Cost Management ITTO Flashcards

1
Q

7.1

Plan Cost Management - Inputs

A
  1. 1.3.1 Project Charter
  2. 2.3.1 Project Management Plan
  3. 1.3.1 Schedule Management Plan
  4. 1.3.1 Risk Management Plan
  5. 1.1.3 Enterprise Environmental Factors (E.E.F.)
  6. 1.1.4 Organizational Process Assets (O.P.A.)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

7.1

Plan Cost Management - Outputs

A

07.1.3.1 Cost Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

7.1

Plan Cost Management - Tools & Techniques

A
  1. 1.2.1 Expert Judgment
  2. 0.2 Data Analysis Tools and Techniques Group
  3. 5.2.2 Alternative Analysis
  4. 1.2.4 Meetings
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

7.2

Estimate Costs - Inputs

A
  1. 2.3.1 Project Management Plan
  2. 4.3.1 Scope Baseline
  3. 1.3.1 Cost Management Plan
  4. 1.3.1 Quality Management Plan
  5. 3.1.2 Project Documents
  6. 4.3.1 Lessons Learned register
  7. 5.3.2 Project Schedule
  8. 2.3.1 Resources Requirements
  9. 2.3.1 Risk Register
  10. 1.1.3 Enterprise Environmental Factors (E.E.F.)
  11. 1.1.4 Organizational Process Assets (O.P.A.)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

7.2

Estimate Costs - Outputs

A
  1. 2.3.1 Cost Estimates
  2. 4.3.2 Basis of Estimates
  3. 3.1.2 Project Documents
  4. 1.3.2 Assumption log
  5. 4.3.1 Lessons Learned register
  6. 2.3.1 Risk Register
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

7.2

Estimate Costs - Tools & Techniques

A
  1. 1.2.1 Expert Judgment
  2. 4.2.2 Analogous Estimating
  3. 4.2.5 Bottom up estimating
  4. 4.2.3 Parametric Estimating
  5. 4.2.4 3-points Estimating
  6. 0.2 Data Analysis Tools and Techniques Group
  7. 5.2.2 Alternative Analysis
  8. 2.2.6 Cost of Quality
  9. 4.2.6 Reserve analysis
  10. 3.2.2 Project Management Information System (PMIS)
  11. 0.2 Decision making Tools and Techniques Group
  12. 5.2.3 Voting
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

7.3

Determine Budget - Inputs

A
  1. 2.3.1 Project Management Plan
  2. 4.3.1 Scope Baseline
  3. 1.3.1 Cost Management Plan
  4. 1.3.1 Resources Management Plan
  5. 3.1.2 Project Documents
  6. 4.3.2 Basis of Estimates
  7. 5.3.2 Project Schedule
  8. 2.3.1 Cost Estimates
  9. 2.3.1 Risk Register
  10. 1.1.1 Business Documents
  11. 1.1.2 Agreements
  12. 1.1.3 Enterprise Environmental Factors (E.E.F.)
  13. 1.1.4 Organizational Process Assets (O.P.A.)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

7.3

Determine Budget - Outputs

A
  1. 3.3.1 Cost Baseline
  2. 3.3.2 Project Funding Requirements
  3. 3.1.2 Project Documents
  4. 5.3.2 Project Schedule
  5. 2.3.1 Cost Estimates
  6. 2.3.1 Risk Register
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

7.3

Determine Budget - Tools & Techniques

A
  1. 1.2.1 Expert Judgment
  2. 3.2.2 Cost Aggregation
  3. 3.2.6 Financing
  4. 3.2.5 Funding Limit Reconciliation
  5. 3.2.4 Historical Information review
  6. 0.2 Data Analysis Tools and Techniques Group
  7. 4.2.6 Reserve analysis
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

7.4

Control Costs - Inputs

A
  1. 2.3.1 Project Management Plan
  2. 2.3.1 Performance Measurement Baseline
  3. 1.3.1 Cost Management Plan
  4. 3.3.1 Cost Baseline
  5. 3.1.2 Project Documents
  6. 4.3.1 Lessons Learned register
  7. 3.3.2 Work Performance Data
  8. 3.3.2 Project Funding Requirements
  9. 1.1.4 Organizational Process Assets (O.P.A.)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

7.4

Control Costs - Outputs

A
  1. 3.3.4 Change Requests
  2. 3.3.4 Work Performance Information
  3. 4.3.2 Cost Forecasts
  4. 2.3.1 Project Management Plan
  5. 2.3.1 Performance Measurement Baseline
  6. 1.3.1 Cost Management Plan
  7. 3.3.1 Cost Baseline
  8. 3.1.2 Project Documents
  9. 1.3.2 Assumption log
  10. 4.3.1 Lessons Learned register
  11. 4.3.2 Basis of Estimates
  12. 2.3.1 Cost Estimates
  13. 4.3.2 Cost Forecasts
  14. 2.3.1 Risk Register
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

7.4

Control Costs - Tools & Techniques

A
  1. 1.2.1 Expert Judgment
  2. 3.2.2 Project Management Information System (PMIS)
  3. 4.2.3 To-Complete Performance Index
  4. 0.2 Data Analysis Tools and Techniques Group
  5. 5.2.2 Earned Value Analysis (EVA)
  6. 4.2.6 Reserve analysis
  7. 5.2.2 Trend analysis
  8. 5.2.2 Variance analysis
How well did you know this?
1
Not at all
2
3
4
5
Perfectly