Contract administration Flashcards
Why is adjudication always included in a JCT contract, while arbitration is optional?
Statutory adjudication is a mandatory right under ‘construction contracts’, as defined in the Construction Act 1996
What is a “lump sum” contract?
Fixed total price for entire project (like JCT)
For straightforward projects with clear scope of works
What is a “Time and materials” contract?
Contractors are reimbursed for cost and materials, and labour time at established rate.
For rojects without well-defined works scope
What is a “relevant event”?
delay that is NOT fault of contractor, eg. “client in control” or “neutral event (noones fault).
Does not necessarily allow contractor to claim for Loss and Expense (neutral events do not allow this - exceptional weather, civil commotion)
What is a “relevant matter”?
Client’s fault. Contractor could claim for Loss and Expense.
Give examples of when a contractor may be entitled to loss and expense claim.
“Client in control” - failure to provide access, information, decisions, delay of named subcontractor.
What are the limitations of the JCT MW16 contract?
Its brevity – can be silent on some matters.
Doesn’t allow for named subcontractors.
No Bills of Quantities.
Suitable for relatively simple works only.
Simplicity means amendments sometimes required.
Roles can become a bit blurred.
What is a “traditional” procurement route?
Linear path - employer engages designers first, then contractor to build works
What is a “design and build” procurement route?
Contractor designs and builds the works. “one stop shop”
No CA, only “employers agent” (more aligned to the client)
What is a “management forms” procurement route?
Client employs different subcontractors directly, there is a main contractor but no contractual relationship between them and client (management contractor).
Most risk lies with employer
What are pros and cons of “standard contracts”?
Pros:
Recognised in industry
Familiarity with all
Clarity of content
Written by experts
Complies with laws
Cons:
Not always “robust” enough for employer
Not necessarily easy to understand for first-time employers
Require amendments for bespoke additions
What are pros and cons of “bespoke contracts”?
Heavily weighted in favour of employer
Contractor prices higher due to risks
May contain onerous T&Cs
What is a “letter of intent”?
“partial contract” effectively - simple statement of intent, not binding on either party.
Allows contractor to start work quickly
When is a PC certificate issued?
When “‘the client is physically able to take occupation of the
works and use them for their intended purpose” (RICS Black Book definition)
What happens at PC?
Employer must insure building, takes possession
Half retention release
Defect rectification period begins
LDs cannot be taken