Contract practice L1 Flashcards

Contract practice L1

1
Q

What key function does a contract perform on a construction project?

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a contract?

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Define express terms?

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Define implied terms?

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What six conditions need to be met for a contract to be in place?

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the main suites of construction contracts?

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is tort?

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the influences which will affect contract selection?

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Can you name three standard forms of contracts that can be used on a construction project?

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What do you understand about the following forms of contract; FIDIC JCT NEC ACA ICC and IChemE?

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does JCT stand for?

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Name the key components of the JCT contract suite.

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

When was the JCT contract suite last updated? Tell me about some of the key changes that were made.

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How was the JCT contract suite modernised through the last update?

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How does JCT facilitate electronic working?

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

How does the JCT work alongside the Construction Playbook?

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How has the JCT contract suite incorporated diversity and inclusion?

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is the JCT Fluctuations Hub used for?

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Explain the JCT Target Cost Contract to me.

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What form of NEC contract might the Target Cost Contract be a good alternative for?

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What are the main parts of the JCT contracts?

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What are the JCT schedules?

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

How are relevant events and relevant matters dealt with under NEC?

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

How does NEC deal with loss and expense?

A

A

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
What types of insurance are required under JCT?
A
26
How is fitness for purpose dealt with under JCT DB / CDP?
A
27
What is the contractor’s design liability under JCT contracts (for CDP elements)?
A
28
What are the differences in procurement between JCT Standard Form and JCT with Contractor's Design?
A
29
When would you use a JCT IC or MW contract?
A
30
Can benefits be assigned under JCT contracts?
A
31
When and why would you use each?
A
32
Explain the role of main sub and package contracts from the standard suites you are aware of.
A
33
In a contract you have used explain the following; roles and responsibilities of the parties pricing options and risk allocation.
A
34
What client specific considerations have you taken into account when selecting a contract type?
A
35
What insurance provisions are in the JCT and NEC standard forms of contract?
A
36
What is a contractor’s all risk insurance or contract works insurance?
A
37
What do you understand by insurance in joint names?
A
38
What is a collateral warranty?
A
39
What is your understanding of what a letter of intent is?
A
40
What is a comfort letter/consent to spend/recognition of contract?
A
41
When might you use advance payments?
A
42
What is the final account?
A
43
Who prepares the final account in a JCT form of contract?
A
44
Who prepares the final account in the NEC4 form of contract?
A
45
What is the purpose of a final account?
A
46
On the issue of the final account what are the relevant time periods in a JCT form of contract?
A
47
When must the final certificate be issued?
A
48
Tell me two of the information or statements that must be contained in the final certificate.
A
49
What are the usual constituents of a final account?
A
50
What is released to the contractor in the final certificate?
A
51
What are the usual constituents of a final account?
A
52
What are the four elements of a valid contract?
A
53
What third party rights might be included in a contract?
A
54
How does dispute resolution work in a contract you have experience of?
A
55
What is common law?
A
56
What do you understand by consideration in contract?
A
57
What do you understand by invitation to treat in contract?
A
58
How is the JCT form of contract structured?
A
59
How is the NEC form of contract typically structured?
A
60
What is the difference between a contract executed under seal and underhand?
A
61
When selecting a form of contract what factors do you consider?
A
62
What alternative forms of contract are there available and what would influence your recommendation of a form of contract?
A
63
Design and Build contracts - what are the 3 main forms of this contract?
A
64
Name 3 factors you think make this form of contract valid for your work?
A
65
Apart from JCT D&B what other forms of D&B contracts are there?
A
66
Have you ever considered a NEC D&B contract?
A
67
Within a JCT SBC when and why would you use a Schedule 2 quotation?
A
68
What are the timescales in a Schedule 2 quotation?
A
69
If the contractor on a D&B contract fails to issue the final account within the due period what action should you advise your client to take?
A
70
If you had to explain the differences to your client between sectional completion and partial possession can you provide an example of the differences under a JCT D&B contract?
A
71
How do sectional completion partial completion and beneficial use differ? Define each of the above.
A
72
If you client wanted to place furniture in the completed parts of a project which would you recommend sectional completion or partial possession?
A
73
What are liquidated damages?
A
74
What is your understanding of retention and bonds?
A
75
What is your understanding of early possession?
A
76
What contractual weight does a practical completion certificate carry in a JCT contract?
A
77
Tell me about some of the insurances a subcontractor would need if they were responsible for a part of the design work.
A
78
What do you understand by a parent company guarantee?
A
79
When might it be used?
A
80
What is your understanding of sectional completion?
A
81
What is your understanding of performance bond?
A
82
When might it be used?
A
83
What is you understanding of limitation of liability?
A
84
Talk me through how you’ve ensured insurances from subcontractors were at the correct level.
A
85
What do you understand by relevant event in a JCT form of contract?
A
86
What do you understand by compensation event in a NEC form of contract?
A
87
In the NEC form of contract talk me through five things that can lead to a compensation event.
A
88
In the NEC form of contract when can the completion date be adjusted?
A
89
In the NEC form of contract what is a defined cost?
A
90
In the NEC form of contract what is a disallowable cost?
A
91
When were changes to NEC4 last made?
A
92
What changes were made?
A
93
How are NEC contracts categorised by different alternative pricing options?
A
94
What are these pricing options?
A
95
How is BIM integrated in a contract you are familiar with? Explain Secondary Option X7.
A
96
What issue was raised by Triple Point Technology v PTT Public Co?
A
97
How was Secondary Option Y(UK)2 updated to reflect the judgement in Rochford Construction v Kilhan Construction?
A
98
How were Secondary Option X22 and Secondary Option Y(UK) 1 amended?
A
99
When are NEC compensation events not time barred?
A
100
In a NEC contract how would you detail if the contract is to be D&B?
A
101
What does the works information is included in a NEC contract?
A
102
What are the different types of FIDIC contract and how do they reflect different risk profiles?
A
103
What is your understanding of the difference between delay and disruption?
A
104
When does financial management of a project typically take place?
A
105
Explain what happens during the post contract phase.
A
106
How do you implement and manage cost control procedures and reporting within the scope of a contract?
A
107
What contract legislation are you aware of?
A
108
Explain how contracts may deal with contractor designed works.
A
109
Explain your understanding of contracts and sub-contracting.
A
110
What payments provisions and change procedures are you aware of?
A
111
What factors affect the choice of security in a contract?
A
112
What insurances are you aware of?
A
113
What is novation and assignment?
A
114
What is a collateral warranty?
A
115
What are the three ways that benefits can be transferred under JCT contracts?
A
116
Who might want a collateral warranty?
A
117
How are they requested?
A
118
What are the common clauses / terms in collateral warranties?
A
119
What is the difference between a bond and collateral warranty?
A
120
With any D&B contract there is a high probability that collateral warranties will apply where would you expect to see them and between which parties?
A
121
Are there any alternatives to collateral warranties?
A
122
Explain your understanding of retention.
A
123
What is the purpose of retention?
A
124
What items do not have retention taken on them?
A
125
Who receives the interest accruing on retention money?
A
126
When is the retention released to the contractor?
A
127
What if the contract sum increases?
A
128
Explain your understanding of liquidated and delay damages.
A
129
Explain your understanding of claims for extensions of time acceleration and loss and expense.
A
130
What is early possession?
A
131
Explain your understanding of phasing.
A
132
How can a contract be terminated?
A
133
Explain the impact of insolvency on contracts.
A
134
How do you deal with final accounts?
A
135
What is a pre-construction services agreement (PCSA)?
A
136
When are pre-construction services usually used?
A
137
What should be taken into account in the wording of a PCSA?
A
138
What might the pitfalls be?
A
139
When would you recommend the use of a PCSA?
A
140
How does a PCSA differ to a LOI?
A
141
Explain your understanding of defects and rectification.
A
142
How has Covid-19 affected a contract you have worked on?
A
143
Explain the differences between cost reimbursement and lump sum contracts.
A
144
Explain a key principle of the new RICS Guidance Note Subcontracting (1st Edition).
A
145
What is a subcontractor defined as within this?
A
146
What does the Guidance Note not cover?
A
147
If an architect develops a design to a certain stage and the appointed D&B contractor then wants to use the design and develop further what do they need to do? Explain in this scenario how copyright ownership works.
A
148
What is novation?
A
149
How does novation affect the employer’s rights?
A
150
What are the advantages of novation?
A
151
Are there any disadvantages of novation?
A
152
Do you have novation on traditional contracts?
A
153
What measures can be taken to effectively control costs during the construction phase of a project?
A
154
How can you control costs to keep a job under budget?
A
155
How do NEC and JCT manage change control?
A
156
Why is cash flow important?
A
157
How does a cash flow help a company remain solvent?
A
158
What is risk allocation?
A
159
What do you understand by risk management?
A
160
What is a risk management strategy?
A
161
What are the benefits of risk management?
A
162
What are the stages of risk management?
A
163
Why is risk management needed in construction?
A