Conflict avoidance, management and dispute resolution procedures Flashcards

1
Q

What is your first step in resolving a dispute?

A
  1. Define a source of the dispute (get more information about what cause the problem) in order to resolve the dispute amongst the parties involved.
  2. Seek Third party to resolve the dispute
  3. Review the contract
  4. Try to use mediation or negotiation first
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How does Arbitration differ to Adjudication?

A

Arbitration:

  • a procedure in which both sides agree to let an impartial third party, the arbitrator, decide the case
  • the arbitrator may be a lawyer, or may be an expert in the field of the dispute, or in some cases, an arbitration panel
  • The arbitrator’s decision, known as an award, is legally binding and can be enforced through the courts. Normally, there is no appeal, however there are exceptions in which appeals may be accepted.
  • Arbitrators have the power to ascertain facts rather than just listen to submissions, and to order costs.
  • Arbitrations are typically conducted by either one or three arbitrator(s), referred to in each case as the “tribunal”. The tribunal is the equivalent of a judge (or panel of judges) in a court action.

Adjudication:

  • the decision is the responsibility of a third party adjudicator selected by the parties to the dispute.
  • Adjudication decisions are binding unless and until they are revised by subsequent arbitration or litigation after practical completion, or by agreement between the parties (hence the term ‘pay now argue later’)
  • There is no right of appeal and limited right to resist enforcement. Generally, adjudicators do not have the power to award costs (other than their own fees and expenses).
  • Adjudication must adhere to strict timescales and typically takes up to 28 days.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Are both or either of these options final and binding? (Arbitration and Adjudication)

A

The arbitrator’s decision, known as an award, is legally binding and can be enforced through the courts.

Adjudication decisions are binding unless and until they are revised by subsequent arbitration or litigation after practical completion, or by agreement between the parties (hence the term ‘pay now argue later’). There is no right of appeal and limited right to resist enforcement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How much do these costs? (Arbitration and Adjudication)

A

There is no set rate for an adjudicator, with a range of hourly rates being charged, but the cost of the adjudication will very much depend on the size, nature and complexity of the dispute. Adjudicator’s fee may vary from £250 to £1,000 per hour.

Arbitration fees are higher as they include registration/administration fee, the fees of the Arbitral Tribunal, case administrators, counsel (as per London Court of International Arbitration’s ) and also it takes longer so consequently fee are cover over longer period of time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Who pays for the dispute resolution procedures?

A

Adjudication - The parties will be jointly and severally liable to pay the adjudicator a reasonable amount in respect of fees for work reasonably undertaken and expenses reasonably incurred by him.

NEC Suite of Contract: The Parties are free to agree with the Adjudicator that he should decide apportionment. If Option W1, or they don’t agree, the Parties pay in equal shares. If Option W2 is used, the Adjudicator must decide (clause 3.2)

Arbitration - The default position is that each party will pay one half of the total costs of the arbitrator/arbitration. Each will be responsible for their own legal costs.

Mediation - The usual practice is for both /all parties who are in dispute to pay equally towards the mediation fee.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Who would decide who the mediator would be in mediation?

A

Parties are free to choose their mediator. As per RICS guidance on Mediation - Parties should choose a mediator who is experienced in the sort of dispute with which they are dealing, and an effective way of finding one is often by personal recommendation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How has your reading of the RICS guidance note on CA and DR assisted you in your role?

A

By reading RICS Professional guidance on Conflict avoidance and dispute resolution in construction, I understand the the principles of conflict avoidance process and I was able to implement them into my work before the issue arose. This included good payment practice, record keeping and regular reporting and proactivity.

In addition, I was aware of different dispute resolution techniques (negotiation, mediation, expert determination, adjudication, arbitration, litigation, dispute boards and I was able to advice which of them would be applicable to our contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What did you include in the preparation of documents for a potential adjudication on the Project Winchester scheme?

A

I produce a report summarizing the issue. The disagreement was regarding the value implemented as a CE through PMI. Therefore this included the evidence of relevant communication issues to and from the Contractor, references to relevant clauses within the contract allowing the PMI, basis of the PMI assessment relevant calculation and supporting documentations (benchmarking, cost analysis).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What was the ADR process on this contract? (Project Winchester)

A
  • Dispute resolution option W2 was incorporated into the contract on Project Winchester, which means that the Adjudication was a form of dispute resolution. The adjudication nominating body stated within Contract Data Part one was the RICS.
  • the process of adjudication was detailed in Clause W2.3
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What were the timescales if an adjudication was presented to your client?

A

In line with the NEC3 contract and the Construction Act:

  • before a Party refers dispute to the Adjudicator, they gives a notice of adjudication to the other Party with a brief description of the dispute and the decision which they wish adjudicator to make
  • if the adjudicator is named in the contract data, the part sends a copy of the notice of adjudication to the Adjudicator when it is issued. the adjudicator notify the parties within 3 day whether or not he or she is able to decide the dispute (NEC contract)
  • Within 7 days of the Notice of Adjudication the Adjudicator should be appointed and the Referral Notice Served by the Referring Party the Referral Notice should include the outline of the Referring party’s case with supporting evidence and documentation.
  • Within 7 days of the Referral Notice (can be extended to 14 days) the Responding party must serve their response including supporting documentation and evidence.
  • The adjudicator may request further documents , site visit or oral hearing in order to make a decision
  • The adjudicator decision must be given within 28 days of the Referral Notice and it binding unless it is challenged by litigation or arbitration.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What was your advice on the NSN Project adjudication regarding entitlement?

A
  • In accordance with the Contract, Consultants were entitled to two sets of rates: one where working at the office provided by the Employer (lower rate) and at the office not provided by the Employer (higher rate).
  • The dispute arose when due to Covid pandemic the Consultants were not longer able to work from the Employer’s Office and were working from Home instead. The framework agreement specifically described the office not provided by the Employer as the consultant’s head office and not a home office.
  • It was also mentioned that the rate when working at the office not provided by the Client was higher due to additional ongoing cost (electricity , desk, office rent) that the consultant would incur when working from the Head Office.
  • Whilst when working from home there was no evidence of any additional cost incurred by the consultant. Specifically, as cost of setting up the home office due covid pandemic and additional equipment required was already covered by another CE.
  • Therefore, my advice was that although the contract did not specified what rates should be used when working from home, there was no evidence provided that the Consultant incur any additional cost due to working from home. Also, the only reason why the Consultant could not work from the Client office was the government restriction.
  • The Client decided to conduct negotiation with the Consultant and agreed on ‘middle rate’ when working from home during the pandemic.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How did you ascertain the requirements to provide that
evidence? (NSN Project)

A

I was involved in discussions regard the issue with the Consultant based on which I produce a report which included relevant framework and contract clauses as an evidence. In addition, I include the pervious CE issued to cover the cost of setting up the home offices for the Consultant’s employees and its assumptions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the RICS guidance on Conflict avoidance and dispute resolution in construction?

A
  • This guidance note summarises what is meant by conflict avoidance and dispute resolution.
  • It identifies the key issues that all surveyors should understand in respect of these distinct substantive areas and dispute avoidance processes.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is Scott Schedule?

A

A Scott schedule is essentially a table with inputs from both the claimant and respondent. Typically the claimant will set out their argument first, then the schedule is passed to the respondent to set out their response. This requires a degree of collaboration between the parties.

In the event that the dispute reaches the courts, the final column in the schedule is provided for the judge to give their decision against each item.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the most common forms of dispute resolutions in construction?

A
  • Negotiation
  • Mediation
  • Expert determination
  • Adjudication
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is negotiation?

A
  • Negotiation is a process where parities work out between them how to resolve any issues.
  • Power to settle is with the parties.
  • In the construction industry, negotiation is required at almost every stage of a project, from acquiring land and obtaining planning permission, to making appointments, awarding contracts, negotiating change orders and extensions of time, resolving disputes, and so on.
17
Q

What is mediation?

A
  • Mediation is a procedure in which the parties discuss their disputes with the assistance of a trained impartial third person(s) who assists them in reaching a settlement.
  • The power to settle remains with the parties, but the process is led by the mediator.
18
Q

What is the difference between negotiation and mediation?

A
  • during negations parties work out between themselves to resolve the issues, when mediation involved the third party to facilitate discussions and to led the process.
  • negotiations usually involve direct contract between the parties when during mediation the mediator meets with the parties separately.
19
Q

What is adjudication?

A
  • Adjudication is a procedure for resolving disputes. It is provided by a third party adjudicator selected by the parties in dispute.
  • Adjudication decisions are binding unless and until they are revised by arbitration or litigation. There is no right of appeal and limited right to resist enforcement.
  • Generally, adjudicators do not have the power to award costs (other than their own fees and expenses).
    Adjudication must adhere to strict timescales and typically takes up to 28 days.
20
Q

What is arbitration?

A
  • a procedure in which both sides agree to let an impartial third party, the arbitrator, decide the case
  • the arbitrator may be a lawyer, or may be an expert in the field of the dispute, or in some cases, an arbitration panel
  • The arbitrator’s decision, known as an award, is legally binding and can be enforced through the courts. Normally, there is no appeal, however there are exceptions in which appeals may be accepted.
  • Arbitrators have the power to ascertain facts rather than just listen to submissions, and to order costs.
  • Arbitrations are typically conducted by either one or three arbitrator(s), referred to in each case as the “tribunal”. The tribunal is the equivalent of a judge (or panel of judges) in a court action.
21
Q

What is litigation?

A
  • litigation is the process of taking a case to a court of law so that a judgment can be made
  • During litigation, a judge makes the final decisions for the parties unless they settle before trial. Settlement can happen at any point during the litigation process.
  • The process includes: issuing claim at the court, response and defense, court case management, evidence (including disclosure of evidence , witness statement and expert evidence), trail, decision/judgment
22
Q

Which court deals with construction disputes?

A

The Technology and Construction Court (TCC) is a specialist court, which deals principally with technology and construction disputes.

23
Q

What are the parties of adjudication?

A
  • Referring party
  • Responding Party
  • Adjudicator
24
Q

What are responsibilities of each party?

A

Referring party
• must serve the Notice of Adjudication including key information such as details of the parties, the contract , the nature of the dispute, the remedy sought;
• the adjudicator should be appointed within 7 days of the Notice of adjudication.
• must serve referral notice within 7 days of the notice of Adjudication – this should set up the referral party case and other supporting information
Responding Party
• within 7 days of the Referral Notice the Responding Party must serve their response together with evidence
Adjudicator
• the adjudicator must give this decision within 28 days
• the decision is binding unless challenged by litigation or arbitration

25
Q

How NEC4 deals with Dispute Resolution? How it impacts on the project management?

A
  • There are three dispute resolution options included in NEC4 Suite of Contract; these are
    • W1 – Used when adjudicator is the method of dispute resolution and the UK Housing Grants, Construction and Regeneration Act 1996 does not apply.
    • W2 – used when adjudication is the method of dispute resolution and the UK Housing Grant, Construction and Regeneration Act applies
    • W3 – Used when a Dispute Avoidance Board is the method of dispute resolution and the UK Housing Grants, Construction and Regeneration Act 1996 does not apply.
  • NEC4 introduces the concept of Senior Representatives. The idea is that Senior Representatives of the parties meet and attempt to resolve the dispute before there is an adjudication. This applies to both options W1 and W2. The Senior Representatives for each party are named in the Contract Data. There is provision for two Senior Representatives from each party.
  • In addition, NEC4 offers an improved provision for dispute resolution procedures, with new processes to help parties avoid the time and costs of formal disputes. The new Dispute Resolution Service Contract (DRSC) will therefore replace the NEC3 Adjudicator’s Contract.

In my option, new option w3 as well as concept of Senior Representative encourage a good management and resolving issues at the project level.

25
Q

How NEC4 deals with Dispute Resolution? How it impacts on the project management?

A
  • There are three dispute resolution options included in NEC4 Suite of Contract; these are
    • W1 – Used when adjudicator is the method of dispute resolution and the UK Housing Grants, Construction and Regeneration Act 1996 does not apply.
    • W2 – used when adjudication is the method of dispute resolution and the UK Housing Grant, Construction and Regeneration Act applies
    • W3 – Used when a Dispute Avoidance Board is the method of dispute resolution and the UK Housing Grants, Construction and Regeneration Act 1996 does not apply.
      *
26
Q

How NEC3 deals with Dispute Resolution?

A

There are two options within NEC3:

  • Option W1 – Despite resolution procedure (used unless the UK Housing Grants, Construction and Regeneration Act 1996 applies)
  • Option W2 - Despite resolution procedure (used in the UK when Housing Grants, Construction and Regeneration Act 1996 applies)
27
Q

What is expert determination?

A

Expert determination is a procedure in which a dispute or a difference between the parties is submitted, by agreement of the parties, to one [or more] experts who make a determination on the matter referred to it [them]. The determination is binding, unless the parties agreed otherwise.

28
Q

What is the difference between NEC3 & NEC4 with regards to Dispute Resolution?

A
  • additional Option W3 in NEC4
  • no role of Senior Representative in NEC3 Option W1 &W2
  • Under clause W2 of NEC4, an adjudicator is appointed under the NEC Dispute Resolution Service Contract (DRSC) and therefore replace the NEC3 Adjudicator’s Contract.
29
Q

What is ADR?

A

Alternative dispute resolution (ADR) refers to ways of resolving disputes between consumers and traders that don’t involve going to court

30
Q

What are the common methods of ADR?

A
  • mediation
  • negations
  • expert determination
  • adjudication
  • arbitration
31
Q

Explain how to make a claim for an adjudication?

A
  1. Start with identifying the dispute and right to adjudicate and establish if adjudication is right method of dispute;
  2. Identify contract, parties, nominating body, procedure to follow
  3. Identify legal basis of your claim, analyze the risks
  4. Draft the Referral Notice and Notice of Adjudication including collection of all evidence and supporting information
  5. Appoint professionals if required
  6. Serve Notice of Adjudication
  7. Appoint the Adjudicator
  8. Serve Referral Notice
32
Q

What is the referral notice and what is included?

A
  • Once a Notice of Adjudication has been given, and a person has been appointed to act as an adjudicator, the dispute must be formally referred to the adjudicator.
  • The Referral Notice is the referral of the dispute in writing to the adjudicator, and its purpose is to set out clearly and concisely the referring party’s case. It is, effectively, the referring party’s pleadings, evidence and submissions all rolled into one.
  • The referring party must serve referral notice within 7 days of the notice of Adjudication – this should set up the referral party case and other supporting information.
33
Q

How the Construction act is relevant to adjudication?

A
  • The Adjudication procedure for the construction works was introduced by the Construction Act.
  • In particular section 108 and 108A refers to right to adjudication and adjudication cost, it set out the processes and timescale of the adjudication process
  • Contractual adjudication procedures must comply with Section 108 of the Housing Grants, Construction and Regeneration Act.
  • If the parties do not agree procedural rules which comply with the Housing Grants, Construction and Regeneration Act then the Act imposes the rules set out in the Scheme for Construction Contracts.
34
Q

What is Scheme for Construction Contracts?

A

The Scheme for Construction Contracts (England and Wales) Regulations (also known as The Scheme for Construction Contracts) is a scheme which applies when construction contracts do not comply with the Housing Grants, Construction and Regeneration Act.

35
Q

What are the provision/entitlements within the Construction Act with regards to the payments?

A
  • The right to be paid in interim, periodic or stage payments for project over 45 days unless otherwise agreed.
  • The right to be informed of the amount due, or any amounts to be withheld - Payment Notice to be issued and include the amount due and basis of the calculations (Section 110). This must be issued no later than 5 days after the payment due date, even if no amount is due.
  • 7 calendar days before final date for payment, the client must issue a pay less notice if they intend to pay less than the amount set out in the payment notice, setting out the basis for its calculation
  • Final date fir payment is 17 calendar days from due date.
  • The right to suspend performance for non-payment.
36
Q

What are the Payment provisions/process within Scheme for Construction Contract?

A
  • Payment notice: Within five calendar days after the due date, the payer (or the specified third person) must give a payment notice to the payee specifying the amount the payer (or the specified third person) considers to be due on the due date and the basis for that sum.
  • Payment notice served by the payee: If the payer (or specified third person) fails to serve a payment notice within five calendar days after the due date, the payee can issue a payment notice. This is more commonly referred to as a ‘default payment notice’.
  • Pay less notice: If the payer intends to pay less than the notified sum then the payer (or specified third party) may serve a ‘pay less notice - 7 calendar days before final date for payment.
  • The payee should receive the sum specified in the payment notice or pay less notice by the final date for payment (17 calendar days from due date)