Case study Flashcards
What was the use class of your building?
B2 - General Industrial
How did you determine the age of the building?
- The asbestos roof was a good indicator that the property was constructed in circa 1970s when these installations were most prevalent.
- I also reviewed the planning portal to see if there were any historic planning applications for the industrial estate which there were not.
How did you know that the warehouse floor was in-situ cast? How is an in situ concrete floor slab cast?
- There were day joints present to the concrete slab which indicated the different stages that it was cast.
- In this instance, the long strip method had been used whereby the floor had been cast in two long strips. The process involves laying the concrete between formwork which defines the strip and then levelling the surface manually using a compacting beam and following the top edge of the formwork.
What would be the build up of the slab?
Typically:
- Wearing surface.
- Structural slab.
- DPM membrane.
- Hardcore sub base.
- Formation level (earth) which may have been built up using sub-grade fill.
What type of asbestos would you expect to find in the cement roof sheets?
- Chrysotile - this was confirmed by the asbestos refurbishment and demolition survey I instructed.
Were there any other ACM’s picked up by the R&D survey?
Yes:
- Chrysotile located in the adhesive backing to the vinyl floor tiles at ground floor level.
- Chrysotile located in the sink pad to the kitchen / break out area.
What did you request from the contractor following the asbestos removal?
- A written confirmation that they had removed the asbestos as identified within the asbestos R&D survey.
- A consignment notice to prove the asbestos has been disposed of as hazardous waste (double bagged and then taken) which quoted the asbestos item codes from the R&D survey itself.
Where the asbestos works notifiable?
- No, as the works were sporadic and of low intensity and carried out in such a way that workers would not be exposed to levels of asbestos beyond the legal control limit of 0.6f/cm3.
- The principal designer requested an air control certificate to ensure that levels were not breached. This was also highlighted by the PD upon review of the contractor’s original Construction Phase Plan.
How much was the dilaps settlement? What was superseded?
- £90,000
- Decorations to the existing roller shutter door (to be replaced).
- Decorations to the portion of the ancillary accommodation block that was demolished.
What is a CAT A refurbishment?
- Also known as a developer’s fit out.
- Provides generic requirements for an incoming tenant such as life safety elements and basic fittings including suspended ceilings, raised floors, carpet and lighting.
- Absent of any tenant bespoke services and finishes.
Why was single stage competitive tendering used?
- Ensured that the tendered costs would be competitive and provide good value.
- Single stage tendering reduced the overall tender period compared to two stage and provided a lump sum cost for the works meaning the client could quickly determine the capital required for the project.
- The client was used to the method and had had success with it on previous projects.
Why did you use the JCT Intermediate Contract? Why didn’t you use with contractor’s design portion?
- The works were relatively simple in nature and involved recognised basic trades.
- The client required the works to be designed on their behalf by myself with the exception of the roof specification which was compiled by Tata Steel, the client approved of this.
- Additional provisions were required such as partial possession and more detailed extension of time provisions compared to that of the MW contract.
- More detailed provisions for loss and expence provided for.
- Provision for testing and opening up - may be needed particularly for roof works.
- They want the consultant to be responsible for all design so that there is a single point of liability should there be an issue with any elements of the design. It is also why all sub-consultants are appointed by Hollis and not directly by the client. We are responsible for everything.
- For example, at Leatherhead the roof oversheet was designed by Tata, but we will still be responsible from M&G’s perspective so we will have to rectify it in the event of faulty design.
What are the types of specification?
- Prescriptive specifications: Provide detailed descriptions of specific materials to use and how they should be installed.
- Performance specifications: Addresses the operational requirements of a installation. The focus is on the project outcome, indicating how it must function, it is up to the contractor how they achieve this.
- Descriptive specifications: Designer controls design intent and defines the performance criteria. Specialist contractor uses skills and expertise to complete the design whilst maintaining the design intent.
What was the build-up / specification of the new roof?
- The specification was provided by Tata Steel as I had specified their systems on other projects that had been a success.
- The system specified was the Tata Steel Trisobuild roof system.
- System comprised of external profiled metal cladding sheets, spacer system, thermal insulation layer and vapour control membrane.
Draw the build up of the new roof system.
- Include for VCL (always on warm side of insulation) and existing roof!
Describe the stages of decorating the profiled metal cladding
- Cladding will be cleaned using a jet wash to remove all grease, oil, general dirt and contaminates and existing flaking paintwork.
- All areas not to be painted will be masked off.
- All cladding will be brushed to remove any dust that could prevent adhesion.
- Spot priming will be undertaken to areas where there is bare metal resulting from the cleaning process to provide a mechanical key.
- Elevation then should be coated in an undercoat to ensure adhesion between the new topcoat and cladding.
- Apply the finishing / top coat.
What were the rooflights? What were their built up? What guarantee did they have?
- Trilite 30 GRP profiled roof lights consisting of inner and outer sheet separated by a polyethylene foam fillers to the internal void.
- Installed with 2 layers of sealant to end laps and one to each side lap.
- Service life in excess of 30 years, 25 year performance warranty from manufacturer.
Draw the rooflight
What u-value did the roof achieve?
0.18
What issues were noted in the CCTV drainage survey?
- Fractures to pipework in isolated locations.
- Silt and debris build up.
- Oil interceptor required maintenance.
- Cost came to £11,000.
How were the drainage repairs completed?
What did you specify for the movement joints?
Sika flex - a silane modified polymer sealant.
What paint was used on the portal frame?
- Crown Gloss metal paint.
- An intumescent paint had not been used as Part B does not require single storey portal frame buildings to have fire protection as they are not supporting any structure above. We would have needed intumescent paint if there was a roof plant area that had permanent access.
- I consulted the improved inspector on this to ensure that those steels that provide restraint to the party wall needed any further fire protection, he confirmed that the existing masonry would be sufficient.
- Note additionally, steels to part walls would need to have increased foundations to prevent uplifting if collapse of purlins occurred.
What testing did the contractor carry out for the retained services?
- Electrical Installation Condition Report.
- Tested the existing fire alarm installation.