Cost Management Flashcards
Develop essential cost management skills by exploring trends, planning strategies, and estimation techniques. Learn to create budgets, establish cost baselines, implement controls, and apply earned value management (EVM) to track project performance and cost efficiency.
Define:
100-Point Method
A method of prioritization where stakeholders each get 100 points to vote on features.
For example, if there are five possible features, a stakeholder could assign 40 points to Feature A, 25 points to Feature B, 20 points to Feature C, 10 points to Feature D, and 5 points to Feature E. Each stakeholder would assign points to each feature based on their prioritization of the feature.
Points for each feature are summed and this total helps prioritize the features based on the collective scoring of the features by the stakeholders.
Define:
Actual Cost
(AC)
The actual amount of monies the project has spent to date.
Define:
Analysis
To develop possible solutions by studying the problem and its underlying need and to understand the information provided.
Define:
Budget Estimate
This estimate is also somewhat broad and is used early in the planning processes and also in top-down estimates.
The range of variance for the estimate can be from –10 percent to +25 percent.
Define:
Burn Rate
The rate of resources consumed by the team; also cost per iteration.
Define:
Cash-Flow Forecasting
This is the cash availability planning for a project, it details when money would be needed in a project across the entire lifecycle.
Define:
Commercial Database
A cost-estimating approach that uses a database, typically software-driven, to create the cost estimate for a project.
Define:
Contingency Reserve
A contingency allowance to account for overruns in costs.
Contingency allowances are used at the project manager’s discretion and with management’s approval to counteract cost overruns for scheduled activities and risk events.
Define:
Cost Aggregation
Costs are parallel to each WBS work package. The costs of each work package are aggregated into their corresponding control accounts.
Each control account is then aggregated to the sum of the project costs.
Define:
Cost Budgeting
The cost aggregation achieved by assigning specific dollar amounts for each of the scheduled activities or, more likely, for each of the work packages in the WBS.
Cost budgeting applies the cost estimates over time.
Define:
Cost Change Control System
A system that examines any changes associated with scope changes, the cost of materials, and the cost of any other resources and the related impact on the overall project cost.
It is part of integrated change control.
List:
Cost Estimate Content
- Labor
- Materials
- Equipment
- Services
- Facilities
- Information technology
- Special categories, such as inflation and contingency reserve
Define:
Cost of Nonconformance to Quality
The cost associated with not satisfying quality expectations.
This is also known as the cost of poor quality.
Define:
Cost of Poor Quality
The monies spent to recover from not adhering to the expected level of quality.
Examples may include rework, defect repair, loss of life or limb because safety precautions were not taken, loss of sales, and loss of customers. This is also known as the cost of nonconformance to quality.
Define:
Cost of Quality
The monies spent to attain the expected level of quality within a project.
Examples include training, testing, and safety precautions.
Define:
Cost Performance Index
(CPI)
To measure the cost spent on a project and its efficiency.
The formula is CPI = Earned Value / Actual Cost
Define:
Cost Variance
(CV)
The difference of the earned value amount and the cumulative actual costs of the project.
The formula is CV = EV – AC.
Define:
Cost-Estimating Policies
This is an organizational Policy on how the project manager or the cost estimator creates the project cost estimate.
Define:
Definitive Estimate
This estimate type is one of the most accurate, it is used late in the planning processes and is associated with bottom-up estimating.
You need the WBS to create the definitive estimate. The range of variance for the estimate can be from –5 percent to +10 percent.
Define:
Earned Value
(EV)
The physical work completed to date and the authorized budget for that work. It is the percentage of the BAC that represents the actual work completed in the project.
Define:
Earned Value Management
(EVM)
This is the process of measuring the performance of project work against what was planned to identify variances, to note opportunities to improve the project, or just to check the project’s health.
It is a system of mathematical formulas that compares work performed against work planned, and it measures the actual cost of the work your project has performed.
EVM is an important part of cost control because it enables a project manager to predict future variances from the expenses to date within the project.
Define:
Estimate at Completion
(EAC)
Forecasting formulas that predict the likely completed costs of the project based on current scenarios within the project.
Define:
Estimate To Complete
(ETC)
An earned value management formula that predicts how much funding the project will require to be completed.
Three variations of this formula are based on conditions the project may be experiencing.
List:
Five EVM Formula Rules
- Always start with EV.
- Variance means subtraction.
- Index means division.
- Less than 1 is bad in an index, and greater than 1 is good. Except for TCPI, which is the reverse.
- Negative is bad in a variance.