CW Questions 04 Flashcards

1
Q

Activity A is worth $200, is 100% complete, and actually cost $200. Activity B is worth $75, is 90% complete, and actually cost $120 so far. Activity C is worth $200, is 75% complete, and has cost $175 so far. The total budget is $1,000. What is the estimate to complete for the project?

(A) $1,000
 	(B) $1,100.04
(C) $1,185.63
(D) $691.24
A

Correct Answer: (D) $691.24

Explanation: To calculate this value, calculate the EAC first. To calculate the EAC, calculate the CPI first. To calculate the CPI, calculate earned value (EV) and actual cost (AC) first. Multiply the percent complete of each activity by its planned value (PV) to obtain the EV for each activity. Sum the earned value of each activity to determine the total earned value. Sum the actual cost of each activity to determine the total actual cost. Divide the earned value of $417.50 by the actual cost of $495.00 to obtain a CPI of 0.84. Divide the BAC of $1,000 by the CPI to obtain an estimated at completion of $1,186.24. To determine the estimate to complete, subtract the actual cost (AC) of $495.00 from the estimate at completion (EAC) of $1,186.24. The difference is $691.24. [section 7.14.2]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Of the following, which is the best description of the relationship between quality control measurements and the Perform Quality Assurance process?

(A) They are an output of the Perform Quality Assurance process
 	(B) They can be fed into the Perform Quality Assurance process to	validate the efficiency and cost effectiveness of Perform Quality Control
(C) They are an output of the Perform Quality Control process
(D) Both A and C
A

Correct Answer: (B) They can be fed into the Perform Quality Assurance process to validate the efficiency and cost effectiveness of Perform Quality Control

Explanation: They can be fed into the Perform Quality Assurance process to validate the efficiency and cost effectiveness of Perform Quality Control. They are an output of the Perform Quality Control process, but that does not describe the relationship. The other answers are noise. [section 8.9, section 8.10]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The IT infrastructure Project Manager is managing his project team. What are the key tools and techniques for this process that are available to the Project Manager?

(A) Observation and conversation, conflict management, issue log,	project performance appraisals, team performance assessments, 	performance reports, and interpersonal skills
 	(B) Observation and conversation, conflict management, issue log,	project performance appraisals, performance reports, and interpersonal 	skills
(C) Observation and conversation, conflict management, issue log,	project performance appraisals, and interpersonal skills
(D) Observation and conversation, conflict management, issue log,	project performance appraisals, team performance assessments, and 	interpersonal skills
A

Correct Answer: (C) Observation and conversation, conflict management, issue log, project performance appraisals, and interpersonal skills

Explanation: Observation and conversation, conflict management, issue log, project performance appraisals, and interpersonal skills are the key tools and techniques of the Manage Project Team process. [section 9.4]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

One of the activities a Project Manager performs on a day to day basis is communicating with individual team members, the team, company personnel, vendors, and customers. Approximately how much of a Project Manager’s job is spent communicating?

(A) At least 30%
 	(B) Not more than 50%
(C) Approximately 90%
(D) 100%
A

Correct Answer: (C) Approximately 90%

Explanation: Approximately 90% of a Project Manager’s time is spent communicating. This could be via email, meetings, listening, speaking, web conference, etc. [section 10.4.2]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

The network project has been very challenging. The cost performance index is presently 0.95 and the schedule performance index is 0.91. Risk could have been managed better from the start of this project. Halfway through the execution of the project management plan, the Project Manager assigned one person to do nothing but monitor for risks and work with the people who implemented the risk response plans. Which of the following is the most complete description of the tools and techniques of the Monitor and Control Risks process?

(A) Risk reassessment, risk audits, variance and trend analysis, reserve 	analysis, status meetings
 	(B) Risk reassessment, risk audits, variance and trend analysis, reserve 	analysis
(C) Risk reassessment, performance measurement, variance and trend	analysis, reserve analysis, status meetings
(D) Risk reassessment, performance measurement, variance and trend	analysis, reserve analysis
A

Correct Answer: (A) Risk reassessment, risk audits, variance and trend analysis, reserve analysis, status meetings

Explanation: Risk reassessment, risk audits, variance and trend analysis, reserve analysis, status meeting, and technical performance measurement are the tools and techniques of the Monitor and Control Risks process. [section 11.7]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The project will be using a company to provide the technicians for a national network upgrade project. The services buyer is providing to the prospective services seller a greatly detailed description of what it wants the seller to do on the project. What type of document is being provided to the seller?

(A) Request for information (RFI)
 	(B) Request for proposals (RFP)
(C) Invitation for bid (IFB)
(D) Request for quote (RFQ)
A

Correct Answer: (B) Request for proposals (RFP)

Explanation: A request for proposals (RFP) deals with a detailed, very specific approach to a customized solution. A request for information (RFI) deals with finding potential vendors for consideration for proposals or quotes. A request for quotes obtains prices from a company for goods or services. An invitation for bid (IFB) is similar to the RFP but typically used in government contracting. [section 12.1.10]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The PMO is conducting a meeting and a fellow Project Manager is reporting that the project is on schedule and under budget. You discover from the project’s team members that the project is behind schedule by four weeks and is over budget. What should you do?

(A) Notify senior management
 	(B) Report the Project Manager to PMI
(C) Ask the PMO to investigate the project status
(D) Review with the Project Manager how this status was produced
A

Correct Answer: (D) Review with the Project Manager how this status was produced

Explanation: As a Project Manager, you should review this information with the Project Manager regarding its accuracy. Asking the PMO to investigate the project status is the next step followed by notifying senior management. The final step is to report the Project Manager to PMI. [section 13.1.3]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

W hat is created in the Initiating Process Group?

(A) Project charter, requirements documentation
 	(B) Project Scope Statement, various management plans
(C) Project charter, project scope statement
(D) Project charter, stakeholder register, stakeholder management plan
A

Correct Answer: (D) Project charter, stakeholder register, stakeholder management plan

Explanation: Answer D contains all documents created during the Initiating process group. All others are created during the Planning process group. [section 3.4.1]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

During the Monitor and Control Project Work process, the Project Manager is placing a great deal of reliance on expert judgment. Do you think this reliance is well founded?

(A) No, if expert judgment is so important there wouldn't be such a market 	for modeling tools
 	(B) Not to such an extent, because modeling tools are more effective
(C) Yes, although modeling tools are effective, expert judgment is often 	more significant and more accurate than those tools
(D) Not to such an extent, because expert judgment functions only as a	check against the results of modeling tools
A

Correct Answer: (C) Yes, although modeling tools are effective, expert judgment can be more significant and more accurate than those tools

Explanation: Although modeling tools are effective, expert judgment can be more significant and more accurate than those tools. The other answers are noise. [section 4.6]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The work breakdown structure represents what?

(A) The decomposition of the work of the project
 	(B) The activity list of the project
(C) The schedule
(D) The decomposition of the activity list
A

Correct Answer: (A) The decomposition of the work of the project

Explanation: The WBS represents the decomposition of the work of the project. If the work is shown in the WBS, it is in the project; if it’s not shown in the WBS, it’s not in the project. Activity lists are sometimes called activity definitions, and the schedule is created after the WBS is created. [section 5.3.1]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The Estimate Activity Duration process is just beginning for the web development project. What will the project manager and his team utilize to create the estimates?

(A) Activity list, resource calendars, project scope statement, project	management plan, activity resource requirements
 	(B) Activity list, activity duration estimates, resource calendars, project 	scope statement, activity resource requirements
(C) Activity list, activity duration estimates, resource calendars, project 	scope statement, project management plan, activity resource 	requirements
(D) Activity list, resource calendars, project scope statement, activity 	resource requirements
A

Correct Answer: (D) Activity list, resource calendars, project scope statement, activity resource requirements

Explanation: The key inputs of the Estimate Activity Duration process are activity list, resource calendars, project scope statement, and activity resource requirements. [section 6.4]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Which of the following shows the remaining amount to be spent on the project based on current spending efficiency?

(A) Cost variance
 	(B) Estimate to complete
(C) Estimate at completion
(D) Budget remaining
A

Correct Answer: (B) Estimate to complete

Explanation: Estimate to complete shows the remaining amount to be spent on a project based on spending efficiency. This value is the difference between actual cost (AC) and estimate at completion. Estimate at completion is a forecast of total project cost, based on spending efficiency. Cost variance is the difference between the amount of work done and what was paid for it. “Budget remaining” is noise. [section 7.14.1]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The company is implementing a stricter and more proactive quality standard for projects in an attempt to improve the quality culture. Once implemented, which of the following impacts on the product support department is most likely to occur?

(A) Increased warranty support
 	(B) Decreased warranty support
(C) Increased inventory requirements
(D) Decreased inventory requirements
A

Correct Answer: (B) Decreased warranty support

Explanation: Typically, the result of implementing more proactive quality standards decreases the need for warranty support. The other answers are noise. [section 8.8.5]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Leadership and managerial style evolve within the project management life cycle. Of the following, which is the best description of the evolution of leadership and managerial style?

(A) Directing, coaching, delegation, facilitation, and support
 	(B) Directing, mentoring, facilitation, and support
(C) Directing, mentoring, delegation, facilitation, and support
(D) Directing, coaching, facilitation, and support
A

Correct Answer: (D) Directing, coaching, facilitation, and support

Explanation: the evolution of leadership and managerial style starts with directing. As the project gains momentum, coaching is applied. When significant work is completed facilitation comes into play. Support is applied as the project is closing. [section 9.1.6]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Of the following, which are the key tools available for use during the Manage Stakeholder Expectations process?

(A) Communication methods, stakeholder analysis, interpersonal skills,	and management skills
 	(B) Issue Logs, stakeholder analysis, and approved change requests
(C) Issue Logs, stakeholder analysis, reporting systems, and approved	change requests
(D) Communication methods, interpersonal skills, and management skills
A

Correct Answer: (D) Communication methods, interpersonal skills, and management skills

Explanation: Communication methods, interpersonal skills, and management skills are the key tools cited for the Manage Stakeholder Expectations process. [section 10.6]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

The project management team has just completed the process of Identifying Risks on the project. They have broken the information into categories and displayed this information in a graphical format. What have they created?

(A) Prioritized list of quantified risks
 	(B) Risk breakdown structure
(C) Risk probabilities and impact matrix
(D) Risk checklist analysis chart
A

Correct Answer: (B) Risk breakdown structure
Explanation: The risk breakdown structure (RBS) is a graphical representation of the risk categorization and risks within those categories of the project. The prioritized list of quantified risks comes in the risk register and involves risk ranking, not identification categorization. The risk probabilities and impact matrix is part of the risk management plan and is used in qualitative risk analysis. The risk checklist analysis chart is noise. [section 11.2.2]

17
Q

A contract is being negotiated with a single source provider that will contain special provisions since the work is being performed at a loss so the provider can gain experience in the market. Of the following, which best represents a special provision?

(A) Payment terms, including arbitration remedies
 	(B) Intellectual property rights and required non-disclosure documentation
(C) Ability to sub-contract
(D) Criteria around which the provider of services can refer to the work
A

Correct Answer: (D) Criteria around which the provider of services can refer to the work

Explanation: Special provisions are extra items that are added to a contract after negotiations have occurred. Standard terms and conditions are typically part of a template the company will use in a contract and often address payment options, intellectual property rights, and sub-contracting. [section 12.2.9]

18
Q

You learn that a former boss of yours who is a PMP has committed to his boss that 100% of the PMO that he manages at their company will be certified. The only problem is that one of the people who passed the test is 22 years old and going to junior college. You know that this person has been working in this area for only two years at most. When asking about it, you are told that they were “creative” with the experience hours of the PMP application. What is the best thing to do?
(A) Contact your former boss and let him know it’s not appropriate
(B) Contact PMI to report the name of the person, the name of supervisor, and the name of the company
(C) Tell your old boss to hire you back or you will turn him into PMI
(D) Ignore it because you don’t work there anymore

A

Correct Answer: (B) Contact PMI to report the name of the person, the name of supervisor, and the name of the company
Explanation: As part of professional and social responsibility, you are responsible for reporting possible violations of the PMI Code of Ethics and Professional Conduct. Contacting your former boss and letting him know it’s not appropriate, ignoring it because you don’t work there anymore, and telling your old boss to hire you back or you will turn him into PMI do not abide with the PMI Code of Ethics and Professional Conduct. [section 13.2.4]

19
Q

A business analyst has a career path that has been very important to her throughout the 10 years of her career. She is put on a very important project with a strong matrix organizational structure. Which of the following is likely viewed as the most serious drawback of being on the project?
(A) Being away from the group might make career advancement in the department more difficult.
(B) Working with people who have similar skills
(C) Working long hours because the project is a high priority
(D) Not being able to take the BAP Certification test because she will be so busy

A

Correct Answer: (A) Being away from the group might make career advancement in the department more difficult.

Explanation: Being away from the normal group and not being able to be as easily promoted is the best answer. Being in a strong matrix environment feels fairly similar to being in a projectized organization where skill set specialty in groups does not have as high a priority. The other answers are noise. [section 3.6.3]

20
Q

The Project Manager and her team have worked diligently to complete the project scope on time and within budget. They are in the process of creating the project files. Of the following, which is the best and most complete definition of project files?

(A) Project documents that record what occurred during the project and	what changes were approved
 	(B) Project documents that record what occurred during the project, what 	changes were approved, and what decisions were made
(C) Project documents that record what occurred during the project, basic 	project statistics (scope, time, and cost), and what changes were	approved
(D) Project documents that record what occurred during the project, what 	changes were approved, basic project statistics (scope, time, and cost),	and what decisions were made
A

Correct Answer: (B) Project documents that record what occurred during the project, what changes were approved, and what decisions were made

Explanation: Project files are project documents that record what occurred during the project, what changes were approved, and what decisions were made. Financial records and legal documents are included in these files [section 4.8.1]