Contract Administration Flashcards
What are the main forms of JCT contract you know?
- JCT Intermediate Building Contract, 2016 (+with contractor’s design portion).
- JCT Minor Works Building Contract 2016 (+with contractor’s design portion).
- JCT Design and Build.
- Management Building Contract 2016.
- Measured Term Contract 2016.
What kinds of works would be included within the contractor’s design portion of a contract and why?
- It is used when the contactor has agreed to design specific parts of the works. They will usually sub-contract the works
whereby a specialist installer or manufacturer is required. Ensures buildability and other factors are taken into account. The
contractor is responsible for the procurement and must adhere to the programme. - Specialist works can include; installation of services, roof replacement etc.
- Takes the liability of the design off the client and design team.
What are the responsibilities of a contract administrator
- They are not a party to the contract and therefore must remain impartial at all times. Simply there to administer the contract.
- Chair pre contract meeting.
- Issue contract instructions.
- Deal with payment provisions.
- Manage change procedures – design changes etc.
- Involve with dispute avoidance.
- Issue certificates.
- Deal with completion / possession issues.
Explain the valuation process and the responsibilities of a contract administrator for a JC intermediate Contract / JCT Minor works contract?
- Contractor must issue application for payment no later than the valuation date.
- Valuation date occurs (stated in contract particulars – will change to closest business day).
- Due date (date at which the CA values the works) is 7 days after the valuation date.
- Contract administrator must issue a certificate for payment (interim cert) within 5 days after the due date – the cert = the
amount they deem should be paid at the due date. - Final date for payment in standard contract is 14 days from the due date.
- If the employer intends to withhold any amount from the sum certified, the they must provide written notice of their intention no later than 5 days before the final date for payment.
Note: The contract gives the contractor the right to submit its own payment application - they are not required to and the CA can undertake the valuation without it.
Note: If the CA doesn’t issue a payment certificate within 5 days after the due date, if the contractor issued an application for payment this becomes a payment notice and acts as the cert, otherwise a contractor can send a payment notice to the CA.
How does the valuation process differ with regards to the JCT Design and Build Contract?
- Essentially the same as the JCT intermediate contract BUT – Due dates can change.
- If the contractor submits their application for payment before the valuation date, then the due date is still 7 days from valuation
date, but if received after the valuation date then the due date is 7 days from the day of receipt of the AFP.
How could an employer take part of a site back quickly?
- By doing sectional completion.
- Early possession – note: when early possession utilised the works or
section of are deemed to be at practical completion
regardless. - Acceleration.
What is practical completion? What happens contractually once PC is certified?
- There is no definitive definition for the term Practical Completion. It is when the works are complete to the satisfaction of the Contract Administrator and the contractor has abided with their duties under the CDM regulations. The CA cannot certify PC where there are outstanding works or patent defects, but they also cannot withhold PC for minor outstanding defects.
- HW Nevill (Sunblest) Ltd v William Press & Son Ltd [1981] (the flexible test) – PC will not be prevented where the works have been completed free from patent defects, other than ones to be ignored as diminimus or trifling (very minor in nature).
- What is deemed diminmus or trifling will be different for each project / the intended end use – swimming pool analogy.
Once PC is certified:
- Start of rectification period.
- Liquidated damages cannot be claimed.
- Release of half the retention.
- Client then claims back possession of the site – insures it etc.
What is partial possession?
- Mechanism to allow employer to take early possession of a site.
- Contract might have provision for sectional completion to allow partial possession.
- Effect of partial possession:
Any part of the works which partial possession is given is deemed to achieve practical completion.
Half retention must therefore be released.
Defects liability begin for that part of the works.
Liquidated damages reduce?
Client is responsible for that part of the works and will need to use its own insurances. - Contractor not obliged to give partial possession but can’t unreasonably withhold it.
- Contactor may not wish to give partial possession due to occupants / other contractors on the site holding up works – may
lead to an extension of time application.
What is the difference between a contract being executed as a deed or underhand?
- The Latent Damage Act 1986 stipulates the limitation period of building contract is (period for which a claimant can bring proceedings against a contractor):
- 6 years from completion for contracts signed underhand.
- 12 years for those executed as a deed.
- The act prevents claimants bringing old cases against contractors and encourages them to do so without delay.
What contractual processes need to occur with regards to an extension of time?
- The contractor is required to notify the CA whenever it becomes reasonably apparent that the progress of the works or any
section of the works is likely to be delayed by a relevant event. - The contractors notification should be in writing and should identify the relevant event that has caused the delay, request that an
extension of time should be granted and then provide details and evidence of causation of the relevant event. They should also
state whether the delay will impact the completion date and if so the amount of delay anticipated. - Contractually the contractor is also required to mitigate the delay even though it isn’t a result of their actions.
- CA then analyses the contractors’ request for extension of time and to determine whether the identified relevant event has indeed
caused the delay. If this is found to be the case they must then grant the extension of time and agree a new contractual
completion date.
What are the two broad groups of relevant events? Give some examples of relevant events
- Relevant events caused by the employer / relevant events caused by neutral events.
- Relevant events caused by the employer: variations and instructions, delays handing over possession of the site, suspension of the contract due to non-payment.
- Relevant events caused by neutral events: Force majeure - act of god (war, natural catastrophes), adverse weather conditions, specified perils (fire, floods), civil commotion (acts of terrorism, strikes etc).
What is single stage tendering?
- Single stage tendering is a tendering procedure whereby a number of pre-selected contractors submit tenders on a competitive basis.
- Each contractor provides a single cost for the whole of the construction works within a predetermined tender period.
- Tenders are then analysed in terms of cost and quality before a single contractor is declared the preferred contractor and enters into a building contract with the client.
What are the advantages of single stage tendering?
- Ensures only capable and approved contractors submit tenders.
- Tends to reduce the overall cost for the tendering process.
- Client get a lump sum for the entirety of the works.
What is traditional procurement?
- The design portion of the works is completed by the client’s design team before competitive tenders are invited and a principal contract employed to construct what has been specified.
- The contractor takes responsibility and financial risk for the construction of the works and completes the works for a contract sum
within a contract period which is confirmed at pre contract stage.
When would traditional procurement appropriate?
- If the design is substantially completed at time of contractor selection.
- The client wishes to retain control over the design and specification.
- When the client needs cost certainty - to get board approval.
- When total programme length isn’t the clients’ main priority.
What forms of contract might you use with traditional procurement?
- JCT Minor Works, 2016.
- JCT Intermediate
What are the advantages of traditional procurement?
- Competitive fairness and transparent process – increase value for money
- Design led – can ensure quality
- Price certainty before commencement
- Well known procedures
- Changes are reasonably easy to arrange and value
What are the disadvantages of Traditional Procurement?
- Increases overall project duration - it is a sequential process with design produced before construction can commence.
- Reduced buildability within the design as contractor has had no input.
- Dual point of responsibility for client for design and construction.
- If the design is not completed at time of tender then cost / time certainty are reduced.
What is included within a tender report?
- List of tenders received.
- Initial tender return totals.
- Any qualifications identified.
- Post-tender adjustments.
- Revised tender sum.
- Comparison of tender sums.
- Recommendation.
What are the key contractual procedures have to occur to enable an employer to claim liquidated damages?
- The contractor must have not completed the works or section of works by the contractual completion date.
- The contract administrator must have issued a certificate of non-completion.
- The employer must have notified the contractor in writing that they intend to claim liquidated damages. This may be by ordering
the contractor to pay them or deducting them from the sums owed to the contractor. - If the employer wants the deduct the liquidated damages from sums owed to the contractor then a pay less notice is required to
ensure compliance with the Housing Grants, Construction and Regeneration Act 1996.
What is procurement?
The overall act of obtaining goods and services from external sources (for example a building contractor) and includes decision making with regards to how the goods are to be acquired by reviewing a client’s requirements (i.e time, quality and cost). and their attitude to risk.
What is tendering?
Tendering forms part of the procurement strategy and involves:
- The bidding process to obtain a cost for the works; and
- How a contractor is appointed.
What is the difference between procurement and tendering?
- Procurement is the overall act of obtaining goods and services from external sources (for example a building contractor) and includes decision making with regards to how the goods are to be acquired by reviewing a client’s requirements (i.e time, quality and cost). and their attitude to risk.
- Tendering forms part of the procurement strategy and involves the bidding process to obtain a cost for the works and how a contractor is appointed.
What is two-stage tendering?
- The first stage of the process involves first-stage tender enquiry documentation being issued to preselected bidding contractors at RIBA stage 2 / 3. At this stage the works are still being designed.
- The contractors then submit their bids which do not give a lump cost for the entirety of the works but confirm their preliminaries costs, proposed sub letting of the works (sub contractors) and their overhead and profit allowances.
- The preferred contractor then joins the design team on a consultant basis using a pre-construction services agreement.
- The preferred contractor then works with the design team to complete the design before presenting a bid for the works.