Design and Specification Flashcards
What is the RIBA Plan of Work?
- The RIBA plan of work organises the process of briefing, designing, constructing and operating projects into 8 stages and explains the stage outcomes, core tasks and information exchanges required at each stage.
What are the stages of the RIBA Plan of Work?
0 - Strategic definition
1 - Preparation and briefing
2 - Concept Design.
3 - Spatial Coordination
4 - Technical Design
5 - Manufacturing and construction
6 - Handover
7 - Use
What are the stage outcomes, core tasks, core statutory processes and information exchange at Stage 0 - Strategic Definition?
- Stage outcome: The best means of achieving the client requirements are confirmed.
- Core tasks:
+ Prepare client requirements.
+ Develop business case for feasible options including review of project risks and budget.
+ Undertake site appraisals. - Core statutory processes:
+ Strategic appraisal of planning considerations.
Information Exchanges:
+ Client requirements.
+ Business case.
What are the stage outcomes, core tasks, core statutory processes and information exchange at Stage 1 - Preparation and Briefing
- Stage outcomes: Project brief approved by the client and confirmed that it can be accommodated on the site.
- Core tasks:
+ Prepare client brief - including project outcomes, sustainability outcomes, quality aspirations and spatial requirements.
+ Undertake feasibility studies.
+ Agree project budget.
+ Source site information - surveys.
+ Prepare project programme. - Core statutory processes:
+ Source pre-application planning advise.
+ Initiate collation of health and safety Pre-Construction Information. - Information Exchanges:
+ Project brief.
+ Site information.
+ Procurement Strategy.
+ Responsibility Matrix.
What are the stage outcomes, core tasks, core statutory processes and information exchange at Stage 2 - Concept Design
- Stage outcome: Architectural concept approved by the client and aligned to project brief.
- Core tasks:
+ Prepare architectural concept incorporating strategic engineering requirements and aligned to cost plan, project strategies and outline specification.
+ Agree project brief derogations.
+ Undertake design reviews with client and project stakeholders. - Core statutory processes:
+ Obtain pre-application planning advise.
+ Agree route to building regulations compliance.
+ Option: submit outline planning application. - Information exchanges:
+ Project brief derogations (aspects of the design that do not need to align with the project brief).
+ Signed off stage report.
+ Project strategies.
+ Outline specification.
+ Cost plan.
What are the stage outcomes, core tasks, core statutory processes and information exchange at Stage 3 - Spatial Coordination
- Stage outcomes: Architectural and engineering information spatially coordinated.
- Core tasks:
+ Undertake design studies, engineering analysis and cost exercises to test architectural concept resulting in spatially coordinated design aligned to updated cost plan, project strategies and outline specification.
+ Initiate change control procedures (process for making any requested changes to the project to make sure they are not made unnecessarily and don’t impact negatively on project programme and cost).
+ Prepare stage design programme. - Core statutory processes:
+ Review design against building regulations.
+ Prepare and submit planning application. - Information exchanges:
+ Signed off stage report.
+ Project strategies.
+ Updated outline specification.
+ Updated cost plan.
+ planning application.
What are the stage outcomes, core tasks, core statutory processes and information exchange at Stage 4 - Technical Design
Stage outcomes: All design information required to manufacture and construct the project completed.
- Core Tasks:
+ Develop architectural and engineering technical design.
+ Prepare and coordinate design team building system information.
+ Prepare and integrate specialist subcontractor building systems information.
+ Prepare stage design programme. - Core Statutory Processes:
+ Submit Building Regulations Application.
+ Discharge pre-commencement planning conditions.
+ Prepare Construction Phase Plan.
+ Submit F10 form to HSE if applicable. - Information exchange:
+ Manufacturing information.
+ Construction information.
+ Final specifications.
+ Building Regulations Application.
What are the stage outcomes, core tasks, core statutory processes and information exchange at Stage 5 - Manufacturing and Construction?
- Stage outcomes: Manufacturing, construction and commissioning completed.
- Core tasks:
+ Finalise site logistics.
+ Manufacture building systems and construct building.
+ Monitor progress against construction programme.
+ Inspect construction quality.
+ Resolve site queries as required.
+ Undertake commissioning of building.
+ Prepare building manual. - Core statutory processes:
+ Carry out Construction Phase Plan.
+ Comply with planning conditions relating to construction. - Information exchange:
+ Building manual (O&M manual) including Health and Safety File and Fire Safety Information.
+ Practical completion certificate including defects list.
+ Asset information.
What are the stage outcomes, core tasks, core statutory processes and information exchange at Stage 6 - Handover
- Stage outcomes: Building handed over, aftercare initiated and building contract concluded.
- Core tasks:
+ Hand over building in line with Plan for Use Strategy.
+ Undertake review of project performance.
+ Undertake seasonal commissioning.
+ Rectify defects.
+ Complete initial aftercare tasks. - Core statutory processes:
+ Comply with planning conditions as required. - Information exchange:
+ Feedback on project performance.
+ Final certificate (AI).
+ Feedback from light touch post occupancy evaluation.
What are the stage outcomes, core tasks, core statutory processes and information exchange at Stage 7 - Use
- Stage outcomes: Building used, operated and maintained efficiently.
- Core tasks:
+ Implement facilities management and asset management.
+ Undertake post occupancy evaluation of building performance in use.
+ verify project outcomes including sustainability outcomes. - Core statutory processes:
+ Comply with planning conditions as required. - Information exchange:
+ Feedback from post occupancy evaluation.
+ Updated building manual including health and safety file and fire safety information as necessary.
What are preliminaries?
- They provide the description of the project to allow cost assessment and specify general conditions and requirements for execution. For example: project description, site access and parking etc.
- From the preliminaries a contractor can price for cost significant items that they need to carry out the works such as site welfare and provision of temporary services.
What are preambles?
- A preamble is an explanation of a document, commonly found in contracts, specifications and bills of quantities. It helps with the interpretation of a document.
- A preamble may include:
- Description of parties to the contract.
- A description of the competence of parties to a contract - this will include a set of general standards for the quality of goods or services required.
- Tendering procedures.
- Objectives of the project.
What is the difference between preliminaries and preambles?
- Preambles are the explanation of the works that don’t form part of the costings, preliminaries are used to describe the project and allow costing of items that are required to complete the works, for example temporary access and welfare.
What is NBS?
- The National Building Specification is a UK based company that provides specification platforms used by construction professionals to produce high quality and standardised specifications for construction projects.
Why would you use NBS?
- Allows collaboration - others can be invited to edit the document.
- Ensures consistent standard and format for all projects.
- All statutory standards are kept up to date, such as British Standards.
- Is the standard specification platform used in the UK so contractors are used to working with this form of specification.
What is NBS Chorus?
- A cloud based collaborative specification platform that is used internationally. It allows construction professionals to produce high quality specifications efficiently.
What is a schedule of works?
- A description of the work in list format often used on smaller projects or those involving alteration works prepared by designers.
What supporting documentation could you include within a specification the contractor(s)?
- Specialist surveys such as structural engineers reports, drainage surveys etc.