Contract administration Flashcards

1
Q

Why is adjudication always included in a JCT contract, while arbitration is optional?

A

Statutory adjudication is a mandatory right under ‘construction contracts’, as defined in the Construction Act 1996

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a “lump sum” contract?

A

Fixed total price for entire project (like JCT)
For straightforward projects with clear scope of works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a “Time and materials” contract?

A

Contractors are reimbursed for cost and materials, and labour time at established rate.
For rojects without well-defined works scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a “relevant event”?

A

delay that is NOT fault of contractor, eg. “client in control” or “neutral event (noones fault).
Does not necessarily allow contractor to claim for Loss and Expense (neutral events do not allow this - exceptional weather, civil commotion)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a “relevant matter”?

A

Client’s fault. Contractor could claim for Loss and Expense.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Give examples of when a contractor may be entitled to loss and expense claim.

A

“Client in control” - failure to provide access, information, decisions, delay of named subcontractor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the limitations of the JCT MW16 contract?

A

Its brevity – can be silent on some matters.
Doesn’t allow for named subcontractors.
No Bills of Quantities.
Suitable for relatively simple works only.
Simplicity means amendments sometimes required.
Roles can become a bit blurred.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a “traditional” procurement route?

A

Linear path - employer engages designers first, then contractor to build works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is a “design and build” procurement route?

A

Contractor designs and builds the works. “one stop shop”
No CA, only “employers agent” (more aligned to the client)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a “management forms” procurement route?

A

Client employs different subcontractors directly, there is a main contractor but no contractual relationship between them and client (management contractor).
Most risk lies with employer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are pros and cons of “standard contracts”?

A

Pros:
Recognised in industry
Familiarity with all
Clarity of content
Written by experts
Complies with laws

Cons:
Not always “robust” enough for employer
Not necessarily easy to understand for first-time employers
Require amendments for bespoke additions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are pros and cons of “bespoke contracts”?

A

Heavily weighted in favour of employer
Contractor prices higher due to risks
May contain onerous T&Cs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a “letter of intent”?

A

“partial contract” effectively - simple statement of intent, not binding on either party.
Allows contractor to start work quickly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When is a PC certificate issued?

A

When “‘the client is physically able to take occupation of the
works and use them for their intended purpose” (RICS Black Book definition)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What happens at PC?

A

Employer must insure building, takes possession
Half retention release
Defect rectification period begins
LDs cannot be taken

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the “critical path”?

A

Path of the project from start to completion, assuming no delays

17
Q

Give examples of what is typically included in “preliminaries” costs.

A

Site huts, welfare, hire
Cranes, scaffold
Power and water
Temp electrics
Site management

18
Q

What are “dayworks”?

A

Contractor paid for specifically instructed work on the basis of the cost of labour, materials and plant plus OHP.
Generally used when work cannot be priced by measurement.

19
Q

What are “preambles” in a contract?

A

An explanation of the document/contract

20
Q

What is a collateral warranty?

A

A “warranty” of sorts provided by one party to another, whom it has no contractual relationship, that it has carried out its works correctly.

21
Q

Under what grounds could a JCT contract be terminated, by either side?

A
  • Default (fails to perform contractual obligations) of contractor. EG, fails to proceed regularly or diligently
  • Default by employer, eg. does not pay when due, obstructs certificates, one-month suspension due to variations
  • Insolvency of contractor/employer
  • Contractor/employer fails to comply with CDM
22
Q

How would a JCT contract be terminated?

A

Termination notices posted (recorded/special delivery), or by hand.
Time periods in the contract must be observed.