Cost Management Flashcards

Develop essential cost management skills by exploring trends, planning strategies, and estimation techniques. Learn to create budgets, establish cost baselines, implement controls, and apply earned value management (EVM) to track project performance and cost efficiency.

1
Q

Define:

100-Point Method

A

A method of prioritization where stakeholders each get 100 points to vote on features.

For example, if there are five possible features, a stakeholder could assign 40 points to Feature A, 25 points to Feature B, 20 points to Feature C, 10 points to Feature D, and 5 points to Feature E. Each stakeholder would assign points to each feature based on their prioritization of the feature.

Points for each feature are summed and this total helps prioritize the features based on the collective scoring of the features by the stakeholders.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define:

Actual Cost

(AC)

A

The actual amount of monies the project has spent to date.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Define:

Analysis

A

To develop possible solutions by studying the problem and its underlying need and to understand the information provided.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Define:

Budget Estimate

A

This estimate is also somewhat broad and is used early in the planning processes and also in top-down estimates.

The range of variance for the estimate can be from –10 percent to +25 percent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Define:

Burn Rate

A

The rate of resources consumed by the team; also cost per iteration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Define:

Cash-Flow Forecasting

A

This is the cash availability planning for a project, it details when money would be needed in a project across the entire lifecycle.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Define:

Commercial Database

A

A cost-estimating approach that uses a database, typically software-driven, to create the cost estimate for a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Define:

Contingency Reserve

A

A contingency allowance to account for overruns in costs.

Contingency allowances are used at the project manager’s discretion and with management’s approval to counteract cost overruns for scheduled activities and risk events.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Define:

Cost Aggregation

A

Costs are parallel to each WBS work package. The costs of each work package are aggregated into their corresponding control accounts.

Each control account is then aggregated to the sum of the project costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Define:

Cost Budgeting

A

The cost aggregation achieved by assigning specific dollar amounts for each of the scheduled activities or, more likely, for each of the work packages in the WBS.

Cost budgeting applies the cost estimates over time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Define:

Cost Change Control System

A

A system that examines any changes associated with scope changes, the cost of materials, and the cost of any other resources and the related impact on the overall project cost.

It is part of integrated change control.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

List:

Cost Estimate Content

A
  • Labor
  • Materials
  • Equipment
  • Services
  • Facilities
  • Information technology
  • Special categories, such as inflation and contingency reserve
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Define:

Cost of Nonconformance to Quality

A

The cost associated with not satisfying quality expectations.

This is also known as the cost of poor quality.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Define:

Cost of Poor Quality

A

The monies spent to recover from not adhering to the expected level of quality.

Examples may include rework, defect repair, loss of life or limb because safety precautions were not taken, loss of sales, and loss of customers. This is also known as the cost of nonconformance to quality.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Define:

Cost of Quality

A

The monies spent to attain the expected level of quality within a project.

Examples include training, testing, and safety precautions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Define:

Cost Performance Index

(CPI)

A

To measure the cost spent on a project and its efficiency.

The formula is CPI = Earned Value / Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Define:

Cost Variance

(CV)

A

The difference of the earned value amount and the cumulative actual costs of the project.

The formula is CV = EV – AC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Define:

Cost-Estimating Policies

A

This is an organizational Policy on how the project manager or the cost estimator creates the project cost estimate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Define:

Definitive Estimate

A

This estimate type is one of the most accurate, it is used late in the planning processes and is associated with bottom-up estimating.

You need the WBS to create the definitive estimate. The range of variance for the estimate can be from –5 percent to +10 percent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Define:

Earned Value

(EV)

A

The physical work completed to date and the authorized budget for that work. It is the percentage of the BAC that represents the actual work completed in the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Define:

Earned Value Management

(EVM)

A

This is the process of measuring the performance of project work against what was planned to identify variances, to note opportunities to improve the project, or just to check the project’s health.

It is a system of mathematical formulas that compares work performed against work planned, and it measures the actual cost of the work your project has performed.

EVM is an important part of cost control because it enables a project manager to predict future variances from the expenses to date within the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Define:

Estimate at Completion

(EAC)

A

Forecasting formulas that predict the likely completed costs of the project based on current scenarios within the project.

23
Q

Define:

Estimate To Complete

(ETC)

A

An earned value management formula that predicts how much funding the project will require to be completed.

Three variations of this formula are based on conditions the project may be experiencing.

24
Q

List:

Five EVM Formula Rules

A
  • Always start with EV.
  • Variance means subtraction.
  • Index means division.
  • Less than 1 is bad in an index, and greater than 1 is good. Except for TCPI, which is the reverse.
  • Negative is bad in a variance.
25
# Define: Fixed Costs
Costs that remain constant throughout the life of the project. ## Footnote Examples are the cost of rented equipment for the project, the cost of a consultant brought on to the project, and so on.
26
# Define: Funding Limit
Most projects have a determined budget in relation to the project scope. There may be a qualifier on this budget, such as plus or minus 10 percent based on the type of cost estimate created.
27
# Define: Funding Limit Reconciliation
An organization’s approach to managing cash flow against project deliverables is based on a schedule, milestone accomplishment, or data constraints.
28
# Define: Funding with Debt
This indicates when the company pays for the project through a line of credit or bank loan.
29
# Define: Funding with Equity
This refers to when an organization balances the project expenses with equity they have in their assets.
30
# Define: Gold Plating
This occurs when the project manager, the project sponsor, or even a stakeholder adds in project extras to consume the entire project budget. ## Footnote It’s essentially adding unneeded features to the product to use up all the funds allocated to the project. Gold plating delivers more than what’s needed and can create new risks and work, and it can contribute to a decline in team morale.
31
# Define: Indirect Costs
These are costs attributed to the cost of doing business. ## Footnote For example, utilities for the performing organization, access to a training room, project management software license, and so on.
32
# Define: Known Unknown
An event that will likely happen within the project, but when it will happen and to what degree is unknown. ## Footnote These events, such as delays, weather or vendor delays, are usually risk-related.
33
# Define: Learning Curve
An approach that assumes the cost per unit decreases the more units workers complete, because workers learn as they complete the required work.
34
# Define: Management Contingency Reserve
This is the “filler” between the cost baseline and the maximum funding. It bridges the gap between the project cost baseline and the maximum funding to complete the project. ## Footnote Contingency reserve is often allotted to risks, specifically "unknown unknowns" that happen in the project.
35
# Define: Monopoly Money
To give fake money to business features in order to compare the relative priority of those features.
36
# Define: Oligopoly
A market condition where the market is so tight that the actions of one vendor affect the actions of all the others.
37
# Define: Opportunity Cost
The total cost of the opportunity that is refused to realize an opposing opportunity.
38
# Define: Parametric Estimating
An approach using a parametric model to extrapolate what costs will be needed for a project. ## Footnote For example, cost per hour and cost per unit. It can include variables and points based on conditions.
39
# Define: Planned Value | (PV)
The work scheduled and the budget authorized to accomplish that work. ## Footnote It is the percentage of the BAC that reflects where the project should be at a particular point in time.
40
# Define: Positive Value
To maximize value through incremental work in order to gain competitive advantage.
41
# Define: Project Variance
The final variance, which is discovered only at the project’s completion. ## Footnote The formula is VAR = BAC – AC.
42
# Define: Reserve Analysis
Cost reserves are for unknown unknowns within a project. The management reserve is not part of the project cost baseline, but is included as part of the project budget.
43
# Define: Rough Order of Magnitude
This rough estimate is used during the initiating processes and in top-down estimates. ## Footnote The range of variance for the estimate can be from –25 percent to +75 percent.
44
# Define: Schedule Performance Index | (SPI)
Measures the project based on its schedule performance. The formula is SPI = EV/PV.
45
# Define: Schedule Variance | (SV)
The comparison of what was planned and what was experienced about a project’s schedule. The formula is SV = EV – PV. ## Footnote The difference between the earned value and the planned value.
46
# Define: Self-Funding
This is when an organization pays for the project expenses from their cash flow.
47
# Define: Single Source
Many vendors can provide what your project needs to purchase, but you prefer to work with a specific vendor.
48
# Define: Sole Source
Only one vendor can provide what your project needs to purchase. ## Footnote Examples include a specific consultant, specialized service, or unique type of material.
49
# Define: Sunk Costs
Monies that have already been invested in a project.
50
# Define: To-Complete Performance Index | (TCPI)
A formula to forecast the likelihood of a project to achieve its goals based on what’s happening in the project right now. ## Footnote To determine whether your project will meet the budget at completion, you’ll use this formula: TCPI = (BAC—EV)/(BAC—AC). To determine whether your project will meet the newly created estimate at completion, you’ll use this version of the formula: TCPI = (BAC—EV)/(EAC—AC).
51
# Define: Value Stream
A Lean principle that includes all of the actions needed to create value for the project customer from the very start. ## Footnote It’s about maximizing value and eliminating waste in the project.
52
# Define: Variable Costs
Costs that change based on the conditions applied in the project (the number of meeting participants, the supply of and demand for materials, and so on).
53
# Define: Variance
The difference between what was expected and what was experienced. ## Footnote Cost variances are usually cost overruns and have to be explained, typically in an exceptions report because it is an exception to the baseline. Cost variances can create project risks, cuts to the project scope, and other measures to accommodate the overrage in expenses.
54
# Define: Variance At Completion | (VAC)
A forecasting formula that predicts how much of a variance the project will likely have based on current conditions within the project. ## Footnote The formula is VAC = BAC – EAC.