Contract Administration Flashcards

1
Q

What are the main forms of JCT contract you know?

A
  • JCT Intermediate Building Contract, 2016 (+with contractor’s design portion).
  • JCT Minor Works Building Contract 2016 (+with contractor’s design portion).
  • JCT Design and Build.
  • Management Building Contract 2016.
  • Measured Term Contract 2016.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What kinds of works would be included within the contractor’s design portion of a contract and why?

A
  • It is used when the contactor has agreed to design specific parts of the works. They will usually sub-contract the works
    whereby a specialist installer or manufacturer is required. Ensures buildability and other factors are taken into account. The
    contractor is responsible for the procurement and must adhere to the programme.
  • Specialist works can include; installation of services, roof replacement etc.
  • Takes the liability of the design off the client and design team.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the responsibilities of a contract administrator

A
  • They are not a party to the contract and therefore must remain impartial at all times. Simply there to administer the contract.
  • Chair pre contract meeting.
  • Issue contract instructions.
  • Deal with payment provisions.
  • Manage change procedures – design changes etc.
  • Involve with dispute avoidance.
  • Issue certificates.
  • Deal with completion / possession issues.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Explain the valuation process and the responsibilities of a contract administrator for a JC intermediate Contract / JCT Minor works contract?

A
  1. Contractor must issue application for payment no later than the valuation date.
  2. Valuation date occurs (stated in contract particulars – will change to closest business day).
  3. Due date (date at which the CA values the works) is 7 days after the valuation date.
  4. Contract administrator must issue a certificate for payment (interim cert) within 5 days after the due date – the cert = the
    amount they deem should be paid at the due date.
  5. Final date for payment in standard contract is 14 days from the due date.
  6. If the employer intends to withhold any amount from the sum certified, the they must provide written notice of their intention no later than 5 days before the final date for payment.

Note: The contract gives the contractor the right to submit its own payment application - they are not required to and the CA can undertake the valuation without it.

Note: If the CA doesn’t issue a payment certificate within 5 days after the due date, if the contractor issued an application for payment this becomes a payment notice and acts as the cert, otherwise a contractor can send a payment notice to the CA.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How does the valuation process differ with regards to the JCT Design and Build Contract?

A
  • Essentially the same as the JCT intermediate contract BUT – Due dates can change.
  • If the contractor submits their application for payment before the valuation date, then the due date is still 7 days from valuation
    date, but if received after the valuation date then the due date is 7 days from the day of receipt of the AFP.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How could an employer take part of a site back quickly?

A
  • By doing sectional completion.
  • Early possession – note: when early possession utilised the works or
    section of are deemed to be at practical completion
    regardless.
  • Acceleration.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is practical completion? What happens contractually once PC is certified?

A
  • There is no definitive definition for the term Practical Completion. It is when the works are complete to the satisfaction of the Contract Administrator and the contractor has abided with their duties under the CDM regulations. The CA cannot certify PC where there are outstanding works or patent defects, but they also cannot withhold PC for minor outstanding defects.
  • HW Nevill (Sunblest) Ltd v William Press & Son Ltd [1981] (the flexible test) – PC will not be prevented where the works have been completed free from patent defects, other than ones to be ignored as diminimus or trifling (very minor in nature).
  • What is deemed diminmus or trifling will be different for each project / the intended end use – swimming pool analogy.

Once PC is certified:

  • Start of rectification period.
  • Liquidated damages cannot be claimed.
  • Release of half the retention.
  • Client then claims back possession of the site – insures it etc.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is partial possession?

A
  • Mechanism to allow employer to take early possession of a site.
  • Contract might have provision for sectional completion to allow partial possession.
  • Effect of partial possession:
     Any part of the works which partial possession is given is deemed to achieve practical completion.
     Half retention must therefore be released.
     Defects liability begin for that part of the works.
     Liquidated damages reduce?
     Client is responsible for that part of the works and will need to use its own insurances.
  • Contractor not obliged to give partial possession but can’t unreasonably withhold it.
  • Contactor may not wish to give partial possession due to occupants / other contractors on the site holding up works – may
    lead to an extension of time application.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is the difference between a contract being executed as a deed or underhand?

A
  • The Latent Damage Act 1986 stipulates the limitation period of building contract is (period for which a claimant can bring proceedings against a contractor):
  • 6 years from completion for contracts signed underhand.
  • 12 years for those executed as a deed.
  • The act prevents claimants bringing old cases against contractors and encourages them to do so without delay.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What contractual processes need to occur with regards to an extension of time?

A
  • The contractor is required to notify the CA whenever it becomes reasonably apparent that the progress of the works or any
    section of the works is likely to be delayed by a relevant event.
  • The contractors notification should be in writing and should identify the relevant event that has caused the delay, request that an
    extension of time should be granted and then provide details and evidence of causation of the relevant event. They should also
    state whether the delay will impact the completion date and if so the amount of delay anticipated.
  • Contractually the contractor is also required to mitigate the delay even though it isn’t a result of their actions.
  • CA then analyses the contractors’ request for extension of time and to determine whether the identified relevant event has indeed
    caused the delay. If this is found to be the case they must then grant the extension of time and agree a new contractual
    completion date.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the two broad groups of relevant events? Give some examples of relevant events

A
  • Relevant events caused by the employer / relevant events caused by neutral events.
  • Relevant events caused by the employer: variations and instructions, delays handing over possession of the site, suspension of the contract due to non-payment.
  • Relevant events caused by neutral events: Force majeure - act of god (war, natural catastrophes), adverse weather conditions, specified perils (fire, floods), civil commotion (acts of terrorism, strikes etc).
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is single stage tendering?

A
  • Single stage tendering is a tendering procedure whereby a number of pre-selected contractors submit tenders on a competitive basis.
  • Each contractor provides a single cost for the whole of the construction works within a predetermined tender period.
  • Tenders are then analysed in terms of cost and quality before a single contractor is declared the preferred contractor and enters into a building contract with the client.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are the advantages of single stage tendering?

A
  • Ensures only capable and approved contractors submit tenders.
  • Tends to reduce the overall cost for the tendering process.
  • Client get a lump sum for the entirety of the works.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is traditional procurement?

A
  • The design portion of the works is completed by the client’s design team before competitive tenders are invited and a principal contract employed to construct what has been specified.
  • The contractor takes responsibility and financial risk for the construction of the works and completes the works for a contract sum
    within a contract period which is confirmed at pre contract stage.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When would traditional procurement appropriate?

A
  • If the design is substantially completed at time of contractor selection.
  • The client wishes to retain control over the design and specification.
  • When the client needs cost certainty - to get board approval.
  • When total programme length isn’t the clients’ main priority.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What forms of contract might you use with traditional procurement?

A
  • JCT Minor Works, 2016.
  • JCT Intermediate
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are the advantages of traditional procurement?

A
  • Competitive fairness and transparent process – increase value for money
  • Design led – can ensure quality
  • Price certainty before commencement
  • Well known procedures
  • Changes are reasonably easy to arrange and value
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What are the disadvantages of Traditional Procurement?

A
  • Increases overall project duration - it is a sequential process with design produced before construction can commence.
  • Reduced buildability within the design as contractor has had no input.
  • Dual point of responsibility for client for design and construction.
  • If the design is not completed at time of tender then cost / time certainty are reduced.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is included within a tender report?

A
  • List of tenders received.
  • Initial tender return totals.
  • Any qualifications identified.
  • Post-tender adjustments.
  • Revised tender sum.
  • Comparison of tender sums.
  • Recommendation.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are the key contractual procedures have to occur to enable an employer to claim liquidated damages?

A
  • The contractor must have not completed the works or section of works by the contractual completion date.
  • The contract administrator must have issued a certificate of non-completion.
  • The employer must have notified the contractor in writing that they intend to claim liquidated damages. This may be by ordering
    the contractor to pay them or deducting them from the sums owed to the contractor.
  • If the employer wants the deduct the liquidated damages from sums owed to the contractor then a pay less notice is required to
    ensure compliance with the Housing Grants, Construction and Regeneration Act 1996.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is procurement?

A

The overall act of obtaining goods and services from external sources (for example a building contractor) and includes decision making with regards to how the goods are to be acquired by reviewing a client’s requirements (i.e time, quality and cost). and their attitude to risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is tendering?

A

Tendering forms part of the procurement strategy and involves:

  • The bidding process to obtain a cost for the works; and
  • How a contractor is appointed.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is the difference between procurement and tendering?

A
  • Procurement is the overall act of obtaining goods and services from external sources (for example a building contractor) and includes decision making with regards to how the goods are to be acquired by reviewing a client’s requirements (i.e time, quality and cost). and their attitude to risk.
  • Tendering forms part of the procurement strategy and involves the bidding process to obtain a cost for the works and how a contractor is appointed.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is two-stage tendering?

A
  • The first stage of the process involves first-stage tender enquiry documentation being issued to preselected bidding contractors at RIBA stage 2 / 3. At this stage the works are still being designed.
  • The contractors then submit their bids which do not give a lump cost for the entirety of the works but confirm their preliminaries costs, proposed sub letting of the works (sub contractors) and their overhead and profit allowances.
  • The preferred contractor then joins the design team on a consultant basis using a pre-construction services agreement.
  • The preferred contractor then works with the design team to complete the design before presenting a bid for the works.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What is negotiated tender?

A
  • A single contractor is provided with the tender documentation by the client and then submits their initial cost to carry out the entirety of the works.
  • The client’s professional team then negotiates the cost of the works with the contractor to achieve a final cost.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What are the advantages and disadvantages of single-stage tendering? When would you utilise single stage tendering?

A

Advantages:

  • Ensures that only capable and approved firms submit tenders (as they are preselected from an approved list).
  • Client gets cost certainty as they are provided with a lump sum for the works.

Disadvantages:
- The full design has to be prepared before the works can be tendered which is not suitable whereby total programme length is important.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What are the advantages and disadvantages of two-stage tendering? When would you use two-stage tendering?

A

Advantages:

  • Allows the contractor to contribute to the design and early planning of the work (so increases buildability).
  • Allow the contractor to commence works on sections before the entirety of the design is complete.

Disadvantages:

  • Hard to replace the contractor is second stage negotiations break down.
  • Risk of increased cost for retendering works if second stage negotiations have broken down.
  • The second stage is not a competitive process so the contractors cost may not be competitive.

Two-stage tendering is suitable for:

  • Projects that are complex (require contractor’s input on design).
  • When programme length is important.
  • Projects whereby the magnitude of the works are yet unknown.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

What are the advantages and disadvantages of negotiated tendering? When would you utilise negotiated tendering?

A

Advantages:

  • The contractor is usually approached because they have carried out similar works and to the required standard before so there is greater certainty of cost and quality.
  • Time and cost savings by reducing input into the tendering process because only a single tender needs to be analysed.
  • Time saving on tender process allows earlier commencement of the works.

Disadvantages:

  • Lack of competitive tendering may increase the cost for the works.
  • Negotiation process needs to be structured and controlled otherwise there could be adversity between the parties before works have even commenced.
  • You would usually utilise negotiated tendering when overall programme length is a priority over cost and whereby the client wants to replicate the quality of a project that the contractor has delivered before.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

What are the main procurement routes?

A
  • Traditional.
  • Design and build (single and two stage).
  • Management Contracting.
  • Construction Management.
  • Framework agreements.
  • Partnering.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What is design and build procurement? When would you utilise design and build procurement? What contract would you use?

A
  • Design and build is whereby the contractor is responsible for the design, planning organisation, control and construction of the works to the employer’s requirements.

I would utilise design and build when…

  • The client has a need to make an early start on site as the design can be developed during the construction phase.
  • The client wishes to minimise their risk in relation to the design of the works, this may be due to risky nature of the works for example replacement of combustible cladding.
  • The design is complex and contractor input is needed to ensure buildability.
  • The client does not want to or is not bothered about retaining control over the development of the design.
  • The JCT Design and Build, 2016 contract would be used.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

What is management contracting? When would you utilise management contracting? What contract would you use?

A
  • A procurement option whereby a client employs a management contractor to contribute to design and manage the works.
  • The management contractor has direct contractual links with all of the works contractors and has the responsibility for the works without carrying them out.
  • The management contractor breaks down the project into suitable works packages and selects works contractors through competitive open book tenders.
  • The client then then reimburses the cost of the works packages to the management contractor in addition to their fee.
  • I would utilise this procurement route when:
    1. The client values an early start and overall project length over cost.
    2. The works are extensive.
    3. The works are complicated.
  • I would use the JCT Management Contract, 2016.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

What are the advantages and disadvantages of design and build?

A

Advantages:

  • There is a single point of responsibility for the design and construction of the works.
  • Works can commence earlier on site as the design and construction process can overlap.
  • Contractor involvement with the design ensures buildability and expertise are incorporated into the design. It also promotes innovation in design (contractor’s not constrained by detailed design) which leads to cheaper and faster construction.

Disadvantages:

  • It may be hard for a client to prepare a sufficiently comprehensive brief.
  • Harder to compare tenders as the contractors each have their own designs rather than pricing for fully defined and designed works.
  • Designs submitted may also be uninspiring as contractors may emphasise quickness of construction over quality.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

What is construction management? When would you utilise construction management? What contract would you use?

A
  • A procurement strategy whereby the client engages directly with specialists for the design of the works via individual contracts. A construction manager is then employed on a consultant basis to plan, coordinate and monitor the works.
  • The construction manager coordinates the design team and has no contractual links with the specialist contractors or the design team. They prepare the programme, determine prelims and then break down the project into suitable works packages and obtain and evaluate tenders.
  • I would utilise construction management when:
    1. The client is uncertain of the extent of works to be carried out.
    2. Those clients that want to commence works on site quickly and is less concerned about cost certainty.
    3. The client is an ‘expert’ and would benefit from the simple and direct legal relationships as they allow for effective redress of latent defects should they arise.
  • JCT Management Contract, 2016.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

What are the advantages and disadvantages of the construction management procurement route?

A

Advantages:

  • The construction manager can be appointed early on and can contribute to the design and planning process.
  • Project duration is shortened as there is an overlap between the design and planning.
  • Offers flexibility in design and the works as specialist contractors are let in stages.
  • The simple and direct contractual link between the client and expert contractors allow easy redress regarding latent defects.
  • Cost for the works packages may be lower due to direct contracts between the client and expert contractors.

Disadvantages:

  • Client needs to be an ‘expert’ to manage the various contracts between them and specialist contractors and consultants.
  • Can be difficult to select a suitable construction manager as selection is based on skill and not cost of a tender submission.
  • Puts risks of the performance of specialist contractors largely on the employer as the construction manager has little responsibility.
  • There is little incentive for the construction manager to reduce costs associated with the works as their payment is fee based.
  • The price of the works is not confirmed until the last package of works has been let.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

What are the advantages and disadvantages of the management contracting procurement route?

A

Advantages:

  • Overall project duration is shorter due to overlapping design and construction
  • There is contractor contribution to the design and planning process
  • Changes can be accommodated in packages not yet let if they have no further
    impact
  • The works are let competitively at current market prices on a firm price basis

Disadvantages:

  • Can be difficult to select a suitable construction manager as selection is based on skill and not cost of a tender submission.
  • Puts risks of the performance of specialist contractors largely on the employer as the construction manager has little responsibility.
  • There is little incentive for the construction manager to reduce costs associated with the works as their payment is fee based.
  • The price of the works is not confirmed until the last package of works has been let.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

What are framework agreements? When would you utilise them? What contract would you use?

A
  • Framework agreements allow client’s that are consistently instructing construction work to invite tenders from contractors to be carried out over a prolonged period of time on a call off basis as and when required.
  • Could use JCT FA, 2016.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

What are the advantages and disadvantages of framework agreements?

A

Advantages

  • Reduces costs related to tendering works.
  • Allows quick start on site.
  • Integration of supply chain.
  • Continuity of finishes end product.
  • Allows development of long term and strong relationships.

Disadvantages

  • Reduced competition resulting in higher overall project cost.
  • Contractors must be able to undertake all types of work - this may not be the case if not considered before creation of framework agreement.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

How does a framework agreement last for?

A
  • Will depend on the client or sector but the public sector is governed by EU procurement rules which limit a FA to 4 years.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

How would you choose contractors for a framework?

A
  • Suppliers are appointed on the basis of their capability & capacity to carry out the
    works.
  • I would first discuss the scope of work & size of packages likely to be involved
    throughout the FA & would then draw up a list of potential capable contractors either
    from an internal list of approved contractors which the Client may have (Network
    Rail) or from my own knowledge & experience & discussions with colleagues.
  • I would invite the contractors to pre-qualify for the Framework, requesting information
    such as the financial standing, work load, number & quality of staff, previous
    experience in the potential projects under the FA, H&S & QA procedures in place.
  • Appointment would be assessed based on quality & capability rather than price.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

How would you ensure framework prices remained competitive?

A
  • Carry out random audits & benchmark with the industry data (BCIS or internally against other projects recently tendered).
  • Bid some of the work competitively outside the framework & invite framework
    contractors to tender.”
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

What are contract documents?

A
  • Documents that evidence the details of the building contract.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

What documents would make up the contract documents for a JCT Design & Build Contract?

A
  • Employer’s requirements: Can be a brief written performance statement, sketch drawings, planning permission drawings or detailed drawings and bill of quantities.
  • Contractors proposals: These can be equally as brief or extensive as the employer’s requirements.
  • Contract sum analysis: The CSA could be a full bills of quantities produced in accordance with NRM2 schedule of rates, or a simple elemental cost breakdown.
  • The building contract: JCT Design and Build, 2016.
  • A BIM protocol (if applicable): This creates the requirement for the contractor to provide specified BIM at defined levels of detail and incorporates provisions which supports the production of deliverables for ‘data drops’ at defined project stages.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

What documents would make up the contract documents for an Intermediate Building Contract?

A
  • Drawings.
  • Specification.
  • Schedule of works.
  • Contract sum analysis.
  • Employer’s requirements for any contractor designed portions.
  • The building contract.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

What happens if the employer intends to withhold any amount of a sum certified by the contract administer in a payment certificate?

A
  • The contractor must be given written notice that the employer intends to pay them less than the sum certified no less than 5 days before the final date for payment in the form of a Pay Less Notice.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

What is a Letter of intent / a pre-construction services agreement?

A
  • A letter of intent or a pre-construction services agreement is a document that is used when two parties wish to commence construction works immediately prior to negotiation and formation of the final building contract.
  • There are two main types of letter of intent, these are:
  1. Non-binding letters of intent:
    - Intended to give rise to a contract but confirms the parties intention to enter a contract at some point in the future.
    - It does not create liability for either party to enter into a contract afterwards if they not wish to.
    - The contractor is under no obligation to complete the works in a certain timeframe / complete them at all.
    - There are limited remedies under this form of letter of intent - the employer has no counterclaim for damages for where there isn’t a contract in place, but they can deduct the cost from the value of the works.
  2. Contractual letters of intent:
  • It creates some limited reciprocal rights rights and liabilities between the parties - e.g carrying out works within a timeframe etc.
  • It is usually limited in scope - for example the amount of time the contractor or money the contractor can take / expend.
  • Whether this form of letter of intent is contractually binding will depend on whether:

+ Offer and acceptance
+ Consideration
+ An intention to create legal relations and
+ Certainty as to the essential terms.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

What is good practise to include within a letter of intent / pre-construction services agreement?

A
  • Limit the scope of the letter - limiting the scope by time or money encourages the contractor to agree to a full contract within a certain period of time / once a certain value has been reached. This also protects the employer should a contract not be agreed or signed.
  • State whether or not the contactor should stop works once the limit has been reached and if not then on what terms and confirm the payment provisions.
  • Identify the works to be carried out.
  • Insurance: state the level of public and employer’s liability in addition to all risks insurance. If the contractor is carrying out design works then level of professional indemnity insurance should be stated.
  • CDM Regulations requirements: state that the contractor is to act in accordance with the regulations.
  • Payment provisions: clearly state payment provisions. If not then Scheme of Construction Contracts default payment provisions apply.
  • Warranties: depending on the type of works, third parties may require collateral warranties from the contractor / sub contractors.
  • Copyright: if contractor carrying out design work, the letter should provide for a licence to be given to the employer allowing it to use any design documents following termination of the contractor’s involvement with the works.
  • Termination: letter must provide for the employer to terminate the contractor’s engagement and confirm that the employer has no obligation to enter into a full contract come the end of the letter of intent.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

What are the main pitfalls with letters of intent?

A
  • Both parties can have numerous commercial issues to be resolved before the contract is fully negotiated which leads to parties neglecting these issues meaning that full execution of the contract is never undertaken meaning a contract may never be fully negotiated / executed. This can lead to future disputes and exposure of the parties as the letter of intent does not contain detailed provisions.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

When ideally should a letter of intent be utilised?

A

Stated by Judge in Cunninghame V Collet [2006]:

  • Where contract work scope and price are agreed or there is a clear mechanism in place to reach an agreement.
  • Where terms and conditions are (or are very likely) to be agreed.
  • Where start and finish dates and the outline programme are broadly agreed.
  • Where there are good reasons for the works to be commenced in advance of contract documents being finalised.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

What the Scheme for Construction Contracts (England and Wales) Regulations?

A
  • A scheme that that applies when construction contracts do not comply with the Housing Grants, Construction and Regeneration Act.
  • The scheme either supplements or replaces provisions of a contract where it has deficiencies relevant to the Housing Grants, Construction and Regeneration Act. Ensures that construction contracts remain capable of performance whilst allowing regulatory control over their provisions.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

What is an Extension of Time?

A
  • A contract provision that allows adjustment of the contractual completion date.
  • It reserves the right of the employer to claim liquidated damages in the event that the contractor is unable to complete the works by the completion date for a reason that is partly due to the employers
  • if the completion date could not be adjusted then the contractor would only have the complete the works with a ‘reasonable time’ (time at large).
  • It also protects the contractor as if granted it relieves the contractor of their liability to pay liquidated damages.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

What are the extension of time procedure for a JCT Intermediate contract?

A
  1. Contractor must notify the CA as soon as it becomes apparent to them that a delay has occurred or will likely occur:
    - Notification required even if contractor is not seeking an EoT.
    - Notice doesn’t need to confirm whether the delay is a relevant event.
  2. Contractor must provide CA with any further information reasonably required by the CA to assess the delay.
  3. CA then assesses if there is a delay and notifies the contractor if an EoT has been granted.
    - No defined timeframe for the notification but the CA must notify “as soon as he is able”.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

What are the extension of time procedures for a JCT Design and Build contract?

A
  1. Contractor notifies the Employers Agent / the Employer as soon as it is apparent that a delay has or will occur.
    - Notification required even if EoT is not being pursued.
    - Notice needs to confirm the cause of the delay AND confirm whether the delay is the result of a ‘relevant event’ and confirm the anticipated delay caused to the works / works section.
  2. Employer’s Agent / Employer must assess the delay.
    - Notice must confirm whether an EoT has been granted or not.
    - Contractor must be notified within 12 weeks from receipt of the contractor’s notice / contractor must be notified before the completion date if there are less than 12 weeks until the completion date.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

What is a concurrent delay with regards to an extension of time?

A
  • A concurrent delay is caused two or more delays occurring at the same time. It is not to say that the delays occur simultaneously but their effects are apparent at the same time. For example exceptionally inclement weather occurs alongside a contractor’s inability to source site labour.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

What would you do if you had two or more concurrent delays occur at the same time?

A
  • Customary to grant an extension of time for the ‘dominant reason’ but only where it begins and ends after the other reasons.
  • Even if the dominant reason is not a ground for a loss/expense claim this may still be awarded over other concurrent delays that could lead to a claim.
  • H Fairweather and Co Ltd V London Borough of Wandsworth [1987].
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

What would you do whereby you had concurrent delays where one is deemed a ‘relevant event’ and the other is not?

A
  • The contractor would be granted an extension of time for the full length of delay caused by the relevant event.
  • Henry Boot Construction (UK) Ltd V Malmaison Hotel (Manchester) Ltd [1999]:

+ Malmaison appointed Henry Boot to construct hotel in Piccadilly, Manchester.
+ Judge cited example of exceptionally inclement weather occurred concurrently with a contractor’s inability to source labour during the same week.
+ Judge stated that Architect would not be allow to deny the contractor an extension of time on the grounds that the works would have been delayed by the labour shortage - contractor entitled to an EoT by 1 week.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

What would you do whereby you had concurrent delays where one is deemed a ‘relevant event’ and the other is not?

A
  • The contractor would be granted an extension of time for the full length of delay caused by the relevant event.
  • Henry Boot Construction (UK) Ltd V Malmaison Hotel (Manchester) Ltd [1999].
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

What are the responsibilities of a contractor with regards to delay?

A
  • Contractor must ‘constantly use his best endeavours to prevent delay and must take steps to minimise the effect of the delay on the completion date.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

What are liquidated damages?

A
  • Liquidated damages are a predetermined sum agreed between both parties of a building contract which are to be paid by the contractor to the employer whereby the contractor has failed to complete the works by the contractual completion date.
  • The rate for liquidated damages is stated in the contract particulars and is usually expressed as per week or part there of.
  • If the works are to be carried out in sections, the rate for liquidated damages can differ for different sections.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

How is the rate for liquidated damages determined?

A
  • Usually comprise of cost for anticipated rental income - usually informed by the client’s surveyor, professional fees (CA etc), any other costs incurred as a result of the delay e.g finding alternative accommodation for storage of a an incoming tenant’s property etc.
  • It is no longer essential for the rate to be calculated on the basis of a genuine pre-estimate of the loss likely to be suffered by the employer - reference ParkingEye Limited V Beavis.
  • Provided the amount is not ‘out of all proportion’ to the likely loss, damages will be recoverable and the employer will not have to prove their loss, even if it is much less than the amount of damages being claimed (BFI Group of Companies v DCB Integration Systems).
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

Why should the CA be careful with regards to liquidated damaged when populating contracts?

A
  • If ‘nill’ is inserted as the rate of liquidated damages into the contract, this will likely prevent the contractor claiming liquidated damages or general damages (Temloc V Errill).
  • If nothing is inserted as the rate of liquidated damages then the employer may be able to claim general damages.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

Why should the CA be careful with regards to liquidated damaged when populating contracts?

A
  • If ‘nill’ is inserted as the rate of liquidated damages into the contract, this will likely prevent the contractor claiming liquidated damages or general damages (Temloc V Errill).
  • If nothing is inserted as the rate of liquidated damages then the employer may be able to claim general damages.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

What are the preconditions that must be met for an employer to claim liquidated damages? JCT Intermediate Contract

A
  1. Contractor must have failed to complete the works by the contractual completion date.
  2. Employer / CA must have fulfilled any duties with respect to the award for an EoT (if EoT should have been granted then liquidated damages will not be claimable).
  3. Employer / CA must have issued a certificate of non-completion (JCT Intermediate) / non-completion notice (Design and Build) to the contractor.
  4. Employer must have notified the the contractor before the due date of the final payment (D&B) / before the date of the final certificate that it intends to withhold payment or requires payment for liquidated damages.
  5. A second notice is then required to state how the liquidated damages will be claimed.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

What would you do if a tender was submitted late?

A
  • Advise the client that they must provide formal instruction if they wish for the late tender to be included.
64
Q

What should you be sure to do when analysing tenders?

A
  • Analyse all tenders methodically and logically to ensure the tenders have been analysed on a like-for-like basis.
65
Q

What should you check for with tenders before you undertake a detailed analysis?

A
  • Arithmetical errors.
  • Obvious errors in the programme dates / lead in and contract period.
  • Conflicts of interest - review proposed sub-contractors.
66
Q

What should you do if you find a tender has an arithmetical error?

A
  • According to the JCT tendering guidance note, the employer has agent / the CA has two options:
    1. Notify the tenderer of the errors and give them chance to confirm or withdraw their tender. If withdrawn the next most financially advantageous tender is analysed. If they confirm their tender then a letter of endorsement should be included within the priced documents prior to acceptance. The endorsement should confirm that all rates / costs in the documents (excluding contingencies, PS and prelims) are to be considered as reduced or increased - endorsement should be signed by both parties.
    2. Notify the tenderer and give them opportunity of confirming or correcting it. If the tendered elects not to amend then an endorsement will be required to confirm this. If the tenderer elects to amend their tender then they should be either given access to the original tender to make adjustments or confirm their adjustments in a letter. The letter is then appended to any tender acceptance letter.
67
Q

What should be included included in the tender report?

A
  • List of tenders received.
  • Initial tender return totals.
  • Any qualifications identified.
  • Any post tender adjustments following queries / analysis.
  • The revised tender sum.
  • Comparison of the tender returns - in a tender analysis document.
  • Comparison with the pre-tender estimate.
  • Recommendations.
68
Q

What are the different insurance options under the JCT suite of contracts?

A
  • Option A (new buildings) - requires the contractor to take out and maintain all risks insurance of the works.
  • Option B (new buildings) - requires the employer to take out and maintain all risks insurance of the works.
  • Option C (existing structures) - requires the employer to take out and maintain (a) insurance in respect of the existing structure and their contents and (b) all risks insurance of the works.
69
Q

What is all risks insurance?

A
70
Q

When would a JCT Intermediate Contract be appropriate? When can it be used? When is it not suitable?

A

Appropriate:

  • When works are simple in nature - works themselves are simple and involve recognised basic trades and skills without very complex building services installations.
  • When works are designed by or on behalf of the employer and fairly detailed contract provisions are necessary.
  • When employer provides contractor with drawings, bills of quantities, a specification or work schedule to define the works.
  • Where an Architect of Contract Administrator will administer the contract.

Can be used:

  • When works are to be carried out in sections.
  • by both private and local authority employers.
  • Where provisions are required to cover named specialists (where the work is of a specialist nature and allows the employer the opportunity to select a sub-contractor with the relevant expertise).
  • Where additional provisions not found in minor works contract needed - partial possession, bonds and collateral warranties needed.
  • Using traditional procurement method.

Not suitable:

  • where contractor is to design discrete parts - need ICD.
  • for D&B procurement route.
71
Q

When would a JCT Minor Works Contract be appropriate? When can it be used? When is it not suitable?

A

Appropriate:

  • When work involved is simple in character.
  • Where work designed by or on behalf of the employer.
  • Where the Employer is to provide drawings and/or a specification and/or work schedules to define
    adequately the quantity and quality of the work.
  • Where an Architect/Contract Administrator is to administer the conditions.

Can be used:

  • By private and local authority employers.

Not suitable:

  • Where bills of quantities are required.
  • Where provisions are required to govern work carried out by named specialists.
  • Where detailed control provisions are needed
  • D&B procurement route.
  • When sectional completion partial possession required.
  • When performance bonds required.
72
Q

When would you utilise a contract with a contractor’s design portion? What would be included? Why would you utilise it?

A
  • It is used when the contactor has agreed to design specific parts of the works. They will usually sub-contract the works whereby a specialist installer or manufacturer is required. Ensures buildability and other factors are taken into account. The contractor is responsible for the procurement and must adhere to the programme.
  • Specialist works can include; installation of services, roof replacement etc.
  • Takes the liability of the design off the client and design team.
73
Q

What kinds of items would you cover in a pre-start meeting?

A
  • Introductions – if parties haven’t met before then good to define everyone’s roles in person.
  • Health and safety – F10, Construction Phase Plan, COSHH and CDM regs, site cleanliness, temporary works, contractor’s compound.
  • Contractor / site management – Site manager, office support and progress reports.
  • Communication – Instructions and methods of communication.
  • Contract details: Date of possession, contract sum, programme, completion date, contractor and employers insurances.
  • Site – Access, neighbours, accommodations, working hours, security and any other restrictions.
  • Statutory approvals – Building control.
  • Progress meets and valuations – Agree progress meetings (informal every 2 weeks and formal once a month close to valuation date as possible).
  • Info required.
  • Any other business.
74
Q

What is a procurement strategy? What are the different types of procurement strategy?

A
  • Procurement is the purchasing of goods and services.
  • Construction management: works constructed by numerous trade contractors who are employed by the client but managed by a construction manager (employer’s agent). Allows early appointment of construction manager who can improve buildability and package works. Way of client being able to keep tabs on quality of works.
  • Design and build: Main contractor employed to design and construct the works. Can have single or two stage tendering process – used when specialist design needed / put responsibility of works on contractor (roof / cladding).
  • Framework agreement: Used when client is regularly instructing works and uses a contractor regularly – cuts down lead ins and costs. Contractors submit tender and are instructed on a call off basis.
  • Lump sum: The most traditional form of procurement – a lump sum price for all the works is agreed before they commence. Usually used when a project is well defined and major changes are unlikely.
75
Q

What is a tender? What is tendering? What are the different tendering strategies?

A
  • A tender is a submission made by a prospective supplier in response to an invitation to tender and makes an offer for the supply of goods or services.
  • Single stage: All information is made available to the contractor to allow them to price when tendering commences. Invitation to tender is issued to prospective contractors, tenders are returned, and a preferred tender is selected and the contractor appointed.
  • Two-stage: First stage involves a limited appointment to allow works to commence (maybe enabling works), in the second stage a fixed price is negotiated for the contract. Allow early appointment and commencement of the works.
  • Negotiated: Single contractor is invited to tender; they submit their tender which the CA will then review and negotiate costs before appointment. Utilised where works are highly specialised, or where the contractor has completed a very similar job for the employer before + allows for reduced time and costs tendering (can commence works quicker). Drawback is that competitive pricing might be reduced.
  • Selective tendering: Contractors can submit tenders only by invitation. Pre-selected list of contractors (usually ‘approved’ contractors) based on their suitability for an instruction. Their performance is regularly monitored to allow them to remain on the approved list.
76
Q

How should contract instructions be issued?

A
77
Q

What are the responsibilities of a contract administrator?

A
  • They are not a party to the contract and therefore must repair impartial at all times. Simply there to administer the contract.
  • Chair pre contract meeting.
  • Issue contract instructions.
  • Deal with payment provisions.
  • Manage change procedures – design changes etc.
  • Involve with dispute avoidance.
  • Issue certificates.
  • Deal with completion / possession issues.
78
Q

When would you utilise the JCT Design and Build Contract? What provisions differ from other standard forms of JCT contract?

A
  • Is used for the design and build procurement route (employer appoints main contractor and then gets them to design and then undertake the works, as opposed to using consultants to design works then appoint contractor).
  • Can ensure good buildability (designed by contractor).
  • Some consider only effective for smaller projects where they don’t need as much control / are not as concerned with the design.
  • Client may just like using the contract – has amendments for it.
  • Client doesn’t want liability for the works – cladding replacement etc.
  • Employer will issue ‘employers’ requirements’: gives the minimum standards that the contractor needs to achieve with the works, the scope of services required and allocation of risk for unknown items.
  • Payment notices given instead of payment certs.
  • Retention is 3% rather than 5% - contractor is taking on greater portion of the responsibility.
79
Q

What are the main forms of JCT contracts?

A
  • Intermediate Building Contract 2016 + with contractor’s design portion.
  • Minor Works Building Contract 2016 + with contractor’s design portion.
  • Design and Build Contract 2016.
  • Management Building Contract 2016.
  • Measured Term Contract 2016.
80
Q

When would you utilise a design and build contract? When is it appropriate? When can it be used? When wouldn’t it be suitable?

A

Appropriate:

  • Where detailed contract provisions are necessary and Employer’s Requirements have been prepared and provided to the Contractor.
  • Where the Contractor is not only to carry out and complete the works, but also to complete the design.
  • Where the Employer employs an agent (who may be an external consultant or employee) to administer
    the conditions.

Can be used:

  • Where the works are to be carried out in sections.

Not suitable

Where the Contractor’s design responsibility is restricted to discrete parts of the works and he is not
responsible for completing the design for the whole works, consideration should be given to using one of the
JCT contracts that provide for the employment of an Architect/Contract Administrator and limited design input
by the Contractor.

81
Q

What document would you refer to if unsure what contract to utilise?

A

JCT guidance document - Deciding on the appropriate JCT contracts

82
Q

What is the employers agent?

A

The contract administrator under JCT design and build contracts

83
Q

What is a domestic subcontractor ?

A

A domestic sub-contractor is any sub-contractor, other than a nominated-sub contractor, that the main contractor sub-contracts to carry out part of the works. The work of the sub-contractor is the responsibility of the main contractor as far as the contract between the main contractor and the client is concerned

84
Q

Was does the JCT MW not allow for ?

A
  • Sub-contractor design
  • Section completion
  • Named sub-contractors
  • Clerk of works
  • QS
  • Programme as contract documents
  • Relevant events / matters
  • Novation / Assignment
85
Q

What is the difference between liquidated and unliquidated damages ?

A
  • Liquidated damages are a pre-determined sum of money payable in respect of a specific breach of contract. Most commonly we associate liquidated damages with delay. In this context the parties usually agree in the contract that in the event the contractor is late in reaching completion of the works for handover then the contractor shall pay to the client the sum of [x] per day or per week that the works are delayed. See B is for Breach for more information.
  • Unliquidated damages by contrast are the damages claimed when the loss has not been pre-determined by the parties. I.e. unliquidated damages are claimed for any breach of contract which is not subject to a liquidated damages clause.
86
Q

What are the Sections of JCT MW ?

A
  • Recitals
  • Articles
  • Contract Particulars
  • Attestation
  • Conditions
  • Schedules
87
Q

What are the contract particulars ?

A

Contract Particulars This section contains the all-important contract clauses covering items including:
• Carrying out the works
• Control of the works
• Payment
• Injury, damage and insurance
• Termination
• Dispute

88
Q

How do you assess Extension of Time?

A

This is determined by the amount a project critical path is delayed by a relevant event such as the client failing to provide access or providing delayed instructions or constant variations. The EoT claim is reviewed to determine how the contractor has justified it and I then review this and site notes/emails to determine if the contractor made reasonable efforts to avoid the delay or if the delay was down to their own performances. Where they have cited adverse weather, I will take an average of the last 10 years from met office to determine if the weather at the time of the event was to be unexpected or not.

89
Q

What RIBA stage would you go out to tender ?

A

Single stage – go out to tender at Stage 4 which is technical design.
Two stage – go out to tender at stage 2 or 3 which is concept design or spatial coordination.

90
Q

What forms of contract are you aware of ?

A
  • JCT
  • NEC
  • FIDIC
91
Q

What is the difference between NEC and JCT ?

A

They are both standard forms of contract. JCT is designed for domestic projects whereas NEC is suitable for domestic and international. NEC came after the Latham report and aims to offer better clarity, flexibility and better management processes. In NEC, the contract is administered by a PM and in JCT, it is a CA. NEC requires and enables a more proactive and collaborative approach whereas JCT is aimed at focussing on liabilities and risk. NEC has early warning notices and compensation events rather than relevant events/matters

92
Q

What is a collateral warranty ?

A
  • A contract document that allows an employer to create direct contractual links with a party who isn’t party to the main construction contract.
  • This protects the employer in the event that the contractor becomes insolvent as the employer would have no direct link with any subcontractor and therefore no form of redress if defects arise.
  • JCT provide standard forms of collateral warranties which can be utilised.
93
Q

What is a performance bond ?

A
  • A contractual bond that guarantees the completion of a project. If the contractor does not complete the project, the bond guarantees against financial loss to the client for a specified amount which is usually 10% of the contract value.
  • It is obtained via a bondsman and protects the employer if the contractor becomes involvement - the pay out is there to essentially pay the cost of finding and appointing another contractor to complete the works.
  • Performance bonds will need to run to the end of the rectification period to ensure they are covered for any defects that arise.
94
Q

What is a contract ?

A

It is a written or verbal agreement between parties to carry out a service in exchange for some form of repayment.

95
Q

What is a patent defect ?

A

A patent defect is identified during the rectification period as a result of reasonable inspection.

96
Q

What is a latent defect ?

A

A latent defect exists before its discovery. It cannot be identified from reasonable inspections; hidden or concealed flaw.

97
Q

What insurance would a contractor require before commencing works on site ?

A
  • Professional indemnity
  • Public liability
  • Employers liability
  • All risks insurance
98
Q

What are the contents/what are included in typical contract documents ?

A

Drawings, schedule of work, preliminaries, pre ambles, construction programme, the contracts, photo report, asbestos and H&S information

99
Q

What is required to form a contract ?

A
  • Offer
  • Acceptance
  • Consideration
  • Intention to have Legal relations
  • Ability / Performance
100
Q

What is a relevant matter ?

A

Relevant matters are referred to in some construction contracts, such as JCT contracts. A relevant matter is a matter for which the client is responsible that materially affects the progress of the works. This may enable the contractor to claim direct loss and / or expense that has been incurred. Relevant matters might include:

  • Failure to give the contractor possession of the site.
  • Failure to give the contractor access to and from the site.
  • Delays in receiving instructions.
  • Opening up works or testing works that then prove to have been carried out in accordance with the contract.
  • Discrepancies in the contract documents.
  • Disruption caused by works being carried out by the client.
  • Failure by the client to supply goods or materials.
  • Instructions relating to variations and expenditure of provisional sums.
  • Inaccurate forecasting of works described by approximate quantities.
  • Issues relating to CDM.

Relevant matters should not be confused with relevant events. A relevant event is an event that causes a delay to the completion date, which is caused by the client, or is a neutral event not caused by either party. Relevant events entitle the contractor to claim an extension of time; that is for the completion date to be moved. A relevant event does not necessarily entitle the contractor to claim loss and expense. Similarly, a relevant matter need not necessarily result in a delay to the completion date, and so may not always entitle the contractor to an extension of time.

NEC contracts deal with these issues under the single heading ‘compensation events’. They do not treat compensation events as an allocation of blame, but rather an allocation of risk. Any risk that is not specifically identified as being attributed to the client is borne by the contractor.

The Society of Construction Law Delay and Disruption Protocol, 2nd edition, refers to an event or cause of delay or disruption which under the contract is at the risk and responsibility of the employer, as an ‘employer risk event’.

101
Q

What is a relevant event ?

A

Delays on a project will have different contractual consequences depending on the cause of the delay:

Where a delay which impacts on the completion date is caused by the contractor (culpable delay), the contractor will be liable to pay liquidated and ascertained damages (LADs) to the client.
Where a delay which impacts the completion date is not caused by the contractor, it may be a ‘relevant event’, for which the contractor may be entitled to an extension of time and to claim loss and expense incurred as a direct result of the delay.
A relevant event may be caused by the client, or may be a neutral event such as exceptionally adverse weather. The contract should set out what constitutes a relevant event.

Relevant events may include:

  • Variations.
  • Exceptionally adverse weather.
  • Civil commotion or terrorism.
  • Failure to provide information
  • Delay on the part of a nominated sub-contractor.
  • Statutory undertaker’s work.
  • Delay in giving the contractor possession of the site.
  • Force majeure (events that are beyond the reasonable control of a party, such as a war or an epidemic).
  • Loss from a specified peril such as flood.
  • The supply of materials and goods by the client.
  • National strikes.
  • Changes in statutory requirements.

Delays in receiving permissions that the contractor has taken reasonable steps to avoid.
When it becomes reasonably apparent that there is a delay, or that there is likely to be a delay that could merit an extension of time, the contractor gives written notice to the contract administrator identifying the relevant event that has caused the delay. If the contract administrator accepts that the delay was caused by a relevant event, then they may grant an extension of time and the completion date is adjusted.

Claims for extension of time can run alongside claims for loss and expense however, one need not necessarily lead to the other. The contractor is required to prevent or mitigate the delay and any resulting loss, even where the fault is not their own.

Mechanisms allowing extensions of time are not simply for the contractor’s benefit. If there was no such mechanism and a delay occurred which was not the contractor’s fault, then the contractor would no longer be required to complete the works by the completion date and would only then have to complete the works in a ‘reasonable’ time. The client would lose any right to liquidated damages.

NB: On NEC contracts, delays are dealt with slightly differently and are referred to as ‘compensation events’.

102
Q

How did you determine the length of the defect liability period for this contract ?

A

Under JCT MW this is by default 3 months however I would consider if this should be extended to allow for seasonal changes.

103
Q

What factors did you consider when offering design and construction advice?

A

Cost, time, quality

104
Q

What is Retention ?

A

Retention is a sum deduced at each valuation (generally 5%) to provide the client with security that the contractor will return to correct any defects.

105
Q

What is frustration to a contract ?

A

Frustration occurs when circumstances that are not the fault of either party mean it is impossible to continue with the contract. The contract will come to an end without any party being considered to be in breach. it does not cover contracts that were always going to be impossible to perform. For example, it would not apply in the case of a contract to construct a tall building that could not be fulfilled because the ground conditions were completely unsuitable. Some events that may lead to a frustrated contract include: The government imposing unforeseen restrictions on building. Laws being passed that make it illegal to undertake what was promised under the contract The building where works were to be carried out being destroyed. An event that was crucial for the contractual obligations being cancelled.

106
Q

What does Practical Completion mean ?

A

There is no legal basis for the term Practical Completion. It is when the works are complete to the satisfaction of the Contract Administrator. The CA cannot certify PC of there are outstanding works or patent defects, but they also cannot withhold PC for minor defects outstanding.

107
Q

What does Practical Completion trigger ?

A
  • End of contractor liability (termination of any liquidated damages)
  • Insurance handover
  • Handover of the premises
  • Beginning of the defects liability period
  • Retention releases, generally from 5% to 2.5%
108
Q

What counts as exceptionally adverse weather conditions?

A
  • JCT does not define exceptionally adverse weather condition, meaning it is left to discretion. This means that it can be a potential cause for dispute.
  • NEC defines it as a 1 in 10 year event, otherwise the contractor should have allowed for the effects of weather within their price
109
Q

On a commercial project were an end-user has agreed to move into the property. How would you assess a suitable rate for liquidated damages prior to a project ?

A
  • Loss of income from rent
  • Cost of alternative accommodation incurred during the delay
  • Loss of profit to the business at the property where the works are being carried out.
110
Q

What is Loss and Expense ?

A

Construction contracts will generally provide for the contractor to claim direct loss and/or expense as a result of the progress of the works being materially affected by relevant matters for which the client is responsible, such as:

  • Failure to give the contractor possession of the site.
  • Failure to give the contractor access to and from the site.
  • Delays in receiving instructions.
  • Opening up works or testing works that then prove to have been carried out in accordance with the contract.
  • Discrepancies in the contract documents.
  • Disruption caused by works being carried out by the client.
  • Failure by the client to supply goods or materials.
  • Instructions relating to variations and expenditure of provisional sums.
  • Inaccurate forecasting of works described by approximate quantities.
  • Issues relating to CDM.
  • Claims may comprise costs resulting from disruption to the works or from delays to the works (prolongation).

The contractor must give written notice of a claim as soon as it becomes reasonably apparent that the regular progress of the works is being materially affected. This need not necessarily result in a delay to the completion date, and so claims for loss and expense and claims for extensions of time do not necessarily always run together.

Claims are restricted to ‘direct’ loss and expense and so ‘consequential losses’ (such as lost production) are generally excluded. Direct losses are those that ‘flow naturally’ from the breach of contract.

There is disparity between contract types about whether items such as head office overheads can be included in claims for loss and expense, and some court rulings have allowed such claims. If there are specific consequential losses which the parties to the contract wish to exclude, it may be prudent therefore to state these explicitly within the contract.

NB: The New Engineering Contract (NEC3) contains provision for the contractor to claim payment for ‘compensation events’ rather than loss and expense.

111
Q

What is the procedure for an extension of time ?

A
  • The contractor must provide written notice as soon as it becomes apparent that the work will not complete on time.
  • Notice must include the conditions causing the delay.
  • CA must then decide if the condition is relevant event and whether an extension of time is granted.
  • Must notify the contractor as soon as decision is made and within 12 weeks of receipt of notice. If the EOT is warranted, the CA has to fix a later completion date and notify the contractor.
112
Q

What are the prerequisites for claiming liquidated damages? Intermediate Building Contract

A
  • The contractor must have failed to complete the works by the date for completion or any extended date (if an EoT has altered the completion date).
  • The contract administrator must have issued a certificate of non-completion (cl.2.22).
  • The contract administrator must have fulfilled all duties with respect to the award for an extension of time (cl.19.2).
  • The employer must have given the contractor written notice of its intention before the date for the final certificate.
113
Q

What are the prerequisites for claiming liquidated damages? Design and Build Building Contract

A
  • The contractor must have failed to complete the works by the completion date.
  • The employer (or employer’s agent) must have fulfilled all duties with respect to the award for an EoT.
  • The employer (or employer’s agent) must have issued a non-completion notice to the contractor.
  • The employer (or employer’s agent) must have notified the contractor before the due date for the final payment that it may require payment of, or withold, liquidated damages.
114
Q

owefpkdfpjk

A

asdjnkadfjnkdfjno

115
Q

INSURANCE OPTIONS

A
116
Q

ACCELERATION

A
117
Q

ALL CONTRACT PROVISIONS FOR CASE STUDY!!!

A
118
Q

You used a letter of intent for the instruction in Barking, what advise did you provide your client with regards the letters of intent? What was the outcome?

A

Advice:

  • I advised that depending on the contents of a letter of intent, their legal effect can range dramatically and therefore it would need to be carefully drafted by their lawyers to include key provisions that would protect both the employers and contractor’s positions.
  • I advised that a letter of intent should only be used when; the scope of works and price have been agreed, where terms and conditions are agreed (or likely to be agreed), where start and end dates of the project are broadly agreed, when there is a good reason to not wait until the main contract has been agreed.
  • I explained that the client and contractor should have real intentions to enter into the full contract and not issue further letters of intent as if key provisions were not included within the letter of intent that would be included in the full building contract both parties would be exposed. For example if the LOI didn’t include a provision for liquidated damages the employer would not be able to claim if non-completion had occurred.

Outcome:

The client’s lawyers issued a compressive letter of intent that included:

  • Contract sum for the works: £600K.
  • Contract period for the full scope of works.
  • Authority to proceed to cost of £106K - based on a pro rata rate of the contract sum over a 2 week period which was how long it was anticipated to take full agreement and execution of the building contract.
  • Liquidated damages: £35K per week for each section of the works.
  • Insurance: PII, PLI
  • CDM Regulations: CPP and general CDM obligations.
119
Q

Why did you deem it necessary to use a LOI for Barking?

A
  • The contractor needed to make an earlier start on site than originally agreed as the employer had interest for the property from very reputable prospective tenant. However, the tenant would only want the unit if the works could be completed by certain dates which meant the full building contracts had not been drafted or agreed at that point. Therefore a letter of intent would mobilise the contractor to commence works early.
120
Q

Why did you advise single stage tendering rather than two stage?

A
  • The client required the full design prepared the works were tendered and required a lump sum cost for the works to ensure the project was feasible and they could gain board approval for capital.
  • Works were relatively simple in nature and therefore didn’t require contractor input for buildability (would do in first stage of two stage tendering).
121
Q

How are liquidated damages calculated?

A
  • Loss of rental income.
  • Professional fees (e.g CA fees).
  • Looking for alternative accommodation (in case of residential works).
122
Q

Why did you advise that your client couldn’t claim or shouldn’t claim for liquidated damages? Could that have done without any proof?

A
  • Under the terms of the contract the client could have claimed for liquidated damages however, as they did not have a tenant lined up for the unit and therefore were not suffering any actual loss they chose not to pursue LADs to protect the professional relationship between them and the contractor, particularly as the contractor had been the most competitive for number of refurbishment projects across the estate in the past.
123
Q

What are the implications of an extension of time contractually on the parties?

A
  • Relieves the contractor from having to pay liquidated damages.
  • Reserves the employer’s right to claim liquidated damages - if an extension of time couldnt be granted then it would be time at large and contractor would only need to complete the works within a reasonable time.
  • Contractor is still liable for securing the site / insuring.
124
Q

What is the difference between a relevant event and a relevant matter?

A
  • Relevant event is something that causes a project to overrun and is outside of the contractor’s control and are listed in the JCT contract, these can include acts of god, adverse weather conditions, specified perils (fire and flood etc), delays handling over possession of the site, variations and instructions.
  • Relevant matter are matters for which the employer is responsible for and that materially effect the progress of the works and result in the contractor incurring loss and expense. These can include: delays in handing over possession of the site to the contractor, delays in issuing instructions, discrepancies in contract documents.
125
Q

What preconditions must have been met before an employer can claim liquidated damages?

A
  • The contractor must have failed to have complete the works by the date for completion or any extended date.
  • The contract administrator must have issued a certificate of non-completion.
  • The contract administrator must have fulfilled all duties with respect to the award of an extension of time.
  • The employer must have given the contractor written notice of its intension to claim liquidated damages before the date of the final certificate.
126
Q

KEY CASE LAW FOR LADS, EOT etc fact card.

A
127
Q

What is the procedure for interim valuations for the JCT D&B contract?

A
  1. Valuation date occurs at monthly intervals as stated in the contract particulars (or closest working business day).
  2. If the contractor issues their application for payment prior to or on the interim valuation date then then due date is 7 days after the interim valuation date.
  3. If the contractor submits their interim payment application later than the valuation date the due date is 7 days from the date of receipt.
  4. The employer / EA must issue a payment notice five days after the due date.
  5. The final date for payment is 14 days from the due date.
  6. If employer wishes to pay contractor less than sum stated in interim certificate then they must issue a pay less notice no later than 5 days before the final date for payment.

Note: the overall effect of the payment mechanism is that the contractor’s interim payment application is a condition precedent to its right to be paid!

128
Q

What is the procedure for interim valuations for the JCT Intermediate Contract, 2016?

A
129
Q

What happens if a contractor doesn’t submit an application for payment under JCT D&B?

A

They don’t get paid! Receipt of their interim application for payment is a precedent for their payment.

130
Q

What are the contractual rights of the contractor if they are not paid for any amounts due (both IC / D&B)?

A
  • Provision that allows contractor to add simple interest on late payments at 5% over the base rate of the Bank of England. Interest accrues from the final date for payment until paid by the employer.
  • Provision that allows contractor ‘right of suspension’. If the contractor fails to pay the contractor by the final date for payment the contractor has a right to suspend performance of all its’ obligations under the contract which would include carrying out the work and any insurance obligations.
  • Right to terminate the contract - must give the employer notice of the intention.
131
Q

What happens if the contractor disagrees with sum stated on a payment cert / payment notice?

A
  • Where a certificate has been issued, the contractor is only entitled to the amount shown, irrespective of the sum stated in their application for payment and even if the certificate contains an error.
  • Lubenham v South Pembrokeshire District Council - stated that the contractors remedy for an error made in a cert is to request it is corrected in the next cert or to bring proceedings (such as adjudication) to have the certificate adjusted.
132
Q

What is the procedure for the final account?

A
133
Q

What works are valued at an interim valuation?

A
134
Q

Do you have to value materials on site? What are the risks associated with this?

A
135
Q

What is All Risks Insurance?

A

It is an insurance policy that covers all risks normally associated with a construction project and will protect against:

  • The cost for unforeseen loss or damage to building works.
  • Public liability.
  • Tools.
  • Plant owned by the policy holder.
136
Q

What is Insurance Option A?

A
  • Option A insurance is taken out by the contractor and is to be for the full reinstatement value of the works, including professional fees, to the extent entered in the contract particulars. If no rate is stated for professional fees, the default is 15%.
  • The contractor is responsible for keeping the works fully covered and in the event of under insurance, will be liable for any shortfall in recovery from the insurers.
137
Q

What is Insurance Option B?

A
  • Insurance option B is taken out by the employer, and must be for the full reinstatement value of the works, including professional fees. The employer is responsible for keeping the works full covered and, in the event of under-insurance, will be liable for any shortfall.
138
Q

What is Insurance Option C?

A
  • Insurance Option C is applicable where work is being carried out to existing buildings. It include two insurances, both taken out by the employer. The existing structure and contents must be insured against ‘Specified Perils’. New works in, or extensions to, existing buildings must be covered by an ‘All Risks’ insurance policy, which like Options A & B, must be for the full reinstatement value of the works, including professional fees.
139
Q

What is included in a construction phase plan?

A
  • Description of the works – what risks are identified as part of the works.
  • Management of the works - Communication information (project directory and emergency out of hours contacts), working hours, training (toolbox talks and site inductions), welfare facilities, emergency procedures (nearest A&E), emergency, evacuation plan, site waste management plan.
  • Information on how significant site risks will be managed – site traffic management plan, handling of deliveries, site set-up (contractor’s compound), noisy works (abide by LA rules).
  • The health and safety file
140
Q

What is electronic tendering? What are its’ advantages and disadvantages?

A
141
Q

How should contract instructions be issued?

A

JCT contract states:

  • All instructions must be in writing and sent in the format and by the means which the parties ‘have agreed or may from time to time agree in writing’. So written electronic communication can be used to instruct. If no means have been agreed, then written instructions need to be sent via ‘any effective means’.
  • Oral instructions have no effect and will not be valid into confirmed in writing by the contract administrator. If contractor carries out work from oral instruction before receiving it in writing, they are proceeding at their own risk.
142
Q

What is the RICS Contract Administration Guidance Note? You state that you understand that the RICS Contract Administration Guidance Note has now been withdrawn, why is this and what other sources would you now use?

A
  • The document covers the appointing of a contract administrator, describing the role and its responsibilities. Appendices feature useful checklists and also information regarding office administrative procedures.
  • RICS state on their website that it has been withdrawn due to being ‘out of date’.
  • To my knowledge there is not any replacement document but I refer to the Sara Lupten guides and the JCT Practise notes for how to undertake specific CA duties.
143
Q

What kind of items would you cover in the pre-start meeting?

A
  • Introductions – if parties haven’t met before then good to define everyone’s roles in person.
  • Health and safety – F10, Construction Phase Plan, COSHH and CDM regs, site cleanliness, temporary works, contractor’s compound.
  • Contractor / site management – Site manager, office support and progress reports.
  • Communication – Instructions and methods of communication.
  • Contract details: Date of possession, contract sum, programme, completion date, contractor and employers insurances.
  • Site – Access, neighbours, accommodations, working hours, security and any other restrictions.
  • Statutory approvals – Building control.
  • Progress meets and valuations – Agree progress meetings (informal every 2 weeks and formal once a month close to valuation date as possible).
  • Info required.
  • Any other business.
144
Q

What would you include in meeting minutes?

A
  • Date, time and location of meeting.
  • Attendees and apologies.
  • Review of previous minutes.
  • Program / progress of works.
  • Site management.
  • H&S.
  • Matters arising.
  • Client comments.
  • Actions.
145
Q

What are contract amendments? When have you done this? What is the risk?

A
  • Amendments to contract clauses that usually the employer wishes to make do protect themselves usually from issues they have had in the past or to adapt the contract for the works.
  • I have done this for my case study at the request of the client’s solicitors who issued the contract amendments which were then integrated into the standard form contract.
  • The main addition was a clause that outlined certain works / deleterious materials that should not be specified such as high alumina cement, wood wool slabs and asbestos.
  • Only solicitors should design contract amendments as incorrectly modifying standard forms of contract can lead to no interaction / cross referencing of key clauses (not enforceable if not properly cross referenced), issues with interaction of common law – e.g modifying EoT clauses can lead to unwanted outcomes .
146
Q

What is the process if you suspect defective works has been closed up by the contractor? If the works were found to not be defective, is the contractor entitled to an EoT and loss and expense?

A
  • The CA is permitted under the JCT contracts to instruct the contractor to open up completed work for inspection or arrange for testing of any of the work or materials if they have reasonable grounds for suspecting defective work or materials.
  • CA should instruct opening up as soon as it becomes apparent that it needs actioning to prevent any additional further costs.
  • If no defective works are observed - costs for opening up and testing are added to the contract sum and the contractor may be entitled to and Extension of Time and Loss and/or expense.
  • If work is found to be defective, the contactor must provide a written proposal detailing how they will establish if any other defective works. If the CA does not receive this in 7 days or cannot wait they can instruct further opening up work which the contractor will have to incur the expense for even if the additional testing does not uncover any additional defective works.
  • The contractor has the right to object within ten days of receipt of the instruction to undertaken additional opening up works. If the CA and PC cannot agree then the Employer and Principal Contractor may need to refer to the contractual dispute resolution processes.
147
Q

Talk me through how you would undertake a valuation?

A
  • I try to ensure that progress meetings align as close to the due date of each interim valuation to ensure I can view the current progress of works and value them as accurately as possible.
  • On site I will check off all works completed by observing them against the previous valuation document.
  • I will then review the contractor’s Application for Payment when received and input the valuation percentages I believe are correct against all works items. I will request for vesting certificates for any offsite materials that the contractor has included within their application for payment.
  • I then produce a payment certificate and issue to the employer and contractor, along with formal correspondence and the valuation document.
148
Q

What is the risk of overvaluing works?

A

If a contractor become insolvent during the project they employer will be at a loss.

149
Q

What is the risk of valuing goods off site?

A
  • If the contractor has failed to pay a sub-contractor for goods or becomes insolvent then the sub-contractor could claim ownership of the materials.
  • JCT deals with this by stating that all materials delivered to site cant be removed from the site without written consent by the CA - would be deemed a breach of contract and the employer could claim damages. Also those materials on or off site that have been included within a certificate become the property of the employer.
150
Q

What other suites of contracts are there? When would they be used?

A

NEC (New Engineering Contract)

  • Suitable for domestic and internal use.
  • Aims to offer better clarity, flexibility and management processes.
  • Administered by a Project Manager rather than a Contract Administrator.
  • Has early warning notices and compensation events rather than relevant events / matters.
  • Enables a more proactive and collaborative approach rather than focusing on liabilities and risk (JCT).
  • NEC4 - Engineering and Construction Contract: used for a large proportion of the England Olympic infrastructure.
  • Tend to be used for Public Procurement - Phase 2 of HS2 is using NEC3.

FIDIC

  • French suite of contracts.
  • Used Internationally - good to encourage international bidding to secure more competitive tenders.
  • Contract types are referred to by colour:
  1. Green Book - used for engineering and building work of small value, non- specialist work (traditional procurement), allows for contractors design portion.
  2. Red Book - used for when employer undertakes design (traditional procurement).
  3. Orange Book- used when design is carried out by the contractor (Design and Building procurement) and for turnkey contracts (where employer wants a fully completed project fit for the end user.
151
Q

What impact does selecting the fluctuation provision ‘applies’ in the contract?

A
  • If applied, if the cost for materials increases between submitting a tender and ordering the materials, the client will have to pay for the increase, likewise if they reduce in cost the employer will make a saving.
  • Not included in minor works.
152
Q

What is the difference between the roles of the EA and the CA?

A
  • The Employer’s agent is a term of describe an agent acting on behalf of the client who undertakes the same contract administration duties as a contract administrator but for a D&B procurement route that utilises a JCT Design and Build contract as the contract does not make reference to a contract administrator.
  • Like the contract administrator the Employer’s agent should remain impartial at all times but acts on behalf of the employer on all matters, effectively as if the employer’s agent is the employer.
153
Q

What is the difference between a Project Manager, Contract Administrator and an Employer’s agent?

A

Project Manager

  • Party who manages a team to develop and deliver a project for an employer, often from project inception stage, making decisions on behalf of the employer and giving instructions to the contractor. The project manager is to remain impartial with respect to the contract.

Contract Administrator

  • This is a party who is specifically identified within the contract and is solely responsible for administering the contract for the employer. It is an impartial role and only exists at the point the contract is entered into.

Employer’s Agent

  • The Employer’s agent is a term of describe an agent acting on behalf of the client who undertakes the same contract administration duties as a contract administrator but for a D&B procurement route that utilises a JCT Design and Build contract as the contract does not make reference to a contract administrator.
  • Like the contract administrator the Employer’s agent should remain impartial at all times but acts on behalf of the employer on all matters, effectively as if the employer’s agent is the employer.
154
Q

Minor works Build Contract Factsheet

A

Minor works does not contain the following:

  • Sectional completion / work sections.
  • Possession of the site is not given to the contractor.
  • Partial possession.
  • Sub-letting to names sub-contractors (ones that the client stipulates).
  • Provisions for testing and opening up.
  • Loss and expense less expressly provided for.
  • Extension of time full list of relevant events - JCT recommends referring to standard building contract for relevant events!
  • Extension of time, notice regarding delay - less onerous on the contractor they are only required to give notice to the contract administrator ‘if it becomes apparent that the works will not be completed by the date for completion’ as opposed to IC16 whereby the contractor must give written notice as soon as it becomes apparent that progress is likely to be delayed even if it doesn’t prevent completion of works by the completion date. Additionally MW only states that the contractor does not have to sight the reason for the delay.
155
Q

What contract would you use on a more complex / larger project?

A