terms are not stated within the contract but implied through statue
45
What are the risks of a verbal contract?
It is more difficult to prove the specific terms and conditions
46
What is the difference between assignment and Novation?
Assignment is the transfer of rights Novation is the transfer of rights and obligations
47
Where would you use assignment?
Specialist work
48
Does Novation and assignment need to be contractually agreed?
Novation does Assignment doesn’t
49
What is a collateral warranty?
A document which creates a contractual link between a main body of a contract and a third party
50
Where might you advise a client to use a collateral warranty?
Where a consultant, contractor or sub-contractor has offered services to a third party to ensure there is a resolution for defect claim
51
What are step-in rights?
Step in rights allow on party to take the place of another. For example a funder can step into the place of a insolvent developer in the event of defects with a consultant, contractor or subcontractor
52
What is an alternative to collateral warranties?
Third-party rights
53
Are third party rights act implied or expressed terms within a contract?
Expressed
54
What is the typical period of a collateral warranty?
12 years after practical completion
55
What is your understanding of a net contribution clause?
Associated with collateral warranties Where two or more parties are jointly liable for the same loss or damage on a fair and reasonable basis
56
Can you give me an example of an expressed term?
Valuation date Final date for payment
57
Can you give me an example of an implied term?
Payment notice date
58
What are letters of intent?
Documents used when a contract cannot be signed before the start of a project
59
When should a letter of intent be considered?
A a last resort for a delay of construction works due to contract negotiations
60
What different types of letters of intent are there?
Recognition to contract Consent to spend Comfort letters
61
What is a recognition of contract (letter of intent)?
Used to recognise the existence of a build contract before the document has been signed and binded
62
What happens if a contractor rejects the contract but has started works under a ‘recognition of contract’ letter of intent?
Employer is liable for contractors profit and loss
63
How is a contract underhand different from a deed?
Underhand contracts are signed by both parties A deed is signed by both parties, witnessed and sealed
64
What are liquidated damages?
Pre-estimated loss of revenue should the contractor not fulfil their obligations by practical completion
65
How would you advise a client if they informed you their LAD’s rate was £100,000 per week?
1. I would check this is a genuine estimate of loss 2. Inform them that the rate could be unenforceable if it is not a genuine estimate
66
What must be in place before an employer can apply liquidated damages?
A certificate of non-completion
67
How are liquidated damages applied?
Through a pay-less notice
68
What is the defects liability period?
A period stated within the contract for the contractor to rectify any defects which may arise Generally 12-month period
69
How are defects during the defect liability period delay with if the contractor fails to rectify?
The retention monies can be used to employ a contractor to rectify the defects
70
If there is a discrepancy between the employers requirements and contractors proposals, what prevails?
Contractors proposals prevail
71
What is a bespoke contract?
Contract conditions drafted specifically for a project
72
What advantages do standardised contracts have over bespoke contracts?
More legal precedent More robust Fairer
73
What are the main elements of a JCT contract?
RAPACS Recitals Articles Contract particulars Attestation Conditions Schedules
74
What are the main elements within the conditions?
Definitions of the work, Carrying out the works, Control of the works, Payment, Variations, Injury, damage and insurance, Assignment, third party rights and collateral warranties, Termination, Settlement of disputes
75
What does completion mean on a construction contract?
Where the contractor has fulfilled their obligations including works and documents (e.g., operation and maintenance manuals, collateral warranty)
76
Why is practical completion important?
It triggers several contractual consequences Client takes possession and co trim of building Cessation of liquidated damages Client responsible for insuring the works Commencement of defect liability period Bonds and guarantees expire A requirement for an account for the works to be made
77
What is the difference between practical completion and beneficial occupation?
Practical completion is where all obligations have been satisfied Beneficial occupation is client occupation if intended use is satisfied
78
When can partial possession be withheld?
If the possession will affect the contractors ability to perform its obligations
79
What are patent defects?
Defects which are known at practical completion
80
What are latent defects?
Defects which arise months or years after Practical Completion
81
What is the limitation period for latent defects?
Depends on the execution of the contract Under hand = 6 years Deed = 12 years
82
What is a final account?
A statement agreed by the contractor and client stating the full and final amount of all project works including the contract and variable costs
83
What must be in place before liquidated damages can be deducted?
Non completion certificate Pay less notice
84
What two forms of damages can a client take if the contractor is late?
Liquidated damagea Unliquidated damages
85
What is the difference between liquidated and unliquidated damages?
Liquidated damages is a pre-estimated figure included in the contract for genuine loss Unliquidated damages is actual loss estimated by the employer and determined by court
86
How does liquidated damages apply to sectional completion?
Separate liquidated damages for all sections
87
What is your understanding of ‘time at large’?
Where no completion date is specified within the contract and the contractor can finish within a reasonable time
88
What are the disadvantages with ‘time at large’?
The client cannot apply for damages
89
Is a contractor liable for damages of completion has been issued with outstanding works?
No Once completion is issued liquidated damages cannot be applied
90
How are damages typically calculated?
Loss of revenue Leasing alternative accommodation
91
How are liquidated damages deducted?
Pay-less notice (HGCRA)
92
What happens if the loss is higher than the liquidated damages stated within the contract?
The employer must suffer the loss
93
What happens if an extension of time has not been confirmed but the practical completion date has not been met?
Liquidated damages can be applied Damages can be recalculated and refunded in the next interim valuation
94
What advise would you give to a client regarding a ‘nil’ rate for liquidated damages
Risk Reduces contractors incentive to meet the completion date Prevents employer recovering losses