Design Economics and Cost Planning Flashcards
What is the difference between a cost plan and Order of Cost Estimate?
- A cost plan the construction costs broken down into the elements to understand the cost limit of each element of the building. Provides a frame of reference to develop the the design and maintain cost control.
- An estimate is a forecast of construction cost.The purpose of an order of cost estimate is to establish affordability of a proposed development for a client.
What design detail would you expect in RIBA Stage 0 (Strategic definition and brief)?
- Stage 0 is about determining the best means of achieving the client’s requirements.
- An open mind is required because a building might not be the most appropriate solution.
- Stage 0 is not about design or the practical details. It focuses on making the right strategic decisions and capturing them in a Business Case. The stage involves considering the pros and cons, Project Risks and Project Budget for a range of options and, where necessary, carrying out Site Surveys and corresponding planning appraisals, before undertaking a comparative analysis and recommending and ratifying the best option for delivering the Client Requirements.’
What design detail would you expect in RIBA Stage 1 (Preparation and brief)?
Stage 1 is about developing the detail of the brief and making sure that everything needed for the design process is in place before Stage 2. This includes ensuring that the brief can be accommodated on the site. Involves:
- Developing an initial project brief. This may include; considering feedback from previous projects, defining overall spatial requirements, carrying out surveys and quantifying the budget.
- Carrying out feasibility studies.
- Undertaking a project risk assessment, including; planning risks, programme and procurement strategy.
- Assembling the project team and defining their roles and responsibilities.
What design detail would you expect in RIBA Stage 2 (concept design)?
Stage 2 is about getting the design concept right and making sure that the look and feel of the building is proceeding in line with the client’s vision, brief and budget. Includes:
- The design concept.
- Outline specifications.
- Schedules of accommodation.
- A planning strategy.
- The cost plan.
- Procurement options.
- Programme and phasing strategy.
- Buildability and construction logistics.
What design detail would you expect in RIBA Stage 3 (detailed design)? - Now known as spatial coordination
The purpose of Stage 3 is to spatially coordinate the design before the focus turns to preparing the detailed information required for manufacturing and constructing the building. Includes:
- Schedules of accommodation, including occupancy numbers for each space.
- Key assemblies, component drawings and schedules
- Structural plans sections, elevations and specifications:
- Building services plans, sections and elevations
- Fire strategy,
What design detail would you expect in RIBA Stage 4 (technical design)?
Stage 4 is about developing the information required to manufacture and construct the building. This requires information from the design team and the specialist subcontractors employed by the contractor, regardless of which procurement route is used. Includes:
- By the end of the stage the architectural, structural and mechanical services design and specifications should describe all the main components of the building and how they fit together,
- any performance specified work should be defined and there should be sufficient information for applications for statutory approval to be completed.
- Room data sheets are also likely to have been prepared along with outline technical specifications.
What design detail would you expect in RIBA Stage 5 (construction)? now known as Manufacturing and construction.
Stage 5 is when the building is manufactured and constructed.
What design detail would you expect in RIBA Stage 6(handover and close out)?
By Stage 6 the building will be in use and the emphasis of the project team will have switched to closing out any defects and completing the tasks required to conclude the Building Contract.
What design detail would you expect in RIBA Stage 7 (in use)?
This is the period when the building is in use, lasting until the building reaches the end of its life.
What can you do to adjust costs for time and location?
Indices can be used which set a base for project data. Indices that can be used are cost and time.
How did you ensure NRM compliance with internal walls?
This is measured on the centre line of the internal wall or partition. No deduction is made for door openings, screens or the like. The internal skin of external wall is included within external wall.
How do you know that quantities from BIM are correct?
When checking my quantities, I always cross check with drawings, for example, the perimeter by height for external wall areas.
What effect did the precast concrete panels have on the main contractor preliminaries?
Using precast concrete panels meant that there would be less time on site as it is quicker construction than other methods such as traditional brick. This would reduce the preliminary running costs
Why are costs different in different locations?
- Wages
- Site logistics
- Proximity to services and supplies
- Availability of labour
What is the BCIS ?
BCIS is the Building Cost Information Service of the Royal Institution of Chartered Surveyors (RICS). It is described by RICS as ‘the leading provider of cost and price information to the construction industry and anyone else who needs comprehensive, accurate and independent data.’
How did you go about carrying out the cost plan?
- Understand design – which RIBA stage is it? – check NRM which lists what is required for stage 2 and stage 3
- Query design
- Split elements to team – order of take-off – agree timescales
- Begin quantification
- Prelims
- OHandP, Contingency
- Market testing/ rate testing
- Assumptions, exclusions, drawing list, exec summary
- Include benchmarking exercises
What is the importance of a cost plan?
- To understand in an elemental form the costs of the project and how to control the costs.
- To inform the design team in changes to reflect the cost.
What is a cost analysis?
A systematic breakdown of existing cost data to allow for an extent of examination and comparison with other similar projects.
What are external factors that can affect cost?
1) location of the building project
2) state of the construction economy (and general economy) at the point in time when construction cost is established
What can effect the cost of a building?
- floor areas
- efficiency ratios
- number of storeys
- basement
- functional units
- number of weeks to complete
- method of tender ( cost reimbursement, GMP, lump sum)
- procurement and risk associated
- location of project
- base date for project
- number of tenderers
- sustainability rating
- type of building
- outline specification of the works - pike v strip or concrete v steel
How can cost data be shown?
- tables
- trend charts and graphs
- pie charts
- scatter diagrams
- waterfall diagrams
Why is the contract duration a factor of cost?
- A longer contract may increase the cost of preliminaries (insurances, contractors compound, staffing etc).
- Constructing under time pressure may carry a price premium ( working out of hours, out of sequence, number of different contractors).
What are abnormals?
Costs which are considered project specific. Classified as such because they have a notable cost consequence.
What is the difference between life cycle costing and whole life costing?
- Life cycle cost accounts for all relevant costs over a defined period of time (the period of analysis).
- Whole life costs can include costs associated with the provision of construction works that are not included in the clients costs.
What are the three types of lifecycle costs?
- construction costs
- maintenance costs (hard facilities management - redecoration, periodic inspection, periodic maintenance, unscheduled corrective and responsive maintenance, planned and preventive maintenance)
- operation costs (soft facilities management - all costs incurred in running and managing the facility - IT services, cleaning, waste management, catering, rent, insurances, utilities)
What is life cycle costing?
Life cycle cost accounts for all relevant costs over a defined period of time (the period of analysis).
Where can you get LCC data from?
- Unstructured historical data - estate managers
- Structured historical data- BCIS running cost analysis
- Data from modelling
- data from manufacturers, suppliers and specialist contractors
What is an order of cost estimate?
The determination of possible cost of a building(s) early in design stage in relation to the employer’s fundamental requirements. This takes place prior to preparation of a full set of working drawings or bills of quantities and forms the initial build-up to the cost planning process.’
What is BIM?
Building information modelling.
NOT a software - It is a PROCESS
It provides architecture, engineering and construction professionals information and tools to efficiently plan, design, construct and manage buildings and structures