Contract Admin Flashcards
What is the role of a Contract Administrator?
- Execution of the Construction Contract
- The CA is not a party to the main contract and must remain impartial.
- They have a duty to deliver the project safely, to the specified quality standards, on time, and with in budget.
What are the main responsibilities of the CA?
-Administer the Contract
- Chair meetings
-Report to the client
- Issue certificates under the contract (e.g Extention of time, PC, Non completion)
- Authorise payment
- Give contract instructions
-
What is a Letters of Intent?
A letter of intent is a method of instructing a contractor to proceed with the works before formal execution of the contract.
Why might a LOT be used?
- Where the employer needs to commence works ungently
- To carry out emergency works (i.e dismantling dangerous structures, environmental cleaning, removal of hazardous materials
- It gives parties time to negotiate the contract terms with disrupting the programme
What would be included in an LOI
- The contract parties
- Scope of works
- Contract price (if agreed)
- Key dates
- Statement of intention to enter into a formal contract
What is a pro and con of using a LOI?
Pros - It creates a moral commitment to parties involved and alleviates programme constraints
Cons- Can be a complicated legal situation and can be a risk to both parties
What would you include within tender documents?
- Form of Tender
- Non Collusion Certificate
- Preliminaries (i.e contract details, incl parties, project, site description etc.
- Preambles (Materials and workmanship clauses)
- Specifications (Schedule of works, Drawings)
- Pre- construction information
What are the main certificates under JCT Forms of Contract?
- Payment Certificates
- Partial Possession/ Sectional Completion
- Practical completion
- Certificate of Non Completion
- Certificate of Making good defects
What are the main certificates under JCT Forms of Contract?
- Payment Certificates
- Partial Possession/ Sectional Completion
- Practical completion
- Certificate of Non Completion
- Certificate of Making good defects
What are the main forms of Contract in the JCT Suite?
- Minor Works
- Standard Building
- Intermediate
- Design and Build
- Major Project
- Management Building (MB
- Construction Management
What are dispute resolutions available under the JCT Suite of Contract?
- Adjudication ( Third party decides the case (e.g TeSCA).
- Arbitration (Legally binding)
What are the differences between JCT Minor Works and Intermediate?
Express provisions for:
- Named sub-contractor
- Collateral Warranties
- Sectional Completion/ partial possession
- Performance bonds
What procedure take place one the rectification period ends?
- The CA prepares a Schedule of Defects, listing defects that have not been rectified
- Agrees a date with the contractor to which they are made good.
- Issue a Certificate of making good defects, releasing any remaining retention.
When would you issue PC and what happens one issued?
- When works are complete to an extent that the client can safely take occupation
- O&Ms have been issued
- All certificates, guarantees have been issued.
Why would you use a JCT minor works contract?
- The project is small and simple in nature
- Suitable for traditional or conventional procurement.
- Detailed procedures such as named subcontractors are not necessary